Sleeper Village v. NGM Ins.

2010 DNH 064
CourtDistrict Court, D. New Hampshire
DecidedApril 9, 2010
DocketCV-09-44-PB
StatusPublished

This text of 2010 DNH 064 (Sleeper Village v. NGM Ins.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sleeper Village v. NGM Ins., 2010 DNH 064 (D.N.H. 2010).

Opinion

Sleeper Village v . NGM Ins. CV-09-44-PB 4/9/10

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Sleeper Village, LLC

v. Case N o . 09-cv-44-PB Opinion N o . 2010 DNH 064 NGM Insurance Co.

MEMORANDUM AND ORDER

Sleeper Village, LLC, the owner of a residential housing

development project, has filed a petition for declaratory

judgment and damages seeking to recover on a performance bond

issued by NGM Insurance Company. NGM contends that it is

entitled to summary judgment for two reasons. First, it argues

that Sleeper Village is not entitled to recover because it failed

to comply with Section 3.3 of the bond, which specifies that an

owner’s declaration of contractor default does not become

effective unless the owner agrees to pay the contract’s unpaid

balance either to the surety or a contractor selected to complete

the project. Next, it argues that Sleeper Village failed to

fulfill its obligations under Section 5 of the bond, which in

most cases obligates the owner to submit a separate written notice to the surety stating that the surety is in default and

demanding that the default be corrected. I address each argument

in turn.

I. Section 3.3

Section 3.3 of the performance bond states that a surety’s

obligation under the bond does not arise until, among other

things, the owner “has agreed to pay the Balance of the Contract

Price to the Surety in accordance with the terms of the

Construction Contract or to a contractor selected to perform the

Construction Contract in accordance with the terms of the

Contract with the Owner.” (Def.’s Mot. for Summ. J. Ex. 2 , Doc.

N o . 10-3, § 3.3.) NGM argues that Sleeper Village did not comply

with this provision because it never explicitly agreed to pay the

balance of the contract price to a new contractor.

Alternatively, it argues that Sleeper Village failed to comply

with Section 3.3 because it failed to specifically identify the

balance of the contract price that was available to fund the

completion of the contract. Neither argument is persuasive.

On April 9, 2007, Sleeper Village wrote to Moulton

Construction, Inc., the contractor on whose behalf NGM had issued

the performance bond, declaring a contractor default and

-2- terminating the contractor’s right to complete the bonded

project.1 (See Def.’s Mot. for Summ. J. Ex. 6, Doc. N o . 10-7, at

2-3.) Sleeper Village’s attorney forwarded this letter to NGM’s

attorney with a cover letter that (1) referred to Section 3.3 and

included language that, although not in quotation marks, was

directly taken from that section; (2) informed NGM that it had

identified a contractor that was willing to complete the

contract; and (3) stated that Sleeper Village was “prepared to

execute a construction contract for the completion of the work at

its earliest convenience.” (Def.’s Mot. for Summ. J. Ex. 6, Doc.

N o . 10-7, at 1.) Although the cover letter does not precisely

track the language of Section 3.3, it is clear that Sleeper

Village was agreeing to pay the balance of the contract price to

a contractor selected to perform the contract. There is no doubt

that NGM recognized that this was Sleeper Village’s intention

because an NGM attorney stated, in response to the notice of

1 Sleeper Village provisionally wrote to NGM on January 3 0 , 2007 to notify it that it was considering declaring a contractor default. Thereafter, Sleeper Village arranged a conference with NGM and the contractor to discuss methods of performing the contract. The undisputed facts thus establish that Sleeper Village complied with its obligation under the bond to notify the surety that it was considering declaring a contractor default.

-3- contractor default, “I construe the intent of your letter as a

declaration of Contractor Default as well as Sleeper Village

pledging contract balances for the completion of the project, but

you have not stated so in your letter . . . .” (Def.’s Mot. for

Summ. J. Ex. 1 0 , Doc. N o . 10-11, at 1.) Under these

circumstances, NGM is in no position to fault Sleeper Village for

failing to make its intentions clear.

With regard to NGM’s second argument, although Sleeper

Village did not disclose the balance of the contract price in its

notice of default, the performance bond does not obligate it to

do s o . Thus, Sleeper Village did not violate Section 3.3 by

failing to disclose the unpaid balance on the contract.

II. Section 5

When a contractor default is declared, a surety may: (1)

arrange for the contractor to complete the project with the

owner’s consent; (2) complete the project itself; or (3) obtain

bids from other contractors and arrange for the owner to contract

with a new contractor to complete the project. (See Def.’s Mot.

for Summ. J. Ex. 2 , Doc. N o . 10-3, § 4.) Alternatively, the

surety may waive its right to exercise these options and either

pay the balance owed directly to the owner or deny liability and

-4- provide a statement of reasons. (See id.) In the event that the

surety fails to act on a notice of contractor default with

reasonable promptness, Section 5 provides that “the Surety shall

be . . . in default on this Bond fifteen days after receipt of an

additional written notice from the Owner to the Surety demanding

that the Surety perform its obligations under this Bond . . . .”

(Id. § 5.) Section 5 further specifies, however, that the

additional written notice requirement does not apply in the event

that the surety waives its right to alternative remedies and

either denies liability or pays what it owes directly to the

owner.

NGM invokes Section 5 in arguing that it is entitled to

summary judgment. Sleeper Village responds by claiming that

Section 5 did not obligate it to provide a notice of surety

default because NGM waived its right to alternative remedies and

agreed to pay the amount owed directly to Sleeper Village. I

agree with NGM.

Although Sleeper Village’s attorney’s April 9, 2007 cover

letter regarding the notice of contractor default suggests that

the “most appropriate route” would be for NGM to waive its right

to alternative remedies and pay the amount owed on the bond

-5- directly to Sleeper Village, NGM’s attorney’s response clearly

states, “I cannot agree or disagree that [waiver of alternative

remedies] is the most appropriate route.” (Def.’s Mot. for Summ.

J. Ex. 6, Doc. N o . 10-7, at 1 ; Def.’s Mot. for Summ. J. Ex. 1 0 ,

Doc. N o . 10-11, at 2.) The response further states, “So there is

no misunderstanding, [NGM] is not waiving any rights it may have

. . . under either the construction contract or its bond, or by

law, regardless of whether Sleeper Village decides it wishes to

terminate [the contractor] and hire a new contractor to complete

the project.” (Def.’s Mot. for Summ. J. Ex. 1 0 , Doc. N o . 10-11,

at 3.) Under these circumstances, it is quite clear that NGM did

not waive its right to alternative remedies. Thus, Section 5

obligated Sleeper Village to issue a notice of surety default

before exercising its rights under the bond.

CONCLUSION

NGM is entitled to partial summary judgment with respect to

its contention that Sleeper Village failed to provide the notice

Free access — add to your briefcase to read the full text and ask questions with AI

Related

St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
2010 DNH 064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sleeper-village-v-ngm-ins-nhd-2010.