Howard Town Center Developer, LLC v. Howard University

788 F.3d 321, 415 U.S. App. D.C. 390, 2015 U.S. App. LEXIS 9571, 2015 WL 3555830
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 9, 2015
Docket13-7198, 14-7029
StatusPublished
Cited by2 cases

This text of 788 F.3d 321 (Howard Town Center Developer, LLC v. Howard University) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard Town Center Developer, LLC v. Howard University, 788 F.3d 321, 415 U.S. App. D.C. 390, 2015 U.S. App. LEXIS 9571, 2015 WL 3555830 (D.C. Cir. 2015).

Opinion

Opinion for the Court filed by Senior Circuit Judge GINSBURG. "

GINSBURG, Senior Circuit Judge:

Howard University leased a parcel of land in Washington, D.C. to Howard Town Center Developer, LLC. After the Developer failed to make a rental payment of $1,475,000 on May 30, 2013, the University terminated the lease agreement. The Developer sued, and the district court entered a summary judgment in favor of the University. Because we agree with the Developer that there is a genuine dispute whether a rental payment was due on May 30, 2013, we vacate the judgment of the district court and remand this case for further proceedings in that court.

I. Background

Howard University owns a “long-neglected” parcel of land in Washington, D.C. that it sought to transform into an upscale “mixed-use residential/retail development.” In 2010 the University entered into several related agreements with Cast-lerock Partners, LLC, which later assigned its interest in the agreements to Howard Town Center Developer, LLC. Three of those agreements are relevant to this appeal: the Ground Lease, the Development Agreement, and the Amendment to the Development Agreement.

The Ground Lease provides that the University will lease the property to the Developer for 99 years. In exchange, the Developer will make rental payments of $525,000 on January 22, 2010 and of $1,475,000 on March 15, 2011, followed by periodic rental payments in an amount to be determined by a formula specified in the lease. Section 16.2 of the Ground Lease describes the process by which the University may terminate the lease if the Developer fails to pay rent:

Should Tenant at any time be in default with respect to any rental payments or other charges payable by Tenant under this Lease, and should such default continue for a period of ten (10) days after written notice from Landlord to Tenant ... then Landlord may treat the occurrence ... as a breach of this Lease (an “Event of Default”), and in addition to any or all other rights or remedies of Landlord under this Lease or as otherwise permitted by law, it shall be, at the option of Landlord
[t]he right of landlord to terminate this Lease and to declare the' Lease term ended....
[Pjrior to exercising any right to terminate this Lease on account of any Event of Default, Landlord shall provide Tenant and each Leasehold Mortgagee with a written notice (in addition to any notice of default provided for in this Section 16.2 ... ), specifying IN BOLD FACE CONSPICUOUS TYPE, that *324 Landlord intends to terminate the Lease if the Event of Default is not cured within ten (10) days. Upon the expiration of such ten (10) day period, and if such Event of Default has not been cured, Landlord shall have the right, at its sole option, thereafter to elect to terminate this Lease....

The Development Agreement outlines the plans for developing the parcel. It describes, among other things, the type of buildings the Developer must construct on the property and the-timeline for doing so.

The Amendment to the Development Agreement allocates the cost of cleaning up environmental toxins discovered on the site. It modifies the Ground Lease by directing the Developer to make the first two rental payments — of $525,000 and $1,475,000 — to an escrow account rather than to the University directly. The money in the escrow account will be used to satisfy the University’s obligation to cover its share of the cost of cleaning up the toxins, and any remaining funds will be released to the University.

After signing these three agreements, the University and the Developer created an escrow account, and the Developer made the first rental payment of $525,000 into the account. The Developer did not, however, make the second rental payment of $1,475,000 by March 15, 2011 as required by the Ground Lease. The University extended the deadline for the second rental payment, but it remained concerned with the Developer’s progress and demanded assurances that the Developer would stay on schedule. The Developer did not respond and, on September 26, 2011, the University advised the Developer it was in default under the Ground Lease and the Development Agreement. On February 3, 2012 the University again notified the Developer it was in default and the University would regard the Developer’s failure to pay $1,475,000 within ten days as an “Event of Default” under the parties’ agreements. On March 5, 2012 the University informed the Developer it intended to terminate the Ground Lease and the Development Agreement if the Developer did not cure the “Event of Default” within ten days.

In an effort to save the project, the parties returned to the negotiating table and drafted a Second Amendment to the Development Agreement. The proposed Second Amendment — which the parties never signed — provided the Developer would make the $1,475,000 rental payment by May 30, 2013.

Although the parties had not signed the Second Amendment to the Development Agreement, on April 6, 2012 they signed a Term Sheet, which includes the following provisions:

The letters entitled “Notice of Default and Notice of Intent to Terminate” dated February 3, 2012 and again on March 6, 2012 are hereby withdrawn. The defaults related to the timetable for development will be revised and documented in amendments to the Development Agreement and Ground lease. The timetable for cure of the monetary default is defined herein.
The new timetable for development is as follows:
1) Execute this Term Sheet: April 6, 2012, or at such later time as both parties execute the Term Sheet, which shall be deemed to be the Effective Date.
2) Execute Ground Lease Amendment and [Second] Development Agreement Amendment by Monday, April 30, 2012.
3) Execute amendment to Escrow agreement such that $525,000 held in escrow for the purposes of environmen *325 tal remediation will be released upon execution of this Term Sheet.
4) Payment of past due ground rent in the amount of $1,475,000 shall be as follows: (a) no later than ten (10) days after execution of this Term Sheet, a payment of $100,000 will be made, and (b) the balance of $1,375,000 will be paid no later than ninety (90) days after the execution of the Ground Lease and Development Agreement Amendments.

Two of the obligations set forth in the Term Sheet remain unfulfilled: the Developer did not make either rental payment, and the parties did not execute the Second Amendment to the Development Agreement. The parties did, however, terminate the escrow agreement, thereby releasing $525,000 to the University.

The parties continued to negotiate the terms of the Second Amendment to the Development Agreement into early 2013.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Howard Town Center Developer, LLC v. Howard University
278 F. Supp. 3d 333 (District of Columbia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
788 F.3d 321, 415 U.S. App. D.C. 390, 2015 U.S. App. LEXIS 9571, 2015 WL 3555830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-town-center-developer-llc-v-howard-university-cadc-2015.