IN THE INTERMEDIATE COURT OF APPEALS OF WEST VIRGINIA
Spring 2025 Term FILED _____________________ February 20, 2025 released at 3:00 p.m. No. 24-ICA-183 ASHLEY N. DEEM, CHIEF DEPUTY CLERK INTERMEDIATE COURT OF APPEALS _____________________ OF WEST VIRGINIA
WEST VIRGINIA DEPARTMENT OF TRANSPORTATION, DIVISION OF HIGHWAYS, Plaintiff Below, Petitioner,
v.
OLYMPUS PAINTING CONTRACTORS, INC.; GREAT MIDWEST INSURANCE COMPANY; and SKYWARD UNDERWRITERS AGENCY, INC., Defendants Below, Respondents.
___________________________________________________________
Appeal from the Circuit Court of Kanawha County Honorable David J. Hardy, Judge Civil Action No. 22-C-292
AFFIRMED, IN PART, VACATED, IN PART, AND REMANDED WITH DIRECTIONS _________________________________________________________
Submitted: February 4, 2025 Filed: February 20, 2025
David A. Ford, Esq. Johnson W. Gabhart, Esq. W. Va. Department of Transportation, Johnstone & Gabhart, LLP Division of Highways, Legal Division Charleston, West Virginia Charleston, West Virginia Counsel for Respondent Olympus Counsel for the Petitioner Painting Contractors, Inc. Thomas J. Moran, Esq. Wright, Constable & Skeen, LLP Glen Allen, Virginia Gene W. Bailey, II, Esq. David F. Nelson, Esq. John H. Tinney, Jr., Esq. Hendrickson & Long PLLC Charleston, West Virginia Counsel for Respondents Great Midwest Insurance Company and Skyward Underwriters Agency, Inc.
JUDGE WHITE delivered the Opinion of the Court. WHITE, JUDGE:
West Virginia Code § 5-22-2 (2003) – which, for simplicity we refer to as
“Section 2” – creates a process for government agencies to reject “erroneous” bid proposals
by contractors who offer to complete a government project. Section 2(b) spells out four
conditions that the agency must find before rejecting an erroneous bid proposal. Another
part of the statute, Section 2(c), provides that a “contractor who withdraws a bid under the
provisions of this section” is subject to a penalty.
In this appeal, respondent Olympus Painting Contractors, Inc. (“Olympus”)
asserts it discovered a significant clerical mistake in a bid proposal that it prepared for the
petitioner, the West Virginia Department of Transportation, Division of Highways
(“DOH”), after the proposal was opened by the DOH. Olympus contends it had a right
under Section 2 to withdraw the bid proposal upon its discovery of the mistake; the DOH
asserts contractors have no right to withdraw bids under Section 2. Still, despite that
assertion, DOH broadly claims it decided that Olympus did not make a noticeable mistake
and, therefore, was not entitled to the rejection of its bid.
The circuit court below examined the record and, in an order dated March
29, 2024, granted summary judgment to Olympus. Applying the four conditions
established in Section 2(b), the circuit court determined that all of the conditions were
established and that the DOH should have rejected Olympus’s erroneous bid. The DOH
1 appeals that order and asserts, for the first time on appeal, that its decision that no mistake
occurred is entitled to complete deference because Olympus did not show the decision was
arbitrary, capricious, or an abuse of discretion.
As we discuss below, we find that Section 2 is ambiguous. But, in light of
language in the statute and the Legislature’s intentions, we interpret the statute and find
that, after bids are opened, a government agency must reject a bid proposal that a bidding
contractor declares to be erroneous, and seeks to withdraw, if the contractor establishes the
four conditions contained in Section 2(b). The record below shows Olympus established
three of the four conditions while the DOH offered no evidence to the contrary, and so we
affirm the circuit court’s ruling in favor of Olympus on those three conditions. Regarding
the fourth condition – which asks whether Olympus made any error – the circuit court did
not assess whether the DOH’s summary conclusion was arbitrary, capricious, or an abuse
of discretion; accordingly, we vacate the circuit court’s order, in part, and remand for
reconsideration of that condition on the existing record.
I. FACTUAL AND PROCEDURAL BACKGROUND
In early 2021, the DOH posted an invitation soliciting bid proposals1 for a
contract to repair and repaint the Veteran’s Memorial Bridge in Brooke County, West
1 The DOH’s regulations define a “Proposal” as “the offer of a bidder, on the prescribed form, to perform the work and to furnish the labor and material at the prices quoted.” 157 C.S.R. § 3.2.67 (2024).
2 Virginia. The invitation required every contractor bidding for the contract to, among other
things, provide a “bid bond” equal to five percent of the aggregate amount of the
contractor’s proposal.2 A bid bond, also called a “proposal guarantee,” is simply “security
furnished with a bid to guarantee that the bidder will enter into the contract if his or her bid
is accepted.” 157 C.S.R. § 3.2.69.
Olympus submitted a bid proposing to complete the contract for
$5,606,316.34; it included with its proposal a bid bond equal to five percent of the bid total
(that is, $280,315.82). The bid proposal was encrypted and submitted using DOH’s digital
“Bid Express” website,3 an online program that allowed contractors to examine the
contract’s specifications, and to enter and modify their proposals up to the moment of
opening. The DOH publicly decrypted and opened the bid proposals, from Olympus and
2 See W. Va. Code § 5-22-1(d) (2021) (“All bids . . . shall include a valid bid bond or other surety . . . .”); W. Va. Code § 5-22-2(a) (2003) (“No public entity may accept or consider any bids that do not contain a valid bid bond or other surety . . . .”). Similarly, West Virginia Code § 17-4-19(e) (2000) requires bidding contractors to provide “sealed proposals” to the DOH, accompanied by a “certified check of the bidder or bidder’s bond . . . in the amount as the commissioner shall specify in the advertisement, but not to exceed five percent of the aggregate amount of the bid[.]” The DOH’s regulations require a different process (calling bid bonds a “proposal guaranty”) that requires every bid proposal to be submitted electronically and to be “accompanied by a digitally signed proposal guaranty bid bond . . . .” 157 C.S.R. § 3.4.7. See also, W. Va. Department of Transportation, Division of Highways, Standard Specifications for Roads and Bridges, § 102.6 (2023 edition) (“No proposal will be considered unless accompanied by a digitally signed proposal guaranty (bid) bond . . . made payable to the West Virginia Division of Highways. Bid bonds will be accepted only if submitted electronically.”). 3 The parties also refer to the website as “BIDEX” or “BidX.”
3 other bidding contractors, on March 9, 2021, and Olympus was the lowest bidder.
Olympus’s bid proposal was about $1.6 million, or 21.89%, less than the next lowest
bidder.
On March 15, 2021, after the bid proposals were opened but before the DOH
had chosen a winning bidder for the contract, Olympus emailed a letter to the DOH stating
that a clerical mistake had resulted in an error in its bid. Olympus asserted that its bid
proposal had been constructed using prices calculated by the company’s owner, but then
written down by a company employee. There were thirty-four different line items in the
DOH request for bid proposals; one line item was for 177 feet of “removing and replacing
expansion joints.” The company owner calculated that $9,340 per foot was an appropriate
bid amount for the expansion joint repairs, and the company employee wrote that number
down. However, an Olympus clerical employee, tasked with entering the numbers onto the
Bid Express website, mistook the “9” in the handwritten documents for a “5” and
erroneously input a per-foot unit price of $5,340 (or $4,000 less per foot than intended).
For 177 units of this work, the mistake resulted in a bid shortfall of $708,000. Because of
the mistake, Olympus asked the DOH to reject its bid pursuant to Section 2, which (as we
discuss later) establishes a process for government agencies to reject bid proposals that
contain errors.
On March 19, 2021, the DOH replied in a letter noting it had received
Olympus’s notice of the erroneous bid and the request for the bid to be rejected. However,
4 the DOH stated it was unable to grant Olympus’s request because it “considered the bid
submitted by Olympus as a valid bid[.]” In a separate letter dated the same day and titled
“Bid Accepted,” DOH declared that Olympus had been awarded the bridge project and
would be required to sign a contract with the DOH within twenty days.
Olympus did not sign the contract. Instead, Olympus retained a lawyer who
sent further letters to the DOH containing additional evidence and affidavits. Olympus’s
lawyer reiterated the plea that the DOH reject Olympus’s bid proposal pursuant to Section
2, and he requested an administrative hearing. On May 14, 2021, the DOH’s legal division
responded that the DOH had again determined that “the Olympus bid is not an error[.]”
The DOH lawyer declared that the evidence presented by Olympus “did not prove by clear
and convincing evidence” that an error occurred sufficient to “permit the withdrawal of the
bid” under Section 2.4 The DOH lawyer also declared “that no hearing on the issues is
necessary” and warned that, if Olympus did not sign the DOH’s contract by May 28, 2021,
Olympus would forfeit its five percent bid bond.
4 We are uncertain of the source of the DOH lawyer’s clear-and-convincing burden of proof, but we note that one of Olympus’s letters quoted Federal Acquisition Regulations (which govern federal projects) that require clear and convincing evidence “as to the existence of a mistake and as to the bid actually intended.” See, e.g., FAR 14.407-3(b)(1) (2025). However, DOH’s counsel conceded at oral argument that Section 2 only requires proof by a preponderance of the evidence.
5 Olympus refused to sign the DOH contract.5 On May 28, 2021, the DOH sent
an email to the issuer of Olympus’s bid bond demanding that the amount of the bond be
paid to the DOH. The issuer of the bond, respondent Great Midwest Insurance Company,
refused to pay.
The DOH sued Olympus on April 15, 2022, and sought, among other things,
to force payment of the bid bond because Olympus failed to sign the DOH’s contract after
Olympus’s bid was accepted.6 In defense, Olympus continued to argue that it had no
obligation to enter a contract because, under the terms of Section 2, the DOH should have
rejected Olympus’s erroneous bid and returned the bid bond. After conducting discovery,
the DOH and Olympus filed competing motions for summary judgment. Both parties
asserted that no genuine dispute of material fact existed in the record, and that the circuit
court’s considerations were to be guided by Section 2.
On March 29, 2024, the circuit court entered an order that granted summary
judgment to Olympus and denied the DOH’s motion. The circuit court agreed with the
parties’ contention that there were no genuine issues as to any material fact, and found the
5 The DOH did not award the bridge project to the next lowest bidder (Freyssinet, Inc., which bid $7,216,143.40). Instead, it chose to solicit a new round of bid proposals in Fall 2021. Freyssinet submitted the lowest bid proposal at $7,496,014.10, was awarded the contract, and completed the bridge project the following year. 6 The DOH also asserted claims against the company that issued Olympus’s bid bond, Great Midwest Insurance Company, and the company that investigated the DOH’s claim for payment under the bond, respondent Skyward Underwriters Agency, Inc.
6 case was governed exclusively by Section 2. Under that section, the circuit court noted that
a government agency could reject an erroneous bid if four conditions exist:
(1) An error was made; (2) the error materially affected the bid; (3) rejection of the bid would not cause a hardship on the public entity involved, other than losing an opportunity to receive construction projects at a reduced cost; and (4) enforcement of the bid in error would be unconscionable.
W. Va. Code § 5-22-2(b). Based upon the evidence produced by the parties, the circuit
court found “that Olympus made an inadvertent, clerical error when submitting its bid[.]”
Olympus had promptly notified the DOH prior to the DOH’s award of the contract, and
DOH could, with no delay or hardship, have awarded the contract to the next lowest bidder.
Because a DOH engineer had testified that a $708,000 bid error would have “drastically”
altered Olympus’s intended bid, and the testimony of Olympus’s owner that the bid error
was catastrophic and would have threatened the company’s survival, the circuit court found
“it was unconscionable for DOH to require Olympus to perform for a price $708,000 below
its intended bid.”
The circuit court concluded that the “DOH had the authority to reject or
withdraw Olympus’s erroneous bid and return its bid security as the four conditions set out
in West Virginia Code § 5-22-2(b) were met” and that the DOH “should have done so.”
Because Olympus should not have been compelled to enter into a contract based upon its
erroneous bid, the circuit court concluded that the DOH was “not entitled to Olympus’s bid
security[.]” Therefore, the circuit court granted judgment to Olympus and against the DOH,
and it ordered the DOH to return Olympus’s bid bond.
7 The DOH now appeals the circuit court’s March 29, 2024, summary
judgment order that interpreted and applied West Virginia Code § 5-22-2.
II. STANDARD OF REVIEW
Both parties asserted before the circuit court that summary judgment would
be proper because no questions of material fact existed and that the circuit court’s ruling
centered upon the interpretation and application of Section 2. Summary judgment is
appropriate in a case if “there essentially is no real dispute as to salient facts or if [the case]
only involves a question of law.” Williams v. Precision Coil, Inc., 194 W. Va. 52, 58, 459
S.E.2d 329, 335 (1995) (cleaned up). As this case is presented, we assess the circuit court’s
summary judgment ruling de novo to determine if any inquiry concerning the facts was
desirable to clarify the application of the statute. See Syl. Pt. 1, Painter v. Peavy, 192 W.
Va. 189, 451 S.E.2d 755 (1994) (“A circuit court’s entry of summary judgment is reviewed
de novo.”); Syl. Pt. 3, Aetna Cas. & Sur. Co. v. Fed. Ins. Co. of New York, 148 W. Va. 160,
133 S.E.2d 770 (1963) (“A motion for summary judgment should be granted only when it
is clear that there is no genuine issue of fact to be tried and inquiry concerning the facts is
not desirable to clarify the application of the law.”). To the extent the circuit court
interpreted a statute, our review is also de novo. Syl. Pt. 1, Chrystal R.M. v. Charlie A.L.,
194 W. Va. 138, 459 S.E.2d 415 (1995) (“Where the issue on an appeal from the circuit
court is clearly a question of law or involving an interpretation of a statute, we apply a de
novo standard of review.”); Syl. Pt. 1, Appalachian Power Co. v. State Tax Dep’t of W.
8 Va., 195 W. Va. 573, 466 S.E.2d 424 (1995) (“Interpreting a statute or an administrative
rule or regulation presents a purely legal question subject to de novo review.”).
III. DISCUSSION
The DOH’s central argument on appeal is that the circuit court erred in its
application of the four conditions contained in West Virginia Code § 5-22-2(b). Before
turning to the DOH’s argument, we must first examine the language of Section 2 to
determine the Legislature’s intention behind the four conditions. This is because statutes
are to be applied so as to achieve the Legislature’s goals. Put simply, “[o]ur duty is to get
at the intent of the law: we are not responsible for its style.” Pott v. Arthur, 104 U.S. 735,
736 (1881).
Section 2 contains three paragraphs ((a), (b), and (c)) and is titled in a manner
suggesting the statute pertains to three topics: “Designation of time and place for opening
of bids; right to reject or withdraw bid; bid resubmission.” (Emphasis added.) Paragraph
(a) plainly applies to the time and place for opening bid proposals and is not relevant to our
discussion.7 Paragraphs (b) and (c), however, are relevant and provide a process with four
7 West Virginia Code § 5-22-2(a) provides:
The public entity accepting public contract bids shall, in its resolution providing for the contract or purchase and for the advertisement for bids, designate the time and place that the bids will be received and shall at that time and place publicly open the bids and read them aloud. No public entity may accept Continued . . .
9 conditions for government agencies to address errors contained in bid proposals after the
proposals are opened:
(b) . . . The public entity may only reject an erroneous bid after the opening if all of the following conditions exist: (1) An error was made; (2) the error materially affected the bid; (3) rejection of the bid would not cause a hardship on the public entity involved, other than losing an opportunity to receive construction projects at a reduced cost; and (4) enforcement of the bid in error would be unconscionable. If a public entity rejects a bid, it shall maintain a file of documented evidence demonstrating that all the conditions set forth in this subdivision existed. If the public entity determines the bid to be erroneous, the public entity shall return the bid security to the contractor.
(c) A contractor who withdraws a bid under the provisions of this section may not resubmit a bid on the same project. If the bid withdrawn is the lowest bid, the next lowest bid may be accepted.
W. Va. Code § 5-22-2(b) and (c).8
or take any bid, including receiving any hand delivered bid, after the time advertised to take bids. No bid may be opened on days which are recognized as holidays by the United States postal service. No public entity may accept or consider any bids that do not contain a valid bid bond or other surety approved by the State of West Virginia or its subdivisions. 8 Because the first sentence of Section 2(b) has no bearing on our Decision, we have omitted it from the discussion. The first sentence of Section 2(b) provides: “The provisions and requirements of this section, section one of article twenty-two of this chapter [W. Va. Code § 5-22-1], the requirements stated in the advertisement for bids and the requirements on the bid form may not be waived by any public entity.” W. Va. Code § 5-22-2(b). See also Wiseman Const. Co. v. Maynard C. Smith Const. Co., 236 W. Va. 351, 358 n.10, 779 S.E.2d 893, 900 n.10 (2015) (explaining the first sentence of Section 2(b)). There is no allegation DOH waived any of these requirements.
10 Throughout this case, Olympus has asserted that, if a contractor discovers an
error after bid proposals are opened, Section 2 gives the contractor a right to either
withdraw the erroneous bid or have the bid rejected by the government agency. The DOH
takes a contrary position and argues that there is nothing in Section 2 allowing a bidder to
withdraw a proposal after the opening process has occurred. The general rule when
construing a statute is that “[a] statutory provision which is clear and unambiguous and
plainly expresses the legislative intent will not be interpreted by the courts but will be given
full force and effect.” Syl. Pt. 2, State v. Epperly, 135 W. Va. 877, 65 S.E.2d 488 (1951).
However, a statute is open to construction “where the language used requires interpretation
because of ambiguity which renders it susceptible of two or more constructions or of such
doubtful or obscure meaning that reasonable minds might be uncertain or disagree as to its
meaning.” Hereford v. Meek, 132 W. Va. 373, 386, 52 S.E.2d 740, 747 (1949). “When
there is uncertainty as to the meaning of a statute, the statute is ambiguous and must be
evaluated to give effect to the intent of the Legislature.” Dale v. Painter, 234 W. Va. 343,
349, 765 S.E.2d 232, 238 (2014). “A statute that is ambiguous must be construed before it
can be applied.” Syl. Pt. 1, Farley v. Buckalew, 186 W. Va. 693, 414 S.E.2d 454 (1992).
“In ascertaining legislative intent, effect must be given to each part of the
statute and to the statute as a whole so as to accomplish the general purpose of the
legislation.” Syl. Pt. 2, Smith v. State Workmen’s Compensation Commissioner, 159 W.
Va. 108, 219 S.E.2d 361 (1975). Section 2, evaluated as a whole, leads us to find the statute
is ambiguous because it is susceptible to multiple conflicting, but reasonable,
11 interpretations regarding whether a contractor may withdraw an erroneous bid. The title of
the statute suggests that paragraph (b) should pertain to both the “right to reject or withdraw
bid,” but paragraph (b) contains only a process for a government agency to reject an
erroneous bid.9 Paragraph (b) certainly allows a government agency to reject a faulty bid
on its own initiative, but it is unclear what an agency is to do when, as in this case, a bidding
contractor pleads to have an erroneous bid withdrawn or rejected. Furthermore, paragraph
(c) discusses a “contractor who withdraws a bid under the provisions of this section,” but
there are no provisions elsewhere in Section 2 pertaining to withdrawals of bids. Viewing
the parts of the statute as a whole, we perceive that the Legislature intended for Section 2
to encompass a means for contractors to withdraw, or otherwise remove from government
consideration, bids that are materially erroneous.
Our examination of the legislative history behind the adoption of Section 2
bolsters this conclusion. When Section 2 was first introduced in the Legislature in 2003,
paragraph (b) originally centered on the means for a contractor to withdraw a bid proposal
that contained “mechanical, clerical, or mathematical errors.” The proposed version of
paragraph (b) of Section 2 stated, in part:
Bids containing patently obvious, unintentional, and substantial mechanical, clerical, or mathematical errors, or errors of unintentional omission of a substantial quantity of work, labor, material, or services made directly in the
9 We recognize, of course, that statutory titles are not part of a statute; they are “intended as mere catchwords to indicate the contents of the section and are not titles of the sections, or any part of the statute . . . .” W. Va. Code § 2-2-10(b)(3) (2023).
12 compilation of the bid, shall not be considered by the public entity but may be withdrawn by the contractor if clear and convincing sworn, written evidence of such errors is furnished to the public entity within forty-eight hours of the bid opening excluding Saturdays, Sundays, and legal holidays. Such errors must be clearly shown by objective evidence drawn from inspection of the original work papers, documents, or materials used in the preparation of the bid sought to be withdrawn. If the public entity determines that the error is a patently obvious mechanical, clerical, or mathematical error, or unintentional omission of a substantial quantity of work, labor, material, or services, as opposed to a judgment error, and that the bid was submitted in good faith it shall accept the withdrawal and return the bid security to the contractor.
House Bill 3117 (Introduced February 21, 2003; emphasis added). House Bill 3117 also
contained a paragraph (c) to Section 2, the vestiges of which survived into the current
statute, which provided that “[a] contractor who attempts to withdraw a bid under the
provisions of this Section shall not be allowed to resubmit a bid on the project.” Id.
The House Bill 3117 version of Section 2 was heavily revised by the
Legislature into its current form through judiciary committee substitutions and
amendments on the floor, but those revisions further demonstrate a legislative goal to
permit contractors, acting in good faith, to withdraw bid proposals that were formulated
with substantial errors. As we noted earlier, the amendments adopted by the Legislature in
2003 created a test in Section 2(b) with four conditions: (1) there must be an error in the
bid; (2) the error must be material to the contract; (3) rejection must not cause hardship on
the public entity (other than the loss of the bargain presented by the erroneous bid); and (4)
enforcement of the erroneous bid would be unconscionable.
13 The legal question of whether a contractor may withdraw a bid proposal
containing a unilaterally made mistake appears to be a novel one in West Virginia’s courts.
But when the Legislature incorporated the above four conditions into Section 2 in 2003, it
seems to have been aware that the majority of other states’ courts have applied similar
conditions through common-law rules and excused contractors from their bid mistakes.
Stated simply, courts across the country have allowed the withdrawal of a bid containing
errors material to the contract when it would be unconscionable to enforce a contract
formed on the bid, and where withdrawal of the bid would do nothing more than return the
government agency to the status quo before it opened the bid.
The concept of permitting a contractor to withdraw an erroneous bid has been
a principle of the common law since at least 1900. In Moffett, Hodgkins & Clarke Co. v.
Rochester, 178 U.S. 373 (1900), an engineer (who was “extremely nearsighted” and
working in haste and confusion) transcribed his figures and mistakenly inserted into a bid
the sum of $1.50 per cubic yard rather than the $15.00 per cubic yard intended (for moving
2,000 cubic yards of material). Id. at 377. The U.S. Supreme Court reasoned that the
erroneous bid proposal sent to the government was one which the contractor never intended
to make; because the minds of the parties had never met, and the government was trying to
take “an improper and unconscionable advantage” of the contractor’s clerical errors, no
contract could be formed by the faulty bid. Id. at 379.
14 Since 1900, the vast majority of jurisdictions have refused to bind contractors
to erroneous bids. See generally, David B. Harrison, Right of bidder for state or municipal
contract to rescind bid on ground that bid was based upon his own mistake or that of his
employee, 2 A.L.R.4th 991 (1980) (“Although there is some diversity among the sets of
criteria applied by the courts in determining a bidder’s right to a decree of rescission or to
similar relief in situations where the bidder’s proposal was based upon his own mistake,
courts in virtually all the reported cases . . . have recognized that . . . such relief may be
properly granted.”). Courts have articulated a complicated amalgam of common-law
conditions to be weighed before a mistaken bid may be withdrawn, conditions that vary
depending upon whether the bid is withdrawn before it is opened by the government
agency, after it is opened but before it is accepted, or after it is accepted and a contract
formed; and whether the government agency knew of or induced the mistake. One court
gave this two-part guideline for bid withdrawals:
[T]he majority of courts which have addressed the question hold that under the proper circumstances a contractor should be permitted to withdraw a bid or rescind a contract when its bid is based on a mistake of fact. Although courts have not been unanimous in articulating the particular conditions which entitle a contractor to withdraw a bid or rescind a contract, they have generally granted relief to a bidder if (1) the error is so substantial that enforcement would be unconscionable and (2) if notice is given before the nonmistaken party has substantially changed its position so that it cannot be returned to the status quo ante.
Nat’l Fire Ins. Co. of Hartford v. Brown & Martin Co., 726 F. Supp. 1036, 1039 (D.S.C.
1989) (citation omitted). The approach applied by most courts is the doctrine of equitable
recission, which one court assessed had four factors:
15 The general rule as to the conditions precedent to rescission for unilateral mistakes may be summarized thus: 1, the mistake must be of such grave consequences that to enforce the contract as made or offered would be unconscionable; 2, the mistake must relate to a material feature of the contract; 3, the mistake must not have come about because of the violation of a positive legal duty or from culpable negligence; 4, the other party must be put in statu quo to the extent that he suffers no serious prejudice except the loss of his bargain.
City of Baltimore v. De Luca-Davis Const. Co., 210 Md. 518, 527, 124 A.2d 557, 562
(1956). See also James Cape & Sons Co. v. Mulcahy, 700 N.W.2d 243, 255-57 (Wis. 2005)
(identifying five factors for equitable recission). The treatise Bruner and O’Connor on
Construction Law divines six different factors courts have relied upon to relieve a
contractor from a unilateral mistake of fact in a bid:
[R]elief from a unilateral material mistake of fact in a bid can be obtained (1) any time before or after acceptance of the bid if the accepting party had knowledge of or induced the mistake, but (2) only before acceptance if the accepting party is innocent of the mistake. As a general rule, relief for [a] “unilateral” bid mistake of which the bid recipient is innocent will be granted upon proof that: (1) the mistake is of such grave consequences that enforcement of the contract would be “unconscionable”; (2) the mistake relates to a “material” feature of the contract; (3) the mistake did not . . . result from the bidder’s “gross negligence” or a violation of a “positive legal duty”; (4) the mistake was not caused by and was unknown to and not suspected by the bid recipient; (5) granting of relief must not cause the bid recipient any serious prejudice other than loss of the bargain; and (6) the bidder did not assume the risk of mistake.
Philip L. Bruner, Patrick J. O’Connor, Jr., 1 Bruner & O’Connor on Construction Law §
2:139 (2024). See also, Ernest M. Jones, The Law of Mistaken Bids, 48 U. Cin. L. Rev. 43,
54-55 (1979) (outlining seven factors underlying “the impalpable mistake principle”).
16 In this case, we are guided exclusively by the Legislature’s articulation of the
four conditions in Section 2(b). However, it is clear that the Legislature incorporated into
Section 2(b) (in a heavily modified form) the common-law concepts discussed above. In
sum, our review of the common law of our sister states further supports the Legislature’s
intention to incorporate a mechanism into Section 2(b) that permits a contractor to trigger
a government agency to remove an erroneous bid from consideration.
Moreover, we note that another Executive branch agency, the Purchasing
Division of the Department of Administration, has adopted a regulation that expresses the
legislative intention of Section 2. The Purchasing Division has regulations designed to
assist State agencies in procuring services and supplies. The Purchasing Division
regulation which permits a contractor to trigger removal of an erroneous bid from
consideration provides:
The Director may reject a bid a vendor declares to be erroneous after the bid opening, but otherwise appears to be responsive, if all of the following conditions exist: (1) An error was made; (2) The error materially affected the bid; (3) Rejection of the bid would not cause a hardship on the State spending unit involved, other than losing an opportunity to receive commodities, services or printing at a reduced cost; and (4) Enforcement of the part of the bid in error would be unconscionable. In order for the Director to reject a bid under this subsection, the public file must contain documented evidence that all of the conditions set forth in this subdivision exist.
17 148 C.S.R. § 1.6.3.6 (2023) (emphasis added). While the regulation does not allow a
contractor to unilaterally withdraw a bid, it does permit a contractor to prompt the
Purchasing Division to reject a bid if the four conditions of Section 2(b) are established.
Finally, because the bidding process is heavily regulated through statutes and
regulations, it is generally accepted that when a government agency solicits bid proposals
for a contract, and a contractor submits such a bid, both parties must exercise good faith
throughout the bidding process. Bad faith in the submission of an erroneous bid is a ground
for denying a contractor relief; the knowing acceptance of an erroneous bid by the
government is a ground for granting the contractor relief. “This approach recognizes that a
bidder should not be allowed to rescind a mistaken bid if the bid were made in bad faith
and emphasizes the desirability of ensuring that public projects proceed on the basis of
accurate cost estimates.” Powder Horn Constructors, Inc. v. City of Florence, 754 P.2d
356, 362 (Colo. 1988). Federal cases hold that “[i]f the contracting officer is on notice,
actual or constructive, of a bidder’s mistake; fails properly to verify the bid; and
subsequently accepts the bid, a presumption then arises that the contracting officer has
acted in bad faith and taken advantage of the bidder” and reformation or rescission will be
permitted. BCM Corp. v. United States, 2 Cl. Ct. 602, 608 (1983). Relief can be appropriate
“to prevent the government from overreaching when it knows the contractor has made a
18 significant mistake during the bidding process.” Giesler v. United States, 232 F.3d 864,
869 (Fed. Cir. 2000).10
In light of the above discussion, we find that West Virginia Code § 5-22-2 is
ambiguous. However, the Legislature obviously intended for both bidding contractors and
the government agency to have a remedy to withdraw or otherwise void bids with
10 “Every contract imposes upon each party a duty of good faith and fair dealing in its performance and its enforcement.” Mountaineer Fire & Rescue Equip., LLC v. City Nat’l Bank of W. Va., 244 W. Va. 508, 529 n.9, 854 S.E.2d 870, 891 n.9 (2020) (quoting Restatement (Second) of Contracts § 205 (1981)). “Good faith” means “honesty in fact and the observance of reasonable commercial standards of fair dealing.” W. Va. Code § 46-1- 201(20) (2006). “[T]he implied good faith obligations of a contracting party are tantamount to the traditional duties of care to refrain from misrepresentation and to correct subsequently discovered error, insofar as any representation is intended to induce, and is material to, another party’s decision to enter into a contract in justifiable reliance upon it.” Centronics Corp. v. Genicom Corp., 132 N.H. 133, 139, 562 A.2d 187, 190 (1989).
In the context of bidding, for government entities, “Discretion in awarding a . . . contract is not abused when it is predicated upon ‘good faith and honesty.’” Pioneer Co. v. Hutchinson, 159 W. Va. 276, 287, 220 S.E.2d 894, 901 (1975), overruled on other grounds by State ex rel. E. D. S. Fed. Corp. v. Ginsberg, 163 W. Va. 647, 259 S.E.2d 618 (1979). “[T]he good faith and honesty of the award are the determining factors, and the courts may compel . . . officials to act in good faith in awarding contracts on competitive bidding.” Harrison v. City of Huntington, 141 W. Va. 774, 780-81, 93 S.E.2d 221, 224 (1956). “[I]f the party receiving the bid knows . . . that the bidder made a mistake, the contract is voidable by the bidder.” Wendell F. Grimes, Barry J. Walker, Unilateral Mistakes in Construction Bids: Methods of Proof and Theories of Recovery – A Modern Approach, 5 B.C. Indus. & Com. L.Rev. 213, 214 (1964). See also Wiseman Const. Co., 236 W. Va. at 360, 779 S.E.2d at 902 (“[F]ederal standards have the same basic objective[] of . . . ensuring the good-faith conduct of agency officials in securing public contracts . . . .”). Regarding duties of bidding contractors, the Restatement (Second) of Contracts provides that “[a] mistaken party’s fault in failing to know or discover the facts before making the contract does not bar him from avoidance or reformation . . . unless his fault amounts to a failure to act in good faith and in accordance with reasonable standards of fair dealing.” Restatement (Second) of Contracts § 157 (1981).
19 substantial clerical or arithmetical errors. We therefore hold that, under West Virginia Code
§ 5-22-2(b), after the opening of bid proposals, a government agency must reject a bid
proposal that a bidding contractor declares to be erroneous, and seeks to withdraw, if the
contractor establishes by a preponderance of the evidence that the following conditions
exist: (1) An error was made in the bid; (2) The error materially affected the bid; (3)
Rejection of the bid would not cause a hardship on the government agency, other than
losing an opportunity to enter into the contract at the amount stated in the erroneous bid;
and (4) Enforcement of the erroneous bid would be unconscionable.11 If a contractor
succeeds in having an erroneous bid withdrawn through the rejection process established
in West Virginia Code § 5-22-2(b), then the government agency must return the bid bond
to the contractor, and West Virginia Code § 5-22-2(c) mandates that the contractor may
not resubmit a bid on the same contract. Finally, under West Virginia Code § 5-22-2(c), if
the rejected or withdrawn bid was the lowest bid, then the government agency may proceed
to accept the next lowest and acceptable bid.
We now examine the parties’ arguments concerning the application of
Section 2(b) to the facts of this case. Like the circuit court, we must assess the record to
determine if the four conditions in Section 2(b) are established by the record. The first
11 As we noted earlier, during argument before this Court, counsel for the DOH agreed that Section 2 incorporates a preponderance standard of proof. Moreover, in response to questions from the Court, counsel further conceded that Section 2 is mandatory and that, if all four conditions are met, an agency must reject an erroneous bid.
20 condition is that there must be an error, some mistake of fact in the preparation of the bid.12
“Mistakes of fact in bid preparation result from such things as faulty addition, omission of
items, typographical errors, misplaced decimals, errors in transferring items from detail
summary sheets, transposition of numbers, misinterpretation of specifications and a host
of other essentially clerical errors.” 1 Bruner & O’Connor on Construction Law § 2:135
(footnotes omitted).
Before the circuit court, the DOH offered no direct evidence to counter
Olympus’s evidence of a mistake of fact; instead, the DOH offered its conclusion that
Olympus’s bid proposal, compared against the proposals by other contractors and DOH’s
pre-bid estimate, was not “different enough” to be read as a palpable, patent, obvious
mistake – and so, it must not be mistake.13 However, in its briefs and oral argument, the
12 A mistake of fact is different from a mistake of judgment. Under the common- law rulings of most jurisdictions, a mistake of judgment in forming a bid proposal is not a ground for relief. “A ‘mistake in judgment’ exists when a bidder, even though not mistaken about existing facts, is mistaken about what business action should be taken based upon (1) existing facts, or (2) predicted future facts. No legal relief is granted for mistakes in judgment.” 1 Bruner & O’Connor on Construction Law § 2:136. “Mistakes caused by errors in judgment or poor estimating by the bidder, or by his misconstruction of the legal effect of the specifications usually are not grounds for relief.” Charles H. Witherwax, Bid Bond Liability, 1970 A.B.A. Sec. Ins. Negl. & Comp. L. Proc. 50, 52 (1970). Because the facts of this case hinge exclusively on a mistake of fact in Olympus’s bid proposal, we decline to consider whether mistakes of judgment are encompassed by the language of Section 2(b). 13 Counsel for the DOH expanded on this assertion at oral argument. Essentially, DOH engineers suspect that Olympus’s attempt to withdraw could, in reality, be nothing more than “cold feet” and an attempt by Olympus to avoid complying with a bid significantly lower than other bids. We appreciate the DOH’s suspicions, but the standards Continued . . .
21 DOH makes a new argument to this Court that it did not make to the circuit court: that its
conclusions are entitled to absolute deference, and that Olympus has done nothing to show
the DOH abused its discretion or acted arbitrarily or capriciously. The DOH is accurate
that the courts of this State have long held that the DOH has wide discretion in its
application of bidding procedures to protect the public fisc and to ensure contracts are
awarded to the lowest responsible bidder. See, e.g., Syllabus, in part, Excavation Const.,
Inc. v. Ritchie, 159 W. Va. 888, 230 S.E.2d 822 (1976) (“When the Commissioner of the
Department of Highways is required to award a contract to the lowest responsible bidder,
he has wide discretion in determining whether to waive any technicalities in the
requirements of properly promulgated regulations governing bidding procedures . . . .”);
Syl. Pt. 5, in part, Wiseman Const. Co. v. Maynard C. Smith Const. Co., 236 W. Va. 351,
779 S.E.2d 893 (2015) (“[T]he burden of proof in an action challenging the award of a
contract by an unsuccessful bidder or a taxpayer is upon the challenger, who must show
the agency’s actions were arbitrary, capricious, or an abuse of discretion.”).
for summary judgment require evidence from which the circuit court could either discern a triable issue of fact regarding DOH’s theory, or indisputable evidence calling for a resolution as a matter of law. At the summary judgment stage, the DOH was required to “‘offer some concrete evidence from which a reasonable finder of fact could return a verdict in its favor’ or other ‘significant probative evidence tending to support the complaint.’” Williams v. Precision Coil, Inc., 194 W. Va. at 60, 459 S.E.2d at 337 (cleaned up). To the contrary, the DOH asserted that there were no triable issues of fact, and that summary judgment was proper.
22 Despite the circuit court’s proper application of the standards for summary
judgment, the circuit court did not weigh whether or to what degree the DOH’s decision
on the first factor was entitled to deference and whether, in light of the facts presented to
the agency, “there [was] a rational basis for the administrative decision.” Id. Stated
differently, we discern that the circuit court, in the first instance, should weigh whether
DOH’s assessment of the first condition was arbitrary, capricious, or an abuse of its
discretion. Hence, we vacate the circuit court’s decision as to the first condition in Section
2(b), and we remand the case for the circuit court to determine whether the DOH’s decision
on the first factor was arbitrary, capricious, or an abuse of discretion, in light of the
evidence properly before the circuit court.
As for the second, third, and fourth conditions in Section 2(b), we find that
the DOH is not entitled to deference, for an obvious reason: the DOH never conducted any
analysis or made any decisions or findings regarding those factors. Counsel for the DOH
admitted to the trial court that the DOH stopped with the first factor. As counsel stated,
“we don’t believe there was a bid error. . . So we didn’t even go to the other stand – the
other three criteria.” App’x at 570-71. Other than a conclusory statement by DOH’s lawyer
in the May 14, 2021, letter that was responding to entreaties from Olympus’s lawyers, there
is nothing in the record documenting or otherwise establishing that DOH weighed and
applied the second, third, and fourth conditions of Section 2(b) to Olympus’s evidence. We
do not give the statement in the letter special status because “[t]he policy underlying a grant
of special deference to agency decisions . . . does not extend to every agency action. It does
23 not extend to ad hoc representations on behalf of an agency, such as litigation arguments.”
Syl. Pt. 6, Martin v. Randolph Cnty. Bd. of Educ., 195 W. Va. 297, 465 S.E.2d 399 (1995).
Hence, we examine the remaining three conditions to assess whether the circuit court was
correct in its assessment those conditions were met.
Under the second condition in Section 2(b), there must be proof the error
materially affected the bid, that is, that the error “must have a material[, adverse] effect on
the agreed exchange of performances.” Restatement (Second) of the Law, Contracts, § 153
cmt. b. A mistake is material when it “has prevented a true ‘meeting of the minds[.]” 1
Bruner & O’Connor on Construction Law § 2:133. In its solicitation for bid proposals, the
DOH established removing and replacing 177 feet of expansion joints as a separate line
item that required a separate, detailed bid. Olympus’s error related exclusively to that
consequential, material item in the contract. Moreover, the clerical error was material in
that it made the bid significantly different from what the owner of Olympus intended it to
be, resulting in a proposal $708,000 lower than intended. The substantial difference
between the figure intended and the figure inserted into the bid, on a consequential element
of the contract, establishes that Olympus had no “meeting of the minds” with the DOH to
24 form a contract based on the erroneous bid. On this record, we see no error by the circuit
court that the error was material.14
The third condition of Section 2(b) is that there must be proof that rejection
of the erroneous bid would not cause a hardship on the government agency involved, other
than losing the opportunity to receive the goods or services at a reduced cost. The record
shows that the DOH received notice from Olympus of the error in the bid proposal within
three business days; when Olympus sought to be relieved from its bid under Section 2,
DOH summarily declared that it did not believe a mistake had occurred and declared
Olympus the winning bidder. On this record, it appears that if DOH had promptly
conducted the Section 2(b) analysis, it could have awarded the contract to the second-
lowest bidder within days. Instead, the DOH sought to take advantage of Olympus’s overly
low bid and thereby incurred lost time and higher costs for the taxpayer. This case arose
during the COVID-19 pandemic and material costs increased at a dramatic pace. Because
DOH did not let the contract promptly to the next-lowest bidder (as permitted by Section
2(c)), it was forced to advertise and solicit new bids in the Fall of 2021 at a much higher
14 Moreover, the record indicates that counsel for the DOH conceded to the trial court that Olympus’s error “is enough of an amount to be a material effect of a bid.” App’x at 571.
25 price, and the work was not performed until the following year. We find this third condition
established by the record.15
The fourth and final condition is that there must be proof that enforcement
of the erroneous bid would be unconscionable. “The element of unconscionability
addresses the magnitude of the unilateral mistake.” 1 Bruner & O’Connor on Construction
Law § 2:140. “Cases suggest that a pecuniary loss of as little as 10% may be deemed
‘unconscionable’ in apparent recognition of the notoriously low profit margins prevailing
in the construction industry.” Id.16 Unconscionability has been described as a bargain that
“no man in his senses and not under delusion would make on the one hand, and as no honest
and fair man would accept on the other[.]” McGinnis v. Cayton, 173 W. Va. 102, 113, 312
S.E.2d 765, 776 (1984) (Harshbarger, J., concurring) (quoting Hume v. United States, 132
Further, counsel for DOH conceded to the circuit court that “[r]ejection of the bid 15
would not cause hardship on the public entity involved, other than the fact that the project would – might cost more. . . We don’t believe there would be any additional harm to the Department.” App’x at 571-572. 16 Bruner and O’Connor go on to suggest in their treatise that:
Unconscionability presumes a degree of hardship that depends not only on the magnitude of the error, in comparison to the size of the bid, but also on the profit that the bidder will make or the loss that the bidder will sustain if required to perform. The difference between unconscionability and materiality is that a mistake may be material to price but nevertheless not unconscionable because anticipated profit is sufficient to absorb the mistake.
1 Bruner & O’Connor Construction Law § 2:140 (quotation and footnotes omitted).
26 U.S. 406, 411 (1889), quoting Earl of Chesterfield v. Janssen, 28 Eng.Rep. 82, 100 (Ch.
1750)). The evidence of record indicates that the $708,000 understatement in Olympus’s
bid proposal was approximately 14% of its bid, an amount its owner stated was
“catastrophic” to the company. Accordingly, we see no error in the circuit court’s
conclusion that the fourth condition was established by Olympus.
In summary, the record shows that Olympus established the second, third,
and fourth conditions required by Section 2(b). The DOH did not conduct a proper analysis
of those conditions when Olympus notified the DOH of the error in its bid proposal, and
we see no error in the circuit court’s analysis. However, regarding the first condition,
whether “[a]n error was made,” we find that the circuit court should have weighed whether
to afford deference to the DOH’s finding that error did not occur. Essentially, under the
existing record, we direct the circuit court to assess whether the DOH’s determination that
“the Olympus bid is not an error” was arbitrary, capricious, or an abuse of discretion, in
light of the evidence. If the circuit court again concludes that the DOH should have rejected
Olympus’s bid proposal due to errors, then the DOH should not have sought to compel
Olympus to perform the contract under the terms of the faulty bid. And if Olympus could
not be compelled to perform the contract, and should have been relieved from its bid
proposal, then Olympus had no duty to sign the contract and the DOH has no authority to
proceed against Olympus’s bid bond.
27 IV. CONCLUSION
The circuit court’s summary judgment order in favor of Olympus on the
second, third, and fourth conditions in Section 2(b) is supported by the record, and it must
be affirmed. The circuit court’s order regarding the first condition is vacated, and the case
is remanded for further proceedings as outlined above.
Affirmed, in part, vacated, in part, and remanded with directions.