Schuff Steel Company v. Bosworth Steel Erectors, Inc.

CourtDistrict Court, District of Columbia
DecidedFebruary 21, 2024
DocketCivil Action No. 2018-0435
StatusPublished

This text of Schuff Steel Company v. Bosworth Steel Erectors, Inc. (Schuff Steel Company v. Bosworth Steel Erectors, Inc.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schuff Steel Company v. Bosworth Steel Erectors, Inc., (D.D.C. 2024).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

SCHUFF STEEL CO.,

Plaintiff,

v. Civil Action No. 18-cv-435 (TSC) BOSWORTH STEEL ERECTORS, INC., et al.,

Defendants.

MEMORANDUM OPINION

Plaintiff Schuff Steel Co. (“Schuff”) sued its subcontractor Defendant Bosworth Steel

Erectors, Inc. (“Bosworth”) and surety Travelers Casualty and Surety Company of America

(“Travelers”) after Bosworth failed to complete its subcontract work and Schuff took over. In a

previous Opinion (ECF No. 79), the court denied summary judgment to both Schuff and

Bosworth regarding breach of the subcontract, but granted summary judgment to Travelers,

holding that Travelers did not breach the bond because Schuff failed to give it notice and an

opportunity to cure. Schuff Steel Co. v. Bosworth Steel Erectors, No. 18-cv-435, 2022 WL

4534729 (D.D.C. Sept. 28, 2022). Schuff and Bosworth have now cross moved for summary

judgment regarding whether Bosworth can be held liable for its failure to complete the

subcontract work under the surety bond.

Having considered the record and the parties’ briefs, the court will GRANT Schuff’s

Motion for Summary Judgment, ECF No. 82, and DENY Bosworth’s Cross Motion for

Summary Judgment, ECF No. 83. Bosworth was required to complete the subcontract work or

Page 1 of 9 face liability under the plain terms of the surety bond, and the parties do not dispute that

Bosworth failed to complete the subcontract work. Consequently, it is liable under the bond.

I. BACKGROUND

Schuff and Bosworth were two of the subcontractors that constructed the D.C. United

Soccer Stadium now known as Audi Field. Mem. Op., ECF No. 79 at 2. The general contractor

subcontracted steel work to Schuff, which further subcontracted with Bosworth. Id. The

subcontract required Bosworth to obtain a surety bond, which it executed with Travelers. Id.

at 3. The bond named Bosworth as principal, Travelers as surety, and Schuff as oblige. Id.

The Audi Field construction did not go as planned. After a problem with erecting the

scoreboard, Schuff notified Bosworth that it intended to terminate the subcontract due to default,

id. at 7, and notified Travelers, id. at 8. Schuff also filed this suit against Bosworth and

Travelers, seeking damages for breach of contract against Bosworth (Count I) and damages for

breach of the surety bond against Bosworth and Travelers, jointly and severally (Count II).

Compl., ECF No. 1 ¶¶ 28–40. Bosworth filed two counterclaims. First Am. Countercl., ECF

No. 19 ¶¶ 29–54. Following discovery, Schuff and Bosworth cross moved for summary

judgment on Count I and the counterclaims, ECF Nos. 57, 69, and Schuff and Travelers cross

moved for summary judgment on Count II, ECF Nos. 56, 67.

The court denied Bosworth’s and Schuff’s cross motions for summary judgment, finding

genuine issues of material fact regarding breach of the subcontract. Mem. Op. at 13–20. But the

court granted Travelers’ motion for summary judgment and denied Schuff’s cross motion on

Count II, concluding that Travelers did not breach the bond. Id. at 22. Because Schuff and

Bosworth did not move for summary judgment against each other on Count II, the court’s

opinion left unresolved Count II against Bosworth. Id. at 23. Schuff and Bosworth subsequently

Page 2 of 9 cross moved for summary judgment on Count II, regarding whether Bosworth is liable under the

bond. ECF Nos. 82, 83.

II. LEGAL STANDARD

Under Federal Rule of Civil Procedure 56, courts “shall grant summary judgment if the

movant shows that there is no genuine dispute as to any material fact and the movant is entitled

to judgment as a matter of law.” Fed. R. Civ. P. 56(a). A fact is material if “a dispute over it

might affect the outcome of a suit under governing law; factual disputes that are ‘irrelevant or

unnecessary’ do not affect the summary judgment determination.” Holcomb v. Powell, 433 F.3d

889, 895 (D.C. Cir. 2006) (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986)).

An issue is genuine if “the evidence is such that a reasonable jury could return a verdict for the

nonmoving party.” Id. (quoting Anderson, 477 U.S. at 248).

The party seeking summary judgment bears the initial burden to provide evidence

demonstrating “the absence of a genuine issue of material fact.” Celotex Corp. v. Catrett, 477

U.S. 317, 323 (1986). “When parties file cross motions for summary judgment, each motion is

viewed separately, in the light most favorable to the non-moving party, with the court

determining, for each side, whether a judgment may be entered in accordance with the Rule 56

standard.” Howard Town Ctr. Dev., LLC v. Howard Univ., 267 F. Supp. 3d 229, 236 (D.D.C.

2017) (internal quotation omitted).

III. ANALYSIS

A. Bosworth was Bound by the Surety Bond

At the outset, the parties disagree as to whether Bosworth was bound by the surety bond

at all: Bosworth claims it was not bound, but Schuff argues that it was. Compare Mem. in Supp.

of Mot. for Summ. J., ECF No. 82-1 at 5–6 (“Motion”), with Mem. in Opp’n to Pl.’s Mot. for

Summ. J. & in Supp. of Cross Mot. for Summ. J., ECF No. 83-1 at 6–8, 13–14 (“Cross Motion”). Page 3 of 9 As the court previously acknowledged, District of Columbia law applies to this dispute.

See Mem. Op. at 20–21. Under District law, “the written language embodying the terms of an

agreement will govern the rights and liabilities of the parties.” Dyer v. Bilaal, 983 A.2d 349,

354–55 (D.C. 2009) (citation omitted). “In other words, a party’s unexpressed intent is irrelevant

if a contract is unambiguous.” Id. at 355. Here, the surety bond unambiguously binds Bosworth

by its terms. It was signed by Bosworth, it states that Bosworth and Travelers both “bind

themselves,” and it makes Bosworth and Travelers jointly and severally liable for the full amount

of the subcontract work. Subcontract Performance Bond, ECF No. 82-4 at 1–4. Thus, the plain

language suggests the bond makes Bosworth liable so long as the condition precedent is met—

Bosworth fails to “perform the Construction Work to be done under the Subcontract.” Id. at 1, 3.

Moreover, Bosworth’s obligation to Schuff under the bond is not inextricably linked to

Travelers’. Bosworth and Travelers have bonded themselves “jointly and severally.” Id. at 3.

As the Supreme Court has explained, “a joint and several contract . . . contains distinct

engagements, that of each contractor individually, and that of all jointly.” Mason v. Eldred, 73

U.S. 231, 235 (1867). That means contracting parties “may be sued separately on their several

engagements or together on their joint undertaking.” Id.; accord 12 Williston on Contracts

§ 36.1 (4th ed.) (In a joint and several contract, “each party is bound separately for the

performance for which it promises” (citing cases)). The surety bond provides that Schuff must

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mason v. Eldred
73 U.S. 231 (Supreme Court, 1868)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Holcomb, Christine v. Powell, Donald
433 F.3d 889 (D.C. Circuit, 2006)
Fort Lincoln Civic Ass'n v. Fort Lincoln New Town Corp.
944 A.2d 1055 (District of Columbia Court of Appeals, 2008)
Hunt Construction Group, Inc. v. National Wrecking Corporation
542 F. Supp. 2d 87 (District of Columbia, 2008)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
Dyer v. Bilaal
983 A.2d 349 (District of Columbia Court of Appeals, 2009)
Howard Town Center Developer, LLC v. Howard University
267 F. Supp. 3d 229 (District of Columbia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Schuff Steel Company v. Bosworth Steel Erectors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/schuff-steel-company-v-bosworth-steel-erectors-inc-dcd-2024.