Marana Unified School District No. 6 v. Aetna Casualty & Surety Co.

696 P.2d 711, 144 Ariz. 159, 1984 Ariz. App. LEXIS 602
CourtCourt of Appeals of Arizona
DecidedDecember 3, 1984
Docket2 CA-CIV 5139
StatusPublished
Cited by8 cases

This text of 696 P.2d 711 (Marana Unified School District No. 6 v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marana Unified School District No. 6 v. Aetna Casualty & Surety Co., 696 P.2d 711, 144 Ariz. 159, 1984 Ariz. App. LEXIS 602 (Ark. Ct. App. 1984).

Opinion

OPINION

BIRDSALL, Chief Judge.

This appeal arises from a complaint filed by the appellee, Maraña Unified School District, seeking judgment on a bid bond given by appellants, L.G. Lefler, Inc., doing business as Defco Construction Company, principal, and the Aetna Casualty and Surety Company, surety. The bond was provided pursuant to A.R.S. § 34-201(A)(3) because Defco submitted a bid proposal to construct a junior high school building for the appellee. The statute provides:

3. That every proposal shall be accompanied by a certified check, cashier’s check or a surety bond for five per cent of the amount of the bid included in the proposal as a guarantee that the contractor will enter into a contract to perform the proposal in accordance with the plans and specifications, or as liquidated damages in event of failure or refusal of the contractor to enter into the contract. The certified check, cashier’s check or surety bond shall be returned to the contractors whose proposals are not accepted, and to the successful contractor upon the execution of a satisfactory bond and contract as provided in this article.

Although Defco was the low bidder, it refused to enter into a contract with the appellee because it had made a mathematical mistake in its proposal.

The trial court entered summary judgment in favor of the Maraña District in the amount of $270,662.50, that being five per cent of Defco’s base bid plus alternates together with costs and attorney fees. 1 The appellants’ cross-motion for summary judgment was denied.

The facts considered in the light most favorable to the appellants may be summarized as follows. The appellee gave notice *161 of its intent to receive sealed bids for the construction of the school pursuant to A.R.S. § 34-201. The bids were required to be submitted by 4 p.m., February 2, 1982, at which time they were opened. The appellant’s bid was for $4,890,000 together with alternates, all of which totalled $5,936,500. The bid bond attached to the proposal was “in the sum of five per cent of contract bid.” No actual figures were set forth on the bond but the proposal referred to the required bid bond amount as five per cent of the “base bid” which would have been $244,500. Nine other contractors submitted bids. Defco’s was the lowest base bid. The next lowest base bid was $5,447,000. The architect’s estimated cost for the construction without alternates was $4,900,000. Defco’s bid was within two-tenths of one per cent of that estimate.

After all bids were opened, the architect and school district officials reviewed them and a written recommendation was made that day to accept Defco’s base bid together with two alternates totalling $5,253,080.

At about the same time, Defco personnel were recheeking their figures since it appeared that a mistake may have been made. The employee who had tabulated Defco’s bid sheet then discovered that she had used $42,000 as the bid for the structural steel when the correct figure was $412,000, a mistake of $370,000.

According to the employee’s affidavit attached to the appellants’ cross-motion for summary judgment, she was still receiving telephone bids from subcontractors and suppliers and working on Defco’s bid up until 3:30 on February 2; she found a mistake in her first tabulation of some 170 items on the bid sheet and did a second tabulation, then added the figures six times. Since this brought her so close to the time the bid had to be submitted, there was no time to have another employee check her figures.

Defco advised appellee by telephone within one and one-half hours of the bid opening of the mistake which came to $398,752 with the addition of other items based on percentages of the $370,000 error. A letter containing the same information was delivered to the school within three hours after the bid was opened at 4 p.m. In the letter Defco asked to meet with the school officials to show them the calculator tapes and bid sheet which revealed how the error had occurred.

The school board held a special meeting at 7:30 that evening, February 2, receiving the report and recommendation of the architect and the letter from Defco. Apparently because of the latter, they deferred consideration of the bids and the school superintendent was instructed to consult with legal counsel.

A second special meeting of the board was held on February 4 with Mr. Lefler from Defco present. Pursuant to a motion passed by the board, the president asked Lefler if Defco was prepared to perform the contract if awarded under Defco’s original low base bid. Lefler answered no, whereupon the board passed a motion that “the board reject all bids received on February 2 and instruct the architect to prepare to re-bid the construction contract____”

There is no conflict in any of the foregoing facts. Other facts will be discussed as necessary in relation to the issues.

The important issue presented by this appeal is whether a low bidder for a public contract may refuse to enter into a contract because of a mistake in the bid without forfeiting the bid bond. Although this question has never been decided in Arizona, it has been the subject of numerous opinions in our sister states and federal courts. For a recent compilation and discussion of these cases see the annotation in 2 ALR4th 991, “Right of bidder for state or municipal contract to rescind bid on ground that bid was based upon his own mistake or that of his employee.”

Before discussing this issue, which we believe to be dispositive, we reject certain other contentions made by the appellants.

The appellants contend first that the school board never offered a contract to Defco and that it rejected all bids includ *162 ing Defco’s. We disagree. The only evidence is that the school board at its meeting on February 4 asked the Defco officer whether Defco would perform if the contract were awarded for the low base bid. The answer was an unequivocal no. Nothing more should be required. There is no room for any doubt. Defco refused to enter into the contract. It is also abundantly clear that the bids were not rejected until after this refusal. The appellants’ contention that this action released the bid bond is without merit. Likewise we reject the argument that the action of the board rejecting the bids constituted a mutual rescission of the Defco bid bond contract. No weighing of the evidence is required. It is impossible to make any inference other than that the appellee offered the contract and the appellant refused.

Thus we must consider the controlling question — whether Defco’s refusal to enter into a contract because of the mistake in the bid must result in the forfeiture of the bid bond.

It is the appellee’s position that the statute permits no escape from forfeiture. There is authority to support such a result. These decisions are cited by the appellants: Board of Edn. v. Sever-Williams Co., 22 Ohio St.2d 107, 258 N.E.2d 605, cert. denied, 400 U.S. 916, 91 S.Ct. 175, 27 L.Ed.2d 155 (1970), and A.J. Colella, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Cape & Sons Co. v. Mulcahy
2005 WI 128 (Wisconsin Supreme Court, 2005)
Blankenbaker v. Jonovich
71 P.3d 910 (Arizona Supreme Court, 2003)
J.D. Graham Construction Inc. v. Pryor Public Schools Independent School District No. 1
1993 OK CIV APP 44 (Court of Civil Appeals of Oklahoma, 1993)
National Fire Insurance v. Brown & Martin Co.
726 F. Supp. 1036 (D. South Carolina, 1989)
Hill-Shafer Partnership v. Chilson Family Trust
784 P.2d 691 (Court of Appeals of Arizona, 1989)
Powder Horn Constructors, Inc. v. City of Florence
754 P.2d 356 (Supreme Court of Colorado, 1988)
City of Florence v. Powder Horn Constructors, Inc.
716 P.2d 143 (Colorado Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
696 P.2d 711, 144 Ariz. 159, 1984 Ariz. App. LEXIS 602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marana-unified-school-district-no-6-v-aetna-casualty-surety-co-arizctapp-1984.