Nelson M Melo and Sandra K Melo

United States Bankruptcy Court, W.D. Washington·Decided June 21, 2019·No. 17-43644·Unknown

Opinion

\ aes }} Brian D. Lynch —_~U.LS. Bankruptcy Judge

__C—Cti‘“‘UNITED STATES BANKRUPTCY COURT WESTERN DISTRICT OF WASHINGTON AT TACOMA ) In re: Case No. 17-43644-BDL NELSON M. MELO and 41 SANDRA K. MELO, ORDER SUSTAINING OBJECTION BY MORGAN MELO TO PROOF OF CLAIM NO. 4 OF MARTEN TRANSPORT, LTD. Debtors. Morgan Melo, daughter of the debtors Nelson and Sandra Melo, has filed an Objection to Proof of Claim No. 4 (ECF No. 72) filed by Marten Transport, Ltd. Morgan is the defendant an avoidance action asserted by the Chapter 7 Trustee in this case, and seems to have lltaken the strategy of defending that adversary by objecting to all the claims filed in her parents’ bankruptcy, assuming if there are no claims to be administered the Trustee has no reason to recover from her. Morgan objected to Marten Transport’s claim on the grounds it does not allege a claim ! against her parents, but instead is the liability of their former company, TreCore Construction." Marten opposed the objection on two grounds. First, it contended that Morgan did not standing to object to its proof of claim as she was not a party in interest as to the claim. TreCore and a related company filed their own chapter 7 bankruptcies as well. Case Nos. 17-43069 & 17- 43070.

Second, it contended that the debt involved was caused by Nelson Melo’s fraud and there was a basis to pierce the corporate veil to impose alter ego liability for TreCore’s breach of contract. The objection was first heard by the Court on April 2, 2019. The Court determined there were fact questions about both Morgan’s standing as well as individual liability of the debtors and the matter was set for an evidentiary hearing. The evidentiary hearing was conducted on June 4, 2019. Morgan Melo appeared through her counsel John D. Nellor. Marten Transport appeared through its counsel Donald E. Bradley, pro hac vice. Closing arguments were made on June 6, 2019. In accordance with Fed. R. Civ P. 52, made applicable by Fed. R. Bankr. P. 9014(c) and 7052, following are the Court’s findings of fact and conclusions of law. To the extent any of the Findings of Fact are considered Conclusions of Law, they are adopted as such and vice versa. Facts The genesis of this dispute starts with Marten Transport’s hiring of TreCore in December 2016 to repair and construct a parking lot for Marten’s Wilsonville, Oregon site. The contract (Ex. C1) is between Marten and TreCore and provided for a price of $770,271. The contract provided that TreCore was to warrant all title to the work would pass to Marten at the time of payment for the work (Para. 11.2.2); that TreCore was to promptly pay each subcontractor and supplier upon receipt of payment from Marten (Para. 11.3.2); and that Marten was to have no obligation to pay any subcontractor or supplier (Para. 11.3.3). The contract also provided that it shall be governed by the law of the place where the project is located. The contract was signed by Nelson Melo, as president, and Monte Pershall, as senior vice president, on behalf of TreCore, and by a representative of Marten. Marten paid TreCore a 25 percent down payment in December 2016 and then paid for the remainder of the construction cost on two invoices. TreCore emailed Marten on May 1, 2017 indicating the project was 76.6% complete. Nelson Melo was copied on the email. After receipt of the 76.6% email, Marten paid TreCore $397,459.92 on May 12, 2017. TreCore then emailed Marten again on May 12, 2017 indicating the project was “100% complete.” Nelson Melo was again copied on this email. Marten contends these emails represent that not only progress of the construction but also payment of subcontractors was also “100% complete.” Marten then paid TreCore the remaining amount of the contract price of $180,243.46 on May 26, 2017. Marten received word from subcontractor Granite Construction Company in mid-June 2017 that TreCore had not paid Granite for any of its work, despite Granite sending TreCore invoices in April and May 2017. Marten had several communications with TreCore employees about Granite getting paid, although none of the communications were directly with Nelson Melo. Marten was told, in part through an email dictated by Nelson Melo, that TreCore intended to pay the Granite invoices but needed more time as TreCore was going through merger talks. In fact, Nelson Melo had been having merger discussions with acquaintances at Talents Construction since April 2017. TreCore never paid Granite. Granite recorded a mechanic’s lien against Marten’s property in July 2017. To remove the lien, Marten was forced to pay Granite – despite having already paid TreCore for the work. Marten did not ask for or receive a Lien Waiver for the Wilsonville project. Nelson Melo testified he was not the primary manager of the Marten project, and that at the time he was managing several other TreCore projects all over the Western states. He testified he was not aware of the accuracy of the “76.6%” and “100% complete” emails at the time they were sent and was not aware that TreCore had not paid Granite. Three Marten employees testified that Nelson Melo was on the Marten site for a pre-construction meeting, and two other times during the project. None of Nelson Melo’s conversations with these employees related to financial matters or payment of subcontractors but were instead about a few details of the project, along with general chit-chat topics unrelated to the businesses or the contract. During 2017 TreCore faced financial issues due to several other projects. Nelson and Sandra Melo were also approached by a co-owner of TreCore, Monte Pershall, about making a loan to TreCore to assist it financially. Pershall was involved more with the financial side of TreCore’s business. Sandra Melo arranged for Morgan Melo to make a $100,000 loan in early 2017. Morgan provided the money to the debtors, who deposited it in their personal accounts and then Sandra Melo wrote a check to TreCore to loan it the funds. No documents evidencing the loans were introduced; Nelson Melo alone testified about these arrangements. Marten neither impeached or disputed his testimony, nor did Marten offer contrary evidence about the circumstances of the loan. As to Marten’s claim that alter ego liability should apply to Nelson Melo for TreCore’s breach of contract, the only testimony elicited was that Nelson and Sandra Melo, sometime before 2017, had assisted a former TreCore employee to obtain financing and equipment so that he could start his own metal fabricating business in Northern California. The Melos obtained some of the equipment themselves, which they sold or lease-optioned to the new business. In November 2017, Nelson Melo also provided some trailers for use by the metal fabrication business which he personally owned, and which may have been used by TreCore at other times. Nelson Melo testified that he personally owns some equipment and over the years has done side jobs with friends on a personal basis during that time, outside the purview of his various companies. On August 3, 2017, Marten filed a lawsuit against TreCore, Nelson Melo and TreCore’s other principal Pershall in federal district court in Oregon. TreCore filed for chapter 7 bankruptcy on August 15, 2017. The Melos filed this personal chapter 7 bankruptcy in late September 2017. Morgan Melo was scheduled as a creditor, on the debtors’ Schedule F of unsecured debts, with an alleged debt owed of $200,400.2 The debtors’ Chapter 7 Trustee commenced a fraudulent conveyance and/or preference action against Morgan Melo on September 4, 2018 (Ad. Proc. 18-4055). Morgan’s attorney stated on the record that Morgan had asked the Trustee to object to the proofs of claim filed in the debtors’ case that were related to TreCore debts, but the Trustee declined to file such objec

Free access — add to your briefcase to read the full text and ask questions with AI

Nelson M Melo and Sandra K Melo, (Wash. 2019).

Nelson M Melo and Sandra K Melo (Nelson M Melo and Sandra K Melo) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Standard Fire Insurance v. Blakeslee
771 P.2d 1172 (Court of Appeals of Washington, 1989)
Webb v. Clark
546 P.2d 1078 (Oregon Supreme Court, 1976)
Mandalay Resort Group v. Miller (In Re Miller)
292 B.R. 409 (Ninth Circuit, 2003)
In Re Bakke
243 B.R. 753 (D. Arizona, 1999)
Kaloti Enterprises, Inc. v. Kellogg Sales Co.
2005 WI 111 (Wisconsin Supreme Court, 2005)
In Re Sun Ok Kim
89 B.R. 116 (D. Hawaii, 1987)
In Re Lundahl
307 B.R. 233 (D. Utah, 2003)
In Re Barnes
275 B.R. 889 (E.D. California, 2002)
In Re Ulz
401 B.R. 321 (N.D. Illinois, 2009)
Torres Martinez v. Arce (Torres Martinez)
397 B.R. 158 (First Circuit, 2008)
RSL-3B-IL, Ltd. v. Symetra Life Insurance
271 P.3d 925 (Court of Appeals of Washington, 2012)