Carr-Gottstein Properties, Ltd. Partnership v. Benedict

72 P.3d 308, 2003 Alas. LEXIS 57, 2003 WL 21419020
CourtAlaska Supreme Court
DecidedJune 20, 2003
DocketS-10579
StatusPublished
Cited by9 cases

This text of 72 P.3d 308 (Carr-Gottstein Properties, Ltd. Partnership v. Benedict) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carr-Gottstein Properties, Ltd. Partnership v. Benedict, 72 P.3d 308, 2003 Alas. LEXIS 57, 2003 WL 21419020 (Ala. 2003).

Opinion

OPINION

FABE, Chief Justice.

I. INTRODUCTION

A lot owner violated a covenant in her subdivision by taking more than one year to finish construction on her lot. The covenant contained a flat-rate, per diem liquidated damages provision for covenant violations. The issue presented by this appeal is whether flat-rate, per diem liquidated damages can be charged for construction delays that vio *310 late subdivision covenant regulations. We reverse the superior court and hold that such a clause is permissible in this case because the developer's liquidated damages clause attempts to address a situation where it would be difficult to ascertain actual damages or to reasonably forecast the damages likely to oceur in the event of breach.

II. FACTS AND PROCEEDINGS

Carr-Gottstein Properties developed the Southport Subdivision Addition No. 1 in Anchorage. Carr-Gottstein executed a Declaration of Covenants, Conditions and Restrictions (CC & R) that regulates the use of lots within the subdivision. One covenant in the CC & R requires owners of lots within the subdivision to complete any construction of a dwelling within one year. 1 A purpose of this one-year covenant is to protect the aesthetics of the subdivision. The CC & R contains a liquidated damages clause that provides a $25 daily fine for any violation of the CC & R.

Ruth Benedict owned Lot 15, Block 4 in the Southport Subdivision Addition No. 1 (Lot 15). On September 20, 1999, Benedict began construction on her lot. On October 31, 2000, Carr-Gottstein gave Benedict written notice that Benedict was in violation of the one-year construction limitation covenant.

Carr-Gottstein filed suit to require completion of the construction and for assessment of liquidated damages. Carr Gottstein moved for partial summary judgment on the question whether Benedict was in compliance with the covenant. Benedict opposed Carr-Gottstein's motion and filed a eross-motion for summary judgment challenging the validity of the liquidated damages provision. The trial court granted both motions for summary judgment, finding that Benedict was not in compliance with the covenant but also that the CC & R's liquidated damages clause was impermissible because of our ruling in Kalenka v. Taylor 2 Carr-Gottstein now appeals the granting of Benedict's motion for summary judgment. 3

III. STANDARD OF REVIEW

The general enforceability of flat-rate per diem liquidated damages clauses is a question of law. Whether a particular liquidated damages clause is validly applied is a mixed question of law and fact. 4 What legal test a court should apply in determining the validity of a liquidated damages clause is a legal issue 5 Whether facts in a particular case meet the proper liquidated damages test is a factual determination. For questions of law, the standard of review is de novo; we adopt the rule of law that is most persuasive in light of precedent, reason, and policy. 6 We review a court's factual determinations under the clearly erroneous standard. 7

IV. DISCUSSION

Generally, parties to a contract are free to stipulate in advance an amount "to be paid as compensation for loss or injury which may result in the event of a breach of the contract, and such stipulations are valid and enforceable." 8 However, such an advance stipulation may only provide compensation *311 for breach of the contract and may not serve as a penalty that punishes the breaching party. 9 Contractual penalties serve no positive purpose, which is why courts do not enforce them. 10 Courts must determine on a case-by-case basis whether a damages provision is a valid liquidated damages clause or an unenforceable penalty. 11

We 'have instructed trial courts to employ a two-step test in making their determinations regarding the validity of liquidated damages clauses: "Liquidated damages clauses are proper ... where 'it would be difficult to ascertain actual damages," and where the liquidated amount [is] 'a reasonable forecast of the damages likely to occur in the event of breach." "* 12 The Restatement of Contracts uses this widely adopted test. 13

- Carr-Gottstein's liquidated damages clause meets the first part of our test. The liquidated damages. clause in question is meant to address the aesthetic harm caused by delays in construction. In its summary judgment decision, the superior court found that "the damages caused by [Benedict's] breach are of an aesthetic nature which result in damages that are difficult to quantify, but which nonetheless require a remedial response[.]" Moreover, it is generally accepted that injuries caused by construction delays are "nearly always difficult to determine...." 14 - Carr-Gottstein's _- liquidated damages provision thus meets the first requirement of our liquidated damages test.

Carr-Gottstein's clause also meets the see-ond part of our test, as a $25 daily fine is "a reasonable forecast of the damages" likely to occur as a result of this covenant breach. First, because "injury caused by [construction] delay is nearly always difficult to determine," courts are strongly inclined to accept and enforce an amount agreed to in a liquidated damages provision for construction delay. 15 Furthermore, the per diem liquidated damages provision takes into account the magnitude of the breach because the temporal length of the breach in this situation affects the magnitude of the breach. One purpose of the one-year limitation on construction is protection of the subdivision's aesthetics. Lots with unfinished construction often contain work equipment, displaced earth, unfinished edifices, and other unpleasant sights. Such aesthetic blight harms the sale value of other lots within the subdivision and hampers the other lot owners' enjoyment of their property. Each additional day of unfinished construction prolongs this harm, and its magnitude, therefore, is correlated to its temporal length. In setting a per diem fee, Carr-Gottstein's liquidated damages provision attempts to reasonably forecast damages by assigning different damages to breaches of different magnitudes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake & Peninsula Borough Assembly v. Oberlatz
329 P.3d 214 (Alaska Supreme Court, 2014)
Jones v. Bowie Industries, Inc.
282 P.3d 316 (Alaska Supreme Court, 2012)
Shooshanian v. Dire
237 P.3d 618 (Alaska Supreme Court, 2010)
Dominic Wenzell, D.M.D. P.C. v. Ingrim
228 P.3d 103 (Alaska Supreme Court, 2010)
Estate of Maldonado v. Bailey
117 P.3d 720 (Alaska Supreme Court, 2005)
Soules v. Ramstack
95 P.3d 933 (Alaska Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
72 P.3d 308, 2003 Alas. LEXIS 57, 2003 WL 21419020, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carr-gottstein-properties-ltd-partnership-v-benedict-alaska-2003.