Osberg Construction Co. v. City of the Dalles

300 F. Supp. 442, 1969 U.S. Dist. LEXIS 8420
CourtDistrict Court, D. Oregon
DecidedMay 22, 1969
DocketCiv. 67-526
StatusPublished
Cited by5 cases

This text of 300 F. Supp. 442 (Osberg Construction Co. v. City of the Dalles) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Osberg Construction Co. v. City of the Dalles, 300 F. Supp. 442, 1969 U.S. Dist. LEXIS 8420 (D. Or. 1969).

Opinion

OPINION

KILKENNY, District Judge:

The plaintiff, Osberg Construction Company (Osberg), submitted, along with its bid on a contract to be let by the defendant,- City of The Dalles (City), a bid bond in the sum of $24,998.75. According to the Information to Bidders f[ 8 of the Contract Documents for the contract, that bond would be forfeited as liquidated damages in the event that the bidder was awarded the contract and failed to accept within 10 days. The City awarded the contract to Osberg based on Osberg’s original bid, even though the latter notified the City of certain alleged mistakes in the preparation of the bid. When Osberg refused to execute the awarded contract, the City forfeited the bid bond.

In this suit, Osberg seeks a decree ordering the City to return the $24,998.-75 bid bond, restraining the City from any act directed toward realization on the bid bond, and costs. Jurisdiction is based on 28 U.S.C. § 1332.

The contract was to be let by the City for the construction of the Crow Creek Dam. The City’s original project budget was $455,000.00 for the work and material covered by the contract. This was based on an estimate of independent engineers. In August, 1967, however, the City received a revised estimate which raised the amount to $655,520.00.

Osberg is a general contractor, resident in Seattle, Washington. At the time of the letting of the Crow Creek Contract, Osberg had just completed or was still working on sizeable projects in Oregon, Washington and Alaska. Bidding on the Crow Creek Project was handled for Osberg by John W. Osberg, the Company’s Vice-President and Assistant Secretary. On August 30, 3 967, along with other bidders, he toured the jobsite. The closing time for submitting bids or for modifying or withdrawing bids already submitted was 10:00 A.M., September 14, 1967, at The Dalles. This was also the time for the opening of the bids.

Osberg received an addendum to the contract documents, dated September 6, 1967, on the 7th or 8th of September, 1967. It was over the following weekend, on September 9th or 10th, that John Os-berg prepared the Crow Creek bid. He *444 thinks he mailed it on September 11th, a Monday. Then, on the 14th, he “felt a restless apprehension” that he had neglected to provide for the contingency that the stream, which would have to be temporarily diverted, could not be channeled through a 30-ineh concrete pipe which was to be a permanent part of the dam installation. At that time, he “realized” that the addition of a temporary diversion dam and a 48-inch pipeline would be necessary in order to safeguard against the danger of having the construction works washed out. His apprehension over flooding, he says, caused him to review his bid. In that review, he found what he classes as other errors: (1) Under item 2A1 (Move In, Construct Temporary Facility), that he had “extended” no figure for road construction; aiid (2) Under item 2D8 (Rock Excavation of Spillway) that he had similarly failed to “extend any figure” to cover the necessary drilling and shooting.

Osberg’s original bid totaled $499,975.-00. The bid of his next lowest competitor was $574,352.00, a difference of about $75,000.00. The third, fourth and fifth next lowest totaled $635,021.00, $682,-035.00 and $687,662.50, respectively.

Osberg, upon discovering his alleged mistake, attempted to modify his bid before the bids were opened by sending a telegram to the Office of the Mayor, City of The Dalles, sent at 9:45 A.M. of the 14th. By that telegram, Osberg attempted to “raise Item 2A2 Divert and Care for Water one hundred thousand dollars raise item 2D8 Rock Excavation of Spillway .50 per cubic yard total bid increase one hundred twenty five thousand dollars”. About 11:15 A.M. on that same day, Osberg telephoned the City Manager of The Dalles to the effect that the bid was erroneous and should be increased by $125,000.00.

The Contract Documents for the Crow Creek Dam provided that telegraphic modification (the only type allowed) could be effective only if:

“ * * * such telegraphic communication is received by the Owner prior to the closing time, and, provided further, the Owner is satisfied that a written confirmation of the telegraphic modification over the signature of the bidder was mailed prior to the closing time.”

Id. Information to Bidders, p. 2.

Osberg’s telegram did not reach the defendant until 11:20 A.M. when The Dalles office of Western Union telephoned the telegraphic message to the secretary of the City Manager of the City of The Dalles. Thus, according to the announced rules governing the bidding, the attempted modification was technically too late.

The Contract Documents provided that bids could be withdrawn prior to the time for the opening. But, if not so withdrawn, the bidder would not be able to withdraw his bid any time “within thirty days of the actual date of opening thereof.” Osberg’s first attempt to withdraw his bid came in a letter dated September 18, 1967, asking that his bid be increased or, in the alternative, withdrawn.

The information for bidders in the Contract Documents made Osberg’s offer irrevocable for the thirty days following September 14, 1967. By resolution of September 18, 1967, the City of The Dalles awarded Osberg the contract for the construction of the Crow Creek Dam, thus accepting that offer. When Osberg refused to execute the contract sent by City of The Dalles, the City claimed the $24,998.75 bid bond was forfeited according to the plain wording of the terms of the Contract Documents.

Plaintiffs concede the validity of the contractual provisions with reference to forfeiture, but would void those provisions by reason of alleged mistakes in fact on the submission of the bid. They rely chiefly on Rushlight Automatic Sprinkler Co. v. City of Portland, 189 Or. 194, 219 P.2d 732 (1950) and State Highway Commission v. State Construction Co., 203 Or. 414, 280 P.2d 370, 52 A.L.R. 2d 779 (1955). My problem is to decide whether mistakes of fact, rather than mistakes in judgment, were involved. To be kept in mind is the important fact that John W. Osberg toured the jobsite along with all of the other bidders prior *445 to the time he compiled the bid which was submitted by his company. I shall now deal with the claimed mistakes.

The distinction between a mistake of fact and a mistake of judgment is well delineated in M. F. Kemper Construction Co. v. City of Los Angeles, 37 Cal.2d 696, 235 P.2d 7 (1951), where it is held that relief is refused for an error in judgment and allowed only for clerical or mathematical mistakes. In other words, mistakes in fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dunkin' Donuts of America, Inc. v. Middletown Donut Corp.
495 A.2d 66 (Supreme Court of New Jersey, 1985)
Marana Unified School District No. 6 v. Aetna Casualty & Surety Co.
696 P.2d 711 (Court of Appeals of Arizona, 1984)
R. J. Taggart, Inc. v. Douglas County
572 P.2d 1050 (Court of Appeals of Oregon, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
300 F. Supp. 442, 1969 U.S. Dist. LEXIS 8420, Counsel Stack Legal Research, https://law.counselstack.com/opinion/osberg-construction-co-v-city-of-the-dalles-ord-1969.