United House of Prayer for All People v. Therrien Waddell, Inc.

112 A.3d 330, 2015 D.C. App. LEXIS 100, 2015 WL 1432555
CourtDistrict of Columbia Court of Appeals
DecidedMarch 26, 2015
Docket13-CV-912
StatusPublished
Cited by19 cases

This text of 112 A.3d 330 (United House of Prayer for All People v. Therrien Waddell, Inc.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United House of Prayer for All People v. Therrien Waddell, Inc., 112 A.3d 330, 2015 D.C. App. LEXIS 100, 2015 WL 1432555 (D.C. 2015).

Opinion

THOMPSON, Associate Judge:

After a bench trial, the Superior Court (the Honorable Michael Rankin) entered judgment in favor of appellee Therrien Waddell, Inc. (“TWI”), and against appellant United House of Prayer for All People (“UHP”), requiring UHP to pay damages for what Judge Rankin found to be UHP’s breach of a binding and enforceable oral agreement between the parties, under which TWI was to construct an apartment building (the Bailey Park Apartments) at 625 Rhode Island Avenue, N.W. (“the apartment building”), on a lot owned by UHP. UHP seeks reversal of the judgment, contending that there was no intent to be bound and no enforceable agreement because the parties never reached a meeting of the minds on several material terms. Our analysis differs from the trial court’s, but we conclude that the evidence and the law support a conclusion that the parties reached an enforceable oral agreement— specifically, a binding preliminary commitment to negotiate in good faith toward a written construction agreement, within the framework the parties had agreed upon during a meeting between their representatives in December 2010. We find it necessary, however, to remand the matter to the trial court (1) for an additional finding as to whether UHP acted in bad faith in declining to negotiate with TWI; and, if so, (2) for the court also to determine whether, absent UHP’s bad faith, the parties would have entered into a final construction agreement; and (3) for recompu-tation of a damages award.

I. Background

The following factual background is drawn from Judge Rankin’s July 30, 2013, Memorandum Opinion and from the supporting trial testimony and exhibits. 1 In 2009, UHP retained the firm of Suzane Reatig Architecture, PLLC (“SRA”) to perform architectural services in connection with the planned apartment building project (the “Project”). SRA principal Suzane Reatig worked with SRA architect Megan Mitchell to prepare a bid solicitation package. The package included a manual (the “Project Manual” or the “Manual”) containing the specifications for the building; provided that a standardized contract developed by the American Institute of Architects (“AIA”), known as AIA A-101-2007, would be the form of contract between UHP and the contractor whose bid was selected; and provided that the general conditions for the contract would be as set forth in Articles 1 through 14 of another standardized agreement known as AIA A-201-2007.

SRA distributed the bid solicitation package in late November 2010, and on December 20, 2010, TWI Senior Project Manager Richard Whalen sent SRA TWI’s bid. TWI’s bid, the lowest of the four bids *333 SRA received, proposed a total price of $4,899,000 (including profit of $141,000, representing 3% of the contract cost excluding the cost of obtaining a performance bond) and “a duration of 9 months” (based on an assumption that the Project would start in January or February of 2011). The “Notes & Clarifications” attached to TWI’s bid stated that “[w]hile the basic contract form has been indicated, [TWI] reserve[s] the right to negotiate mutually agreeable terms of the construction agreement if selected for the project.”

On December 21, 2010, architect Mitchell invited Whalen to a meeting with SRA and UHP representatives to discuss the Project. The meeting took place on December 22, 2010, and was attended by Whalen and Dan Coffey, a TWI vice-president, representing TWI; by Reatig and Mitchell, representing SRA; and by Apostle Sterling Green, the owner’s representative for UHP.

At the December 22, 2010, meeting, there was a “comprehensive” discussion of TWI’s proposal and the Project. This included a discussion of the “Notes & Clarifications” that TWI had attached to its bid. The Notes & Clarifications reflected TWI’s proposal to “use a less expensive satin finish for the exterior Trespa Meteon facade panels instead of the more expensive metallic finish called for” in the Project specifications. SRA “insisted that the owner wanted the more expensive metallic finish cost included in the contract[,]” which “meant that the cost of the project would increase.” Another major point of discussion at the meeting was the need for a supplementary vapor barrier system: “the architects directed TWI to use a more expensive E.P. Henry product and to include the costs of the system in the contract.” 2 The meeting participants also discussed the importance of obtaining Leadership in Energy and Environmental Design (“LEED”) certification for the Project. “The project manual specified that the Project should qualify for LEED certification but did not specify which LEED credits would be pursued”; during the meeting, the SRA representatives for the first time “identified ... the [specific] LEED credits the Project would try to meet[.]” Coffey informed the meeting participants that Whalen “did not have ... qualifications for the LEED” requirements, and that, instead of Whalen, TWI’s LEED-accredited project manager Jonathan Fuentes, who had been unable to attend the meeting, would be the Project Manager because of his LEED qualifications. 3 Coffey also told the group that *334 meeting UHP’s newly-identified LEED-credit demands “could mean additional time and money.” The meeting participants also discussed that “there were certain things that needed to happen pretty quickly ..., mainly ... some of the long-lead materials that require special fabrication.” The meeting notes reflect that the participants discussed having a pre-con-struction meeting with subcontractors in late January. Judge Rankin found that “Green told TWI’s representatives that the owner expected a ‘long-lasting marriage, not a short honeymoon.’ ”

Judge Rankin found that “[a]t the conclusion of the [December 22] meeting, all parties — Apostle Green, SRA and TWI— had reached a meeting of the minds on the material terms of the contract” and that “Green directed TWI to prepare a written contract based on [the parties’] discussions.” 4 Judge Rankin further found that “[o]n leaving the meeting [TWI] understood that it had to modify its proposal so that the written contract conformed to the specific requirements of the owner as expressed by Apostle Green and SRA” at the meeting.

In preparing the modifications, TWI prepared a schedule of prices that reflected replacement of the less expensive satin-finished panels with the more expensive metallic-finished ones, added the considerably more expensive Henry vapor barrier system, 5 added allowances for LEED-credit items that had not been included in TWI’s original bid (including LEED-required interior bike racks), and added temporary utility costs (which, per the discussion at the December 22 meeting, were to be borne by the general contractor rather than by the owner). These modifications are reflected in the revised “Notes & Clarifications” and revised pricing information TWI sent to Mitchell by email on January 18, 2011. 6 The modified price document indicated a total price of $5,048,600 (up from the original bid price of $4,899,000).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matiella v. Murdock Street LLC
District of Columbia, 2025
Cikeithia Berry
District of Columbia, 2023
Jenkins v. Howard University
District of Columbia, 2023
Sellers, Jr. v. Anthem, Inc.
District of Columbia, 2022
Apprio, Inc. v. Zaccari
District of Columbia, 2021
Mobile Now, Inc. v. Sprint Corporation
District of Columbia, 2019
2301 M Street Cooperative Association v. Chromium, LLC
209 A.3d 82 (District of Columbia Court of Appeals, 2019)
SJ Enterprises, LLC v. Dianne Quander
207 A.3d 1179 (District of Columbia Court of Appeals, 2019)
Copywatch, Inc. v. Cross
299 F. Supp. 3d 189 (D.C. Circuit, 2018)
Capitalkeys, LLC v. Democratic Republic of Congo
278 F. Supp. 3d 265 (District of Columbia, 2017)
Howard Town Center Developer, LLC v. Howard University
267 F. Supp. 3d 229 (District of Columbia, 2017)
Banneker Ventures, LLC v. Jim Graham
798 F.3d 1119 (D.C. Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
112 A.3d 330, 2015 D.C. App. LEXIS 100, 2015 WL 1432555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-house-of-prayer-for-all-people-v-therrien-waddell-inc-dc-2015.