Harrison v. City of Huntington

93 S.E.2d 221, 141 W. Va. 774, 1956 W. Va. LEXIS 28
CourtWest Virginia Supreme Court
DecidedJune 12, 1956
Docket10815, 10816
StatusPublished
Cited by4 cases

This text of 93 S.E.2d 221 (Harrison v. City of Huntington) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harrison v. City of Huntington, 93 S.E.2d 221, 141 W. Va. 774, 1956 W. Va. LEXIS 28 (W. Va. 1956).

Opinion

Given, Judge:

Plaintiffs George B. Harrison, O. H. Hines, John H. Druen and Eugene T. Brennan, as residents and taxpayers of the City of Huntington, instituted their suit against defendants, the City of Huntington, George E. Theurer as Mayor, Nichols & Ronk, Inc., and Middle States Asphalt Corporation, the last named two defendants being paving contractors, praying an injunction restraining defendants from paving certain streets in the City of Huntington, as required by certain contracts entered into between the city and the contractors. The Circuit Court of Cabell County, by order of November 18, 1955, perpetuated a temporary injunction previously awarded, granting the relief sought. Separate appeals from the final order were granted defendant contractors by this Court, which appeals were consolidated and are heard together.

The voters of the City of Huntington, on July 7, 1955, authorized the issuance of bonds, in the amount of $650,-000.00 for the improvement of certain streets within the city. After the preparation of plans and specifications and the advertising for bids, two bids were received, one *776 from each of the contractors named above, each for approximately one half of the amount of the work to be done. At a regular meeting of the City Council of the City of Huntington, held on September 12, 1955, the council rejected the bids. The original specifications required that the contractor to whom the contract might be awarded should commence work thereunder within ten days from the date of the contract, and complete such work within sixty days. Before the date fixed in the advertisement for the opening of the bids, the city, acting through its city engineer, who was responsible for the preparation of the plans and specifications, authorized or directed a change in such plans or specifications whereby the time to be allowed for the completion of the performance of the contract was changed from “sixty days from date of award”, to read “sixty working days from date of award”. The wording of the amendment was carried into the contracts executed between the city and the defendant contractors. All contractors who contemplated bidding on the proposed improvements, and who received from the city officials copies of the plans and specifications, were notified of the authorization of such amendment. Three days later, September 15, 1955, by notice signed by three members of the city council, a special meeting of the city council was called for September 19, 1955. The purposes for which the meeting was called, as stated in the notices, were: “1. To reconsider the action taken on Monday, September 12, 1955, on the motion to reject the bids which were made September 10, 1955, and readvertise for new bids with the time limit taken out and new bids to read thirty days to move in, do what work to be done this fall and a time limit of July 31, 1956, to have the job finished. 2. To reconsider the report from the City Engineer on bids received on September 10, 1955, for paving various projects under the Street Improvement Program. 3. To take whatever action may be deemed necessary to effect the acceptance of bids and the letting of contracts for paving the various projects under the Street Improvement Program.”

*777 At the special meeting a motion was made “that the action of Council taken on September 12, 1955, to reject the bids received September 10, 1955, and readvertise for new bids with the time limit taken out, new bids to read 30 days to move in and go to work, do what can be done this fall and a time limit of July 31, 1956, to have the job completed be rescinded, repealed, nullified, and vacated.” The motion was duly seconded and carried by a vote of eight to four, one member being absent. After further consideration of business before the council, a motion was made, duly seconded, that “the report of the City Engineer be accepted and that the low bids submitted September 10, 1955, for paving various projects under the Street Improvement Program be accepted and that Middle States Asphalt Corporation of Ashland, Kentucky, be awarded the contract on designated Group No. 2 and the bid of $342,302.43 be accepted ; and Nichols & Ronk be awarded the contract on designated Group No. 1 and the bid of $299,749.77 be accepted.” The motion carried by a vote of eight to four, one member being absent. Subsequently, the contracts here involved were executed by the city and the defendant contractors.

The grounds of attack on the contracts are that there was collusive action on the part of certain city officials and bidders which stifled competitive bidding, thus rendering the contracts fraudulent and void; that the amendment authorized to be made in the specifications, whereby the contractor was given “60 working days” instead of “sixty days” to complete the work to be performed, was such a material change as to render the contracts void; and that the council having once rejected the bids, it could not, at a later meeting thereof, by a motion to reconsider, annul the action of the council whereby the bids were rejected, and thereafter authorize the acceptance of the bids.

The trial chancellor found that plaintiffs “failed to prove collusion”, and failed to prove that any officer or *778 agent of the City of Huntington had “intentionally or otherwise imposed restrictions on bidding for the purpose of giving the contract to the defendants” to whom the contracts were let, and that plaintiffs had “failed to prove that the changes in the plans and specifications from sixty days to sixty working days was a material change or that such change prevented or discouraged competitive bidding.” The findings are clearly supported by the evidence, and preclude a reconsideration thereof by this Court.

The position of plaintiffs, that the contracts are ultra vires and void, is based, principally at least, on the nature of the motion by which the city council attempted to annul its own prior action in rejecting the bids at the council meeting of September 12,1955. They contend that the motion was a motion to reconsider, and that the council, because of parliamentary rules by which it was bound, was without power to entertain such a motion, unless made by a member of the council who had voted with the prevailing side, and unless made at the same council meeting at which the vote on the original motion was taken. The argument supporting plaintiffs’ position is based largely on the use of the word “reconsider” in the notice, quoted above, calling the special council meet-ting. Plaintiffs point out that by an ordinance of the City of Huntington it is provided: “In all cases, a motion to reconsider will be entertained only when made by a member who voted with the prevailing side. A majority of those present can consider any vote, but the motion to do so shall be made at the same session of the Council during which such vote was taken.” It is also pointed out that an ordinance of the City of Huntington provides: “The proceedings of the Council, except as otherwise provided for, shall be governed by Karcher’s Handbook of Parliamentary Law”. In so far as pertinent, the provisions of Karcher’s Handbook of Parliamentary Law read: “TO RESCIND This motion is not in frequent use. As its name implies, its purpose is to cancel out or nullify some prior action of the assem *779 bly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sticklen v. Kittle
287 S.E.2d 148 (West Virginia Supreme Court, 1981)
A & D Construction, Inc. v. City of Vineland
418 A.2d 1319 (New Jersey Superior Court App Division, 1980)
Pioneer Co. v. Hutchinson
220 S.E.2d 894 (West Virginia Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
93 S.E.2d 221, 141 W. Va. 774, 1956 W. Va. LEXIS 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harrison-v-city-of-huntington-wva-1956.