Sleeper Village v. NGM Ins.
This text of 2010 DNH 064 (Sleeper Village v. NGM Ins.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Sleeper Village v . NGM Ins. CV-09-44-PB 4/9/10
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Sleeper Village, LLC
v. Case N o . 09-cv-44-PB Opinion N o . 2010 DNH 064 NGM Insurance Co.
MEMORANDUM AND ORDER
Sleeper Village, LLC, the owner of a residential housing
development project, has filed a petition for declaratory
judgment and damages seeking to recover on a performance bond
issued by NGM Insurance Company. NGM contends that it is
entitled to summary judgment for two reasons. First, it argues
that Sleeper Village is not entitled to recover because it failed
to comply with Section 3.3 of the bond, which specifies that an
owner’s declaration of contractor default does not become
effective unless the owner agrees to pay the contract’s unpaid
balance either to the surety or a contractor selected to complete
the project. Next, it argues that Sleeper Village failed to
fulfill its obligations under Section 5 of the bond, which in
most cases obligates the owner to submit a separate written notice to the surety stating that the surety is in default and
demanding that the default be corrected. I address each argument
in turn.
I. Section 3.3
Section 3.3 of the performance bond states that a surety’s
obligation under the bond does not arise until, among other
things, the owner “has agreed to pay the Balance of the Contract
Price to the Surety in accordance with the terms of the
Construction Contract or to a contractor selected to perform the
Construction Contract in accordance with the terms of the
Contract with the Owner.” (Def.’s Mot. for Summ. J. Ex. 2 , Doc.
N o . 10-3, § 3.3.) NGM argues that Sleeper Village did not comply
with this provision because it never explicitly agreed to pay the
balance of the contract price to a new contractor.
Alternatively, it argues that Sleeper Village failed to comply
with Section 3.3 because it failed to specifically identify the
balance of the contract price that was available to fund the
completion of the contract. Neither argument is persuasive.
On April 9, 2007, Sleeper Village wrote to Moulton
Construction, Inc., the contractor on whose behalf NGM had issued
the performance bond, declaring a contractor default and
-2- terminating the contractor’s right to complete the bonded
project.1 (See Def.’s Mot. for Summ. J. Ex. 6, Doc. N o . 10-7, at
2-3.) Sleeper Village’s attorney forwarded this letter to NGM’s
attorney with a cover letter that (1) referred to Section 3.3 and
included language that, although not in quotation marks, was
directly taken from that section; (2) informed NGM that it had
identified a contractor that was willing to complete the
contract; and (3) stated that Sleeper Village was “prepared to
execute a construction contract for the completion of the work at
its earliest convenience.” (Def.’s Mot. for Summ. J. Ex. 6, Doc.
N o . 10-7, at 1.) Although the cover letter does not precisely
track the language of Section 3.3, it is clear that Sleeper
Village was agreeing to pay the balance of the contract price to
a contractor selected to perform the contract. There is no doubt
that NGM recognized that this was Sleeper Village’s intention
because an NGM attorney stated, in response to the notice of
1 Sleeper Village provisionally wrote to NGM on January 3 0 , 2007 to notify it that it was considering declaring a contractor default. Thereafter, Sleeper Village arranged a conference with NGM and the contractor to discuss methods of performing the contract. The undisputed facts thus establish that Sleeper Village complied with its obligation under the bond to notify the surety that it was considering declaring a contractor default.
-3- contractor default, “I construe the intent of your letter as a
declaration of Contractor Default as well as Sleeper Village
pledging contract balances for the completion of the project, but
you have not stated so in your letter . . . .” (Def.’s Mot. for
Summ. J. Ex. 1 0 , Doc. N o . 10-11, at 1.) Under these
circumstances, NGM is in no position to fault Sleeper Village for
failing to make its intentions clear.
With regard to NGM’s second argument, although Sleeper
Village did not disclose the balance of the contract price in its
notice of default, the performance bond does not obligate it to
do s o . Thus, Sleeper Village did not violate Section 3.3 by
failing to disclose the unpaid balance on the contract.
II. Section 5
When a contractor default is declared, a surety may: (1)
arrange for the contractor to complete the project with the
owner’s consent; (2) complete the project itself; or (3) obtain
bids from other contractors and arrange for the owner to contract
with a new contractor to complete the project. (See Def.’s Mot.
for Summ. J. Ex. 2 , Doc. N o . 10-3, § 4.) Alternatively, the
surety may waive its right to exercise these options and either
pay the balance owed directly to the owner or deny liability and
-4- provide a statement of reasons. (See id.) In the event that the
surety fails to act on a notice of contractor default with
reasonable promptness, Section 5 provides that “the Surety shall
be . . . in default on this Bond fifteen days after receipt of an
additional written notice from the Owner to the Surety demanding
that the Surety perform its obligations under this Bond . . . .”
(Id. § 5.) Section 5 further specifies, however, that the
additional written notice requirement does not apply in the event
that the surety waives its right to alternative remedies and
either denies liability or pays what it owes directly to the
owner.
NGM invokes Section 5 in arguing that it is entitled to
summary judgment. Sleeper Village responds by claiming that
Section 5 did not obligate it to provide a notice of surety
default because NGM waived its right to alternative remedies and
agreed to pay the amount owed directly to Sleeper Village. I
agree with NGM.
Although Sleeper Village’s attorney’s April 9, 2007 cover
letter regarding the notice of contractor default suggests that
the “most appropriate route” would be for NGM to waive its right
to alternative remedies and pay the amount owed on the bond
-5- directly to Sleeper Village, NGM’s attorney’s response clearly
states, “I cannot agree or disagree that [waiver of alternative
remedies] is the most appropriate route.” (Def.’s Mot. for Summ.
J. Ex. 6, Doc. N o . 10-7, at 1 ; Def.’s Mot. for Summ. J. Ex. 1 0 ,
Doc. N o . 10-11, at 2.) The response further states, “So there is
no misunderstanding, [NGM] is not waiving any rights it may have
. . . under either the construction contract or its bond, or by
law, regardless of whether Sleeper Village decides it wishes to
terminate [the contractor] and hire a new contractor to complete
the project.” (Def.’s Mot. for Summ. J. Ex. 1 0 , Doc. N o . 10-11,
at 3.) Under these circumstances, it is quite clear that NGM did
not waive its right to alternative remedies. Thus, Section 5
obligated Sleeper Village to issue a notice of surety default
before exercising its rights under the bond.
CONCLUSION
NGM is entitled to partial summary judgment with respect to
its contention that Sleeper Village failed to provide the notice
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2010 DNH 064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sleeper-village-v-ngm-ins-nhd-2010.