J.D. Graham Construction Inc. v. Pryor Public Schools Independent School District No. 1

1993 OK CIV APP 44, 854 P.2d 917, 64 O.B.A.J. 2016, 1993 Okla. Civ. App. LEXIS 71, 1993 WL 217891
CourtCourt of Civil Appeals of Oklahoma
DecidedMarch 9, 1993
Docket79296
StatusPublished
Cited by2 cases

This text of 1993 OK CIV APP 44 (J.D. Graham Construction Inc. v. Pryor Public Schools Independent School District No. 1) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.D. Graham Construction Inc. v. Pryor Public Schools Independent School District No. 1, 1993 OK CIV APP 44, 854 P.2d 917, 64 O.B.A.J. 2016, 1993 Okla. Civ. App. LEXIS 71, 1993 WL 217891 (Okla. Ct. App. 1993).

Opinion

MEMORANDUM OPINION

ADAMS, Presiding Judge:

J.D. Graham Construction Incorporated (Graham) and Mid-Continent Casualty Company, Graham’s bid bond issuer, appeal a trial court judgment in favor of Appellee in this dispute arising under the Public Competitive Bidding Act of 1974 (Act), 61 O.S.1991 101 et seq. Because we agree forfeiture of the bid bond was mandatory under the facts presented by this record, we affirm.

FACTS

The facts in this case are undisputed. 1 Graham responded to an advertised solicitation for prime contracts bids for renovation of six school buildings located in Independent School District No. 1, Mayes County (School). Prior to the scheduled opening of the bids on August 15, 1991, at 2:00 p.m., Graham began soliciting the necessary bids for materials and subcontracts required to complete the project according to School’s specifications and plans.

*919 According to the uncontroverted evidence, it is standard practice in the construction industry for subcontractors and suppliers to frequently delay providing their final lowest prices and bids to the prime contractor until minutes before the prime contract bid must be submitted. With this in mind, Graham stationed one of its associates near the bid submission site to receive from the office by telephone the final base and alternate bid figures for incorporation into the formal bidding documents to be submitted to School. In a “flurry of activity” just minutes before the bid submission deadline, Graham’s president mistakenly relayed to a person in the office an air conditioning subcontractor’s bid as $45,000 instead of the actual bid of $145,000. This wrong information was transmitted to the associate at the bid submission site and used in computing Graham’s total bid.

When the bids were opened and read publicly, Graham was the low bidder. After learning this, Graham’s president and its secretary/treasurer checked the bid figures and discovered the $100,000 error. School’s architect was immediately informed of the error by telephone, and the next day Graham’s president wrote and delivered a letter to School advising of the error and requesting Graham’s bid be withdrawn and its bid bond released. On August 19,1991, Graham's president appeared before the school board to explain the calculation error and again requested to withdraw its bid. On August 27, 1991, Graham was advised that School had awarded it the renovation contract.

Graham and its surety, Mid-Continent Casualty Company (Mid-Continent), sued, requesting a judicial determination that all obligations arising from Graham’s bid and the bid bond were discharged and exonerated by virtue of Graham’s unilateral mistake. They also sought an order compelling School to return the bid bond. Graham and Mid-Continent moved for summary judgment, attaching relevant eviden-tiary materials. School responded, disputed none of the facts stated in Graham’s motion, and asked for summary judgment in its favor. The trial court held the Act required forfeiture of Graham’s bid bond and entered judgment for School for the difference between Graham’s bid and the next highest bidder. Graham and Mid-Continent appeal.

ANALYSIS

Graham argues forfeiture was not required for two reasons. First, Graham claims it was not the “apparently successful bidder” as that term is used in § 107 of the act, and therefore did not forfeit its bond by failing to execute a contract. Second, Graham argues the trial court retained the equitable power to excuse Graham’s unilateral mistake under these circumstances. We address these arguments in the order stated.

Section 107(A) of the Act requires each bidder on a public construction contract to accompany the bid with a certified check, cashier’s check, bid bond, or irrevocable letter of credit in the amount of five percent of the bid. Section 107(B) provides for forfeiture of that security as follows:

The cost of republication of the notice to bidders, all actual expenses incurred by reason of the bidder’s default and the difference between the low bid of the defaulting bidder and the amount of the bid of the bidder to whom the contract is subsequently awarded, but not to exceed the amount of the certified check, cashier’s check, bid bond or irrevocable letter of credit shall be forfeited to the awarding public agency in the event the apparently successful bidder fails to execute the contract or fails to provide the required bonds or irrevocable letters of credit and insurance to the awarding public agency. [Emphasis added]

According to Graham’s argument, “apparently successful bidder” means the bidder to whom the “awarding public agency” awards the contract. Because Graham advised School of the error in its bid and asked to withdraw its bid before the School awarded the contract, Graham claims it was not the “apparently successful bidder” and forfeiture is not required by this section.

*920 The primary goal of statutory construction is to follow the legislative intent, and in doing so this court must presume the Legislature expressed its intent in a statute and intended what it expressed. Ledbetter v. Oklahoma Alcoholic Bev. Laws Enforcement Comm’n, 764 P.2d 172 (Okl.1988); Land v. Transport Indem. Co., 791 P.2d 118 (Okl.App.1990). Where possible, all relevant portions of a statute and related enactments will be considered together to give force and effect to all of them. Clifton v. Clifton, 801 P.2d 693 (Okl.1990). Statutes should be read so as to render every word in a sentence operative, rather than in a manner which would make a statutory provision nugatory. Burris v. State ex rel. Dept. of Public Safety, 785 P.2d 332 (Okl.App.1989).

Graham correctly argues that the Act does not require an award to the lowest bidder but to the lowest responsible bidder, which in all cases is not necessarily the bidder having the lowest bid. 61 O.S.1991 § 103; Rollings Const. Inc. v. Tulsa Metro. Water Auth., 745 P.2d 1176 (Okl.1987). Graham argues a bid cannot be determined to be both lowest and responsible, and therefore “apparently successful”, until the public agency has taken action on the bid.

Graham’s argument overlooks the legislative treatment of the bidder who is awarded the contract. In § 113 that bidder is referred to as “the successful bidder.” Further, Graham’s interpretation robs the word “apparently” of any meaning. In the absence of specific definitions, this court must assume the Legislature intended for words to have the same meaning as that attributed to them in ordinary and usual parlance. Loffland Bros. Equipment v. White, 689 P.2d 311 (Okl.1984). “Apparently” is defined as “in an apparent manner: seemingly, evidently.” Webster’s Third New International Dictionary, 103. A bidder who has been awarded the contract is not “apparently” or “seemingly” successful. Such a bidder has in fact succeeded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanford v. Anadarko Petroleum Corp.
2001 OK CIV APP 90 (Court of Civil Appeals of Oklahoma, 2001)
Leake Estate v. Oklahoma Tax Commission
891 P.2d 1299 (Court of Civil Appeals of Oklahoma, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
1993 OK CIV APP 44, 854 P.2d 917, 64 O.B.A.J. 2016, 1993 Okla. Civ. App. LEXIS 71, 1993 WL 217891, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jd-graham-construction-inc-v-pryor-public-schools-independent-school-oklacivapp-1993.