United States Elevator Corp. v. 1616 Reminc Ltd. Partnership (In Re 1616 Reminc Ltd. Partnership)

9 B.R. 679, 1981 Bankr. LEXIS 4852
CourtUnited States Bankruptcy Court, E.D. Virginia
DecidedFebruary 23, 1981
Docket15-36231
StatusPublished
Cited by2 cases

This text of 9 B.R. 679 (United States Elevator Corp. v. 1616 Reminc Ltd. Partnership (In Re 1616 Reminc Ltd. Partnership)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Elevator Corp. v. 1616 Reminc Ltd. Partnership (In Re 1616 Reminc Ltd. Partnership), 9 B.R. 679, 1981 Bankr. LEXIS 4852 (Va. 1981).

Opinion

MEMORANDUM OPINION

MARTIN V. B. BOSTETTER, Jr., Bankruptcy Judge.

The defendant, 1616 Reminc Limited Partnership (“Reminc”) is a debtor-in-possession in a Chapter XII proceeding under the Bankruptcy Act presently before this Court. The plaintiff, United States Elevator Corporation (“USE”), initiated an action against Reminc by way of an Amended Complaint filed on July 9, 1976, seeking a recovery in the amount of $177,885.00. 1 Reminc filed a counterclaim in the amount of $1,500,000.00 and also served The American Insurance Company [Fireman’s Fund] (“American”) in a suit on a performance and payment bond, as surety, in connection with USE’s contractual obligations for the installation of an elevator system in Rem-inc’s principal asset, an office building. 2 *682 The building in question is located at 1616 North Fort Myer Drive, Arlington, Virginia, and is commonly referred to as the “Xerox Building”.

USE is a wholly-owned subsidiary of Cubic Corporation. On March 16, 1973, USE entered into a subcontract with Citcon Corporation, the general contractor for Reminc during the construction of the Xerox Building. Under this subcontract, USE agreed to install two hydraulic and six electric elevators in the Xerox Building.

This Court determined, by an Order entered cn January 15,1977, that USE’s waiver of mechanic’s lien rights was validly and properly executed by USE. This had the effect of disallowing USE’s claim as a secured claim against Reminc’s real estate.

Prior to this Court’s decision invalidating USE’s mechanic’s lien, USE made application to be treated as an unsecured creditor under Rule 12-30 of the Rules of Bankruptcy Procedure by virtue of an assignment entered into by the general contractor of the Xerox Building, Citcon Corporation (“Citcon”), as assignor, and Reminc as as-signee. Reminc obtained this assignment on August 6, 1976.

On August 15, 1975, Reminc filed a petition initiating the proceedings before this Court. The Plan of Arrangement was confirmed on May 19, 1976.

Several issues are before the Court for resolution. First, is American liable, as surety, on any defects in construction on the part of USE in installing the Xerox Building’s elevator system? Second, does USE remain liable as a principal under the performance bond even if the surety is released therefrom? Third, can USE’s claim as an unsecured claimant be asserted against Reminc as assignee? Fourth, has USE established that the installation of the elevator system was accomplished in a workmanlike manner and in accordance with the terms and specifications of its subcontract? Fifth, is Reminc entitled to damages as alleged in its counterclaim against USE?

Admitted into evidence is a “Contract Bond — Dual Obligee” between Reminc and American. USE is the principal under this bond. American agreed therein to furnish a bond in the amount of $459,000.00 for the performance of USE’s obligations under the contract. Paragraph six (6) of the bond states that:

“[N]o suit, action or proceeding shall be had or maintained against Surety [American] on this bond unless the same be brought or instituted within one (1) year after the date of the completion of the work by Principal or after the date of any default by Principal in the performance of the contract.”

It is uncontroverted that Reminc signed temporary acceptances of the elevator system, dated August 16, 1974. Reminc later signed a final acceptance of the hydraulic elevators on March 15, 1974, and the six elevators on February 24, 1975.

In Virginia, a provision in a bond “which bars recovery from the surety after the expiration of one year following the date on which” the principal completed work on its contract is valid. 3A Michie’s Jur., Building Contracts, § 22 (1976 Replacement). See Con tee Sand and Gravel Company, Inc. v. Reliance Insurance Company, 209 Va. 672, 166 S.E.2d 290 (1969).

Reminc argues that within the context of the Chapter XII proceedings, it asserted USE’s liability for defective performance as part of its Objection to Claim, filed on January 26, 1976. To come within the one-year period mandated under the bond, would require Reminc to establish that its filing of an objection to claim on January 26, 1976, effectively tolled the statute as to American. USE asserts that Larwin Mortgage Investors (not a party to the bond) initially filed the objection, rather than Reminc. It follows that since American was not named as a party in the suit until Reminc filed suit on the bond on November 9, 1976, American was without notice that its obligations under the bond had been invoked.

Reminc further argues that its acceptance of the elevator system does not consti *683 tute a completion of the work by USE, and asserts that since USE continued to work on the elevator system after final acceptance, it is within the one-year statute of limitation under the bond. In support of its position Reminc relies upon the testimony of L. William Cork, as it appears in a deposition de bene esse. Cork, an elevator adjuster with USE in 1975, was sent to the Xerox Building to make corrections in the elevator system. He was employed in USE’s contract and engineering section, rather than its maintenance section. Rem-inc urges that this fact evidences continued activity.

Admitted into evidence is a document entitled “Service Department Contract A,” a maintenance agreement between USE and Reminc, dated June 6, 1974. Attachment I to this contract states in part that “[t]his contract includes three (3) months free service which will commence on the date each elevator is inspected, accepted and placed into permanent operation.”

The Court takes cognizance of a letter addressed to J. B. Jenkins (an employee of Cubic Corporation) from Evans L. Morrison (an employee of Performance Profiles, Inc., an expert witness for USE), dated April 29, 1976, wherein Morrison states that “[fjine tuning adjustments should not be considered as having a relation to completion. It is normal to accept equipment and have it ‘touched up’ later.” Morrison also stated that “[bjased upon the elevator performance data acquired at the job, there is no question that the individual ears and the elevator group are complete — the job is finished.” Morrison reiterated the views expressed in this letter on direct examination in the instant proceeding.

Robert Calhoun Smith, the architect for the Xerox Building, endorsed numerous worksheets admitted into evidence entitled “Application and Certificate for Payment” for work completed between August 1,1974 and October 30, 1974. Each of these documents indicated that one-hundred percent of the work on the elevator system had been completed. In a report to the General Partner of Reminc, dated July 24, 1974, the architect made a notation regarding two of the elevator cars to the effect that although there existed some bounce when a passenger entered the cabs, “[t]he elevators appealed] to be installed in accordance with the manufacturer’s recommendations and shop drawings.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
9 B.R. 679, 1981 Bankr. LEXIS 4852, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-elevator-corp-v-1616-reminc-ltd-partnership-in-re-1616-vaeb-1981.