Surface America, Inc. v. United Surety & Indemnity Co.

867 F. Supp. 2d 282, 2012 U.S. Dist. LEXIS 83143, 2012 WL 2161628
CourtDistrict Court, D. Puerto Rico
DecidedJune 15, 2012
DocketCivil No. 11-1722 (FAB)
StatusPublished
Cited by1 cases

This text of 867 F. Supp. 2d 282 (Surface America, Inc. v. United Surety & Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Surface America, Inc. v. United Surety & Indemnity Co., 867 F. Supp. 2d 282, 2012 U.S. Dist. LEXIS 83143, 2012 WL 2161628 (prd 2012).

Opinion

OPINION AND ORDER1

BESOSA, District Judge.

Plaintiff Surface America, Inc. (“Surface”), brings a suit alleging the breach of a payment bond contract by defendant United Surety & Indemnity Company (“USIC”), a Puerto Rico corporation. (See Docket No. 1.) Before the Court are the motion to dismiss and the motion for summary judgment filed by defendant. (Docket No. 10.) For the reasons set forth below, defendant’s motion to dismiss is GRANTED and its motion for summary judgment is deemed MOOT.

DISCUSSION

I. Background

On an unspecified date, the Public Housing Administration of Puerto Rico (“the Administration”) entered into a contract with contractor Equipex International, Inc. (“Equipex”), in which the latter agreed to build playgrounds on a number of sites overseen by the Administration.2 (See Docket No. 1.) On November 2, 2009, contractor Equipex entered into a subcontract with plaintiff Surface, a New York-based firm, by which plaintiff would supply and install nearly 40,000 square-feet of rubber floors in six of the Administration’s sites. (Docket No. 1 at ¶ 4.) The subcontract between contractor Equipex and plaintiff Surface included the following provision: “Should Contractor [Equipex] fail to make payment in full within payment terms, Subcontractor [Surface] shall be entitled to recover all collection, costs, including but not limited to court costs and legal fees, incurred by Subcontractor [Surface] as a result thereof.” (Docket No. 1, Exhibit I, Article 7.) (emphasis added.)

On October 7, 2009, contractor Equipex obtained from defendant USIC a payment bond contract “in order to guarantee, among other things, payment by Defendant [USIC] to subcontractors” upon completion of the project. (Docket No. 1 at ¶ 5.) The payment bond contract provides that in the event contractor Equipex is unable to pay its subcontractors, defendant USIC shall “make payments to all persons supplying labor and material and in the prosecution of the work provided for in said contract ...” (Docket No. 1, Exhibit II.) Nowhere does the payment bond contract mention the subcontract between plaintiff Surface and contractor Equipex; nor does it provide that plaintiff Surface is entitled to recover court costs or legal fees directly from defendant USIC.

Work on the project commenced in November 2009, and was completed sometime in December 2010. (Docket No. 1 at ¶ 6.) According to the subcontract between plaintiff Surface and contractor Equipex, “Contractor [Equipex] shall pay Subcontractor [Surface] within 5 (five) days of Contractor [Equipex]’s receipt of payment from Owner [the Administration]. If payment from Owner [the Administration] is not received by Contractor [Equipex] through no fault of Subcontractor [Sur[285]*285face], Contractor [Equipex] shall make payment to Subcontractor [Surface] within 30 (thirty) days after a location reaches substantial completion, whichever comes first.” (Docket No. 1, Exhibit I, Article 7.) On March 8, 2010, approximately three months after work had been completed, plaintiff Surface sent a letter to defendant USIC explaining that contractor Equipex had failed to make payment on $350,557.65 still owed to plaintiff. (Docket No. 1, Exhibit III.) Sometime before March 31, 2010, contractor Equipex made a partial payment to plaintiff Surface in the amount of $250,000.00. (Docket No. 1 at ¶ 15.) Plaintiff Surface then sent a letter to defendant USIC demanding payment of the remaining $130,557.65 still owed by Equipex. Id. On April 7, 2010, defendant USIC responded, indicating that it had closed plaintiffs claim without payment. (Docket No. 1 at ¶ 16.) Plaintiff Surface sent another letter to defendant USIC, on April 26, 2010, stating that it had received from Equipex a second partial payment of $65,278.83. In the same letter, plaintiff Surface suggested that if defendant USIC were to make the remaining and final payment of $65,278.82, plaintiff Surface would forgo any claim against defendant. (Docket No. 1 at ¶ 18.) Defendant USIC declined to accept this offer and did not make payment. Throughout June 2010, plaintiff Surface issued several insistent demands for payment of the remaining balance, all of which were rebuffed by defendant USIC. (Docket No. 1 at ¶¶ 19-21.) Finally, on August 13, 2010, plaintiff Surface made one last attempt through its attorney to obtain payment from defendant. (Docket No. 1 at ¶ 22.) This attempt was rebuffed by defendant USIC on October 4, 2010. (Docket No. 1 at ¶ 23.)

Plaintiff Surface now brings suit against defendant USIC for damages arising from two separate causes of action. {See Docket No. 1.) The first, a breach-of-contract claim, calculates damages of $65,278.82 pursuant to defendant’s payment bond contract with contractor Equipex. Id. at ¶ 19. The second claim, predicated on defendant’s “negligent attitude ... in regards to the payment of this debt,” calculates damages of $14,941.72 in “costs, interest and attorney’s fees.” Id. at ¶25. Plaintiff seeks to establish jurisdiction on grounds of diversity, pursuant to 28 U.S.C. § 1332(a) (section 1332(a)), by aggregating the outstanding payment of $65,278.83 with the $14,941.72 in attorney’s fees. (Docket No. 1 at p. 1 & ¶ 25.) Simple addition reveals $80,220.02 in total damages.

Defendant USIC has filed a motion to dismiss, pursuant to Federal Rule of Civil Procedure 12(b)(1) (“Rule 12(b)(1)”),3 arguing that federal jurisdiction is lacking because plaintiffs claim fails to meet the minimum amount-in-controversy stipulated by section 1332. (Docket No. 10 at pp. 2-3.) Defendant does not ardently contest the breach-of-contract claim; in fact, at several points in its motion to dismiss, defendant nearly admits to owing the sum of $65,278.83. (Docket No. 10 at pp. 3 & 6.) Defendant does, however, ferociously contest the second cause of action. Defendant alleges that plaintiff is forbidden from seeking attorney’s fees as part of its damages, and therefore that plaintiffs amount in controversy consists only of $65,278.83, well below the $75,000.00 requirement. Id. Defendant has also filed a motion for summary judgment, arguing that disputes concerning “tax obligations and payment of worker’s compensation insurance” remain unresolved between plaintiff Surface and contractor Equipex; that until these disputes are addressed by both parties, [286]*286“the amount that might be due [plaintiff] Surface is not certain”; and, therefore, that plaintiff Surface has failed to include an indispensable party (Equipex) in its suit.4 (Docket No. 10 at pp. 6-9.)

On October 3, 2011, plaintiff filed an opposition to defendant’s motions. (See Docket No. 11.) Plaintiff challenges defendant’s assertion that parties are typically prohibited from seeking attorney’s costs as part of damages. (Docket No. 11 at pp. 1-4.) Without citing a shred of case law, but presumably relying on Supreme Court precedent explicated by Judge Easterbrook of the Seventh Circuit Court of Appeals,5 plaintiff draws a distinction between fees incurred before filing a complaint (“damages”), and fees incurred after filing a complaint (“costs”). (Docket No. 11 at p. 2.) Plaintiff concedes that attorney’s costs incurred during litigation are off limits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
867 F. Supp. 2d 282, 2012 U.S. Dist. LEXIS 83143, 2012 WL 2161628, Counsel Stack Legal Research, https://law.counselstack.com/opinion/surface-america-inc-v-united-surety-indemnity-co-prd-2012.