Board of County Commissioners v. City & County of Denver

40 P.3d 25, 2001 Colo. J. C.A.R. 1606, 2001 Colo. App. LEXIS 564, 2001 WL 301132
CourtColorado Court of Appeals
DecidedMarch 29, 2001
Docket00CA0217
StatusPublished
Cited by11 cases

This text of 40 P.3d 25 (Board of County Commissioners v. City & County of Denver) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of County Commissioners v. City & County of Denver, 40 P.3d 25, 2001 Colo. J. C.A.R. 1606, 2001 Colo. App. LEXIS 564, 2001 WL 301132 (Colo. Ct. App. 2001).

Opinion

Opinion by

Chief Judge HUME.

In this breach of contract action, defendant, the City and County of Denver (Denver), appeals the trial court's award of contractual damages to plaintiffs, Board of County Commissioners of Adams County (Adams), City of Aurora, City of Brighton, City of Commerce City, and City of Thornton, based on excessive noise levels at the Denver International Airport (DIA). We affirm. -

This dispute arises out of an Intergovernmental Agreement (IGA) entered into on April 21, 1988, between Denver and Adams (the parties). The named cities are third-party beneficiaries of the IGA. When the parties began negotiations, Denver needed a new airport, but did not have enough land to build one. Plaintiffs originally sought to build a multijurisdictional airport, in which they would share authority with Denver. Denver, however, insisted on retaining sole ownership and control of the new airport and focused on annexing land from Adams. In response, Adams sought to negotiate an agreement that would address its primary concern regarding the noise impact a new airport would have on Adams and its cities.

Under the IGA, Denver promised to operate DIA within maximum noise levels called noise exposure performance standards (NEPS). Denver agreed that if these noise levels were exceeded and not cured as provided by the IGA, then Denver would compensate plaintiffs with noise mitigation payments.

Two types of NEPS are defined in the contract: the Leq(24) grid points and the 65 Ldn noise contour line. The Leq(24) is comprised of 101 grid points on the north, west, and south sides of DIA. If a grid point's actual noise level is greater than its particular standard, a Leg(24) violation occurs. The 65 Ldn noise contour line loosely traces DIA's runway configuration with protrusions on each side of the compass. A 65 Ldn violation occurs where the actual 65 Ldn noise level occurs on land beyond the contour line boundary.

DIA opened in 1995, and noise problems followed soon after. Denver violated the Leg(24) grid points fifty-six times and exceeded the 65 Ldn contour in six places during the first year. Seven of the Leq(24) violations were not cured in the second year, and plaintiffs brought suit in accordance with the IGA.

Both plaintiffs and defendant moved for summary judgment. Plaintiffs argued that the noise mitigation payment provision in the IGA was an alternative performance or guarantee of performance provision. In the alternative, plaintiffs argued that the payments were valid and enforceable liquidated damages. Denver argued that the provision was a liquidated damages clause, but unenforceable as a penalty. The court determined that the provision constituted a clause for liquidated damages, but also found that genuine issues of material fact existed as to whether it was enforceable.

*29 Following a four-day trial to the court, the trial court awarded plaintiffs $4.0 million, finding that the provision was enforceable as a valid liquidated damages clause. The damage award consisted of $500,000 for each of the seven grid point violations and $500,000 for violating the noise contour. The court also granted $1,807,218 in prejudgment interest to plaintiffs.

This appeal and cross-appeal followed.

L.

Denver first contends that the trial court erred in finding that the noise mitigation payment provision constituted a valid and enforceable liquidated damages clause. We perceive no error.

Paragraph 5.6.3 of the IGA states:

If the court, after hearing the matter, does not order Denver to exercise its authority to impose such rules and regulations as will achieve and maintain the NEPS, or determines that Denver does not have such authority, then the New Airport shall make a noise mitigation payment of $500,000 for each violation to Adams County or to the city, if any, within which the property affected by the NEPS violation lies.

Unless the contract reveals on its face that the stipulated payment is so disproportionate to any possible loss as to constitute a penalty, the determination of whether the specified damages constitute a penalty is a question of fact. Yerton v. Bowden, 762 P.2d 786 (Colo.App.1988).

To make a factual determination that a liquidated damages clause is valid and en-foreeable, the court must find that: (1) at the time the contract was entered into, the anticipated damages in case of breach were difficult to ascertain; (2) the parties mutually intended to liquidate them in advance; and (3) the amount of liquidated damages, when viewed as of the time the contract was made, was a reasonable estimate of the potential actual damages the breach would cause. Perino v. Jarvis, 135 Colo. 393, 312 P.2d 108 (1957).

Denver bore the burden of proving that the noise mitigation payment provision is an unenforceable penalty. See Rohauer v. Little, 736 P.2d 403 (Colo.1987).

The trial court determined, and we agree, that the noise mitigation payment provision is not so disproportionate on its face as to constitute a penalty. Further, the trial court properly considered the three listed elements in determining that the provision was valid and enforceable.

A.

As to the first element, the trial court found that the evidence established that "it would have been difficult, if not impossible, at the time the IGA was executed, for the parties to ascertain the amount of actual damages that could occur." The fifty- to one-hundred-year expected duration of DIA and the IGA made it particularly difficult to project future population, land uses, and damages. Denver's own expert appraiser testified to the near impossibility of predicting any decrease in property values based on DIA noise as distinct from other factors. Denver does not appear to contest the trial court's factual determination of this issue, and we perceive no error.

B.

As to the second element, the trial court also found that the parties intended to liquidate damages in advance, but Denver now argues that the plain language of the IGA, along with plaintiffs' conduct and admissions demonstrate that the parties intended the noise mitigation payments as penalties. Again, we perceive no error.

In determining the parties' mutual intent, the court should consider the contract's subject matter and the purposes and objects it purports to accomplish. In making this evaluation, the cireumstances surrounding the creation of the contract may also be considered. Powder Horn Constructors, Inc. v. City of Florence, 754 P.2d 356 (Colo.1988).

Here, the evidence at trial established that the IGA was an intensely negotiated doeument that took over three years to complete. Both parties were represented by sophisti *30 cated business people, including experts and attorneys experienced in negotiating contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bose Corporation v. Ejaz
732 F.3d 17 (First Circuit, 2013)
Planned Pethood Plus, Inc. v. KeyCorp, Inc.
228 P.3d 262 (Colorado Court of Appeals, 2010)
Puls v. Landmark Community Newspapers, Inc.
335 F. App'x 805 (Tenth Circuit, 2009)
Butler v. Lembeck
182 P.3d 1185 (Colorado Court of Appeals, 2007)
Denver Foundation v. Wells Fargo Bank, N.A.
163 P.3d 1116 (Supreme Court of Colorado, 2007)
Klinger v. Adams County School District No. 50
130 P.3d 1027 (Supreme Court of Colorado, 2006)
Turnbaugh v. Chapman
68 P.3d 570 (Colorado Court of Appeals, 2003)
Leanin' Tree, Inc. v. Thiele Technologies, Inc.
43 F. App'x 318 (Tenth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
40 P.3d 25, 2001 Colo. J. C.A.R. 1606, 2001 Colo. App. LEXIS 564, 2001 WL 301132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-county-commissioners-v-city-county-of-denver-coloctapp-2001.