Howard Town Center Developer, LLC v. Howard University

267 F. Supp. 3d 229
CourtDistrict Court, District of Columbia
DecidedJanuary 31, 2017
DocketCivil Action No. 2013-1075
StatusPublished
Cited by18 cases

This text of 267 F. Supp. 3d 229 (Howard Town Center Developer, LLC v. Howard University) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard Town Center Developer, LLC v. Howard University, 267 F. Supp. 3d 229 (D.D.C. 2017).

Opinion

MEMORANDUM OPINION

BERYL A. HOWELL, Chief Judge

This case returns to the' Court for reconsideration of the appropriateness of summary judgment in favor of either the defendanVcounter-plaintiff Howard University (“the University”), which owns property that it seeks to develop, or the plaintiff/counter-defendant Howard Town Center, LLC, (“the Developer”) and the third-party defendant Castlerock Partners, LLC, another developer, The D.C. Circuit concluded that a “term sheet” (the “Term Sheet”) —which the Developer previously urged this Court to disregard but, in an about-face, characterized on appeal as controlling the outcome of .the present dispute — might affect the parties’ respective claims in this case and, for this reason, vacated the entry of summary judgment in favor of the University and remanded the case for consideration of the significance of the Term Sheet. The parties have now filed cross-motions for summary judgment. See Mot. Def. Howard Univ. Summ. J. Am. Compl., Counterclaim, & Third-Party Compl. (“Def.’s Mot.”), ECF No. 86; Plaintiff & Third-Party Def.’s Mot. Summ. J,. (“PL’s Mot.”), ECF No. 87. In those motions, the University seeks a rental payment originally due in 2011 from the Developer, which for the past eight years has been unsuccessful in developing the property, while the Developer seeks yet more time to fulfill its'contractual obligations with respect to the property. For the reasons set- forth below, the motions are- denied.

I. BACKGROUND

The factual and procedural history underlying the present dispute is fully set out *232 in this Court’s prior Memorandum Opinion granting summary judgment in favor of the University, see Howard Town Ctr. Developer, LLC v. Howard Univ., 7 F.Supp.3d 64, 66-76 (D.D.C. 2013), as well as in the D.C. Circuit’s decision vacating that judgment and remanding the case, see Howard Town Ctr. Developer, LLC v. Howard Univ., 788 F.3d 321, 323-25 (D.C. Cir. 2015), and, consequently, will be summarized only briefly.

The parties’ now contentious relationship began over eight years ago, in December 2008, when the University executed a development agreement with the third-party defendant to develop for mixed use a parcel of land in Washington, D.C. that the University agreed to lease for this purpose. Def.’s Statement Undisputed Material Facts Supp. Mot. Summ. J. (“Def.’s SMF”) ¶¶ 1-2, ECF No. 86. 1 In' January 2010, the University and the third-party defendant executed a ground lease for the parcel, along with a second development agreement, both of which agreements the third-party defendant assigned on the same day to the Developer, a newly created entity in which the third-party defendant and its principal hold interests. Id. ¶¶ 4, 7, 9, 11. 2 The ground lease provided for payments to the University on the following schedule: $525,000 on January 22, 2010; $1,475,000 no later than March 15, 2011; and monthly installments of rent thereafter. Id. ¶ 8. The development agreement provided that construction would begin on the parcel no later than March 15, 2011, with substantial completion by March 15, 2013. Id. ¶ 10. 3 The agreements also provided for their termination upon the occurrence of certain events to be considered defaults, with provisions requiring notice and an opportunity to cure be given to the defaulting party.

In accordance with these agreements, the Developer made the first rental payment of $525,000 into an escrow account. Id. ¶ 23. Yet, March 15, 2011, the key date for payment of the second rental payment, came' and went with the Developer neither paying the University the $1,475,000 required under the lease agreement, nor beginning construction on the project as provided in the development agreement. Id. ¶ 29. According to the Developer, this failure is attributable to a myriad of factors relevant to an analysis of its contractual obligations under the agreements existing at that time, including “the financial crisis,” that made securing financing difficult. PI. & Third-Party Def.’s Statement Material Facts Not Gen. Disp. (“Pl.’s SMF”) ¶ 52, ECF. No. 87. As it became clear that construction would not commence as *233 agreed in the lease and development agreements, the parties began to discuss alternative timelines and alterations to the building project, which discussions continued after March 15, 2011, and included the University’s proposal of December 8, 2011, as an amended deadline for commencement of construction and payment of the second installment of rent. Def.’s SMF ¶ 32. The Developer never formally accepted in writing the University’s offer of an amended schedule, failed to comply with this offered extended schedule, and did not respond to the University’s August 30, 2011, demand for assurances of the Developer’s ability and willingness “to fulfill its contractual commitments to the University.” Id ¶¶ 34-37. Consequently, on September 26, 2011, the University sent the Developer a notice of default under the lease and development agreements, citing eight distinct defaults, including the Developer’s failure to make progress on improvements to the property, as well as its failure to give the University requested assurances as to its ability to make a rental payment on December 8, 2011, Def.’s SMF ¶ 39; Pl.’s SMF ¶ 65.

Following the notice of default, the Developer failed to cure any of the cited defaults or to make the second rental payment of $1,475,000, which was originally due by March 15, 2011, by the University’s proposed extended date of December 8, 2011, or to commence construction on the project. Def.’s SMF ¶ 40. Four months after issuance of the first default notice, the University sent the Developer, on February 3, 2012, a second notice of default and notice of intent to terminate both the lease ,and development agreements, citing the Developer’s failure to make the requisite payment by December 8, 2011. Id. ¶45.

By the time of the second default notice, the parties had begun to discuss a way to resolve the Developer’s enumerated defaults. These discussions resulted in execution, on February 14, 2012, id. ¶ 48, óf a “Pre-Negotiation Agreement” to govern “discussions relating to the obligations the Developer owes to the University pursuant to the Ground Lease and Development Agreement dated January 22, 2010,” Def.’s Mot., Ex. 24 (“Pre-Negotiation Agreement”)' at 1, ECF No. 86-24. Thé Pre-Negotiation Agreement provided, inter alia, that the content of the discussions would remain . private; any additional binding agreements must be reduced to writing; and the negotiations could be terminated at any time. Pre-Negotiation Agreement at 1-2. Notwithstanding the agreement to negotiate, on March 5, 2012, the University sent the Developer a third notice of default and notice of intent to terminate both the lease and development agreements due to the Developer’s continuing failure to make the second rental payment of $1,475,000, which was now almost one .year overdue. Def.’s SMF ¶50.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
267 F. Supp. 3d 229, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-town-center-developer-llc-v-howard-university-dcd-2017.