Seaboard Surety Co. v. Town of Greenfield Ex Rel. Greenfield Middle School Building Committee

266 F. Supp. 2d 189, 2003 U.S. Dist. LEXIS 9871, 2003 WL 21350451
CourtDistrict Court, D. Massachusetts
DecidedMarch 7, 2003
DocketCIV.A.00-12615 FHF
StatusPublished
Cited by4 cases

This text of 266 F. Supp. 2d 189 (Seaboard Surety Co. v. Town of Greenfield Ex Rel. Greenfield Middle School Building Committee) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaboard Surety Co. v. Town of Greenfield Ex Rel. Greenfield Middle School Building Committee, 266 F. Supp. 2d 189, 2003 U.S. Dist. LEXIS 9871, 2003 WL 21350451 (D. Mass. 2003).

Opinion

MEMORANDUM AND ORDER

FREEDMAN, Senior District Judge.

I. INTRODUCTION

The plaintiff, Seaboard Surety Company (“Seaboard”), brings this action against the defendant, the Town of Greenfield, Massachusetts, acting by and through the Greenfield Middle School Building Committee (the “GMSBC”), (collectively “Greenfield”), seeking a declaration that it is exonerated and discharged from any liability under a surety performance bond because the defendant materially breached the bond contract. Greenfield has filed counterclaims alleging Seaboard’s negligence and material breach of that same contract. Before the Court are the parties’ cross motions for summary judgment.

II. BACKGROUND

On June 18, 1998, pursuant to the bidding provisions set forth under Massachusetts General Laws, Chapter 149, Sections 44A-H, Greenfield entered into a general contract with Interstate Construction Co., Inc. (“ICC”), to renovate the Middle School Building in Greenfield, Massachusetts (the “Project”) for the contract price of $10,085,244 (the “Construction Contract”). Exh. I. 1 At that time, ICC provided a performance bond (the “Bond”) to Greenfield, as required under Massachusetts law and pursuant to the terms of the Construction Contract. Exhs. 1, 2. The Bond was amongst ICC (as the “Contractor”), Greenfield (as the “Obli-gee” or “Owner”), and Seaboard Surety Company (as the “Surety”). Exh. 2. The Construction Contract stipulated that the renovation work was to be substantially completed by September 1, 1999, or any reasonable extension thereof, that time was of the essence, and that ICC would work regularly and diligently to achieve substantial completion during the prescribed time for completion. Exh. 1 at Article 3.

As to Contractor Default, Paragraph 3 of the Bond provided:

3. If there is no Owner Default, the Surety’s obligation under this bond shall arise after
*191 3.1 The Owner has notified the Contractor and the Surety at its address described in Paragraph 10 below that the Owner is considering declaring a Contractor Default and has requested and attempted to arrange a conference with the Contractor and the Surety to be held not later than fifteen days after receipt of such notice to discuss methods of performing the Construction Contract. If the Owner, the Contractor and the Surety agree, the Contractor shall be allowed a reasonable time to perform the Construction Contract, but such an agreement shall not waive the Owner’s right, if any subsequently to declare a Contractor Default; and
3.2 The Owner has declared a Contractor Default and formally terminated the Contractor’s rights to complete the contract. Such Contractor Default shall not be declared earlier than twenty days after the Contractor and the Surety have received notice as provided in Sub-paragraph 3.1; and
3.3 The Owner has agreed to pay the Balance of the Contract Price to the Surety in accordance with the terms of the Construction Contract or to a contractor selected to perform the Construction Contract in accordance with the terms of the contract with the Owner.

Exh. 2 at ¶ 3.

On November 12, 1998, and again on March 23, 2000, Greenfield notified Seaboard and ICC that it was considering declaring a Contractor Default under Paragraph 3.1 of the Performance Bond and requested a conference with both. Exh. 7. On August 24, 2000, Greenfield notified Seaboard and ICC that it was declaring ICC to be in default and was formally terminating ICC’s right to complete the contract. Exh. 6. At the same time, Greenfield agreed to either pay the remaining balance of the contract price to Seaboard or to a contractor retained by Seaboard to perform the Construction Contract, in accordance with the terms of the contract. Exh. 6.

Paragraph 4 of the Performance Bond provides as follows:

4. When the Owner has satisfied the conditions of Paragraph 3, the Surety shall promptly and at the Surety’s expense take one of the following actions:
4.1 Arrange for the Contractor, with consent of the Owner to perform and complete the Construction Contract; or
4.2 Undertake to perform and complete the Construction Contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by the Owner and the contractor selected with the Owner’s concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Construction Contract, and pay to the Owner the amount of damages as described in Paragraph 6 in excess of the Balance of the Contract Price incurred by the Owner resulting from the Contractor’s default; or
4.4 Waive its right to perform and complete, arrange for completion or obtain a new contractor and with reasonable promptness under the circumstances:
.1 After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, tender payment therefor to the Owner; or
*192 .2 Deny liability in whole or in part and notify the Owner citing reasons therefor.

Exh. 2 at ¶ 4.

Following notification of ICC’s alleged default, on September 25, 2000 Seaboard requested documents and information from Greenfield to aid Seaboard in its review of the default allegations and the Project status. Exh. 8. Seaboard made repeated requests for such materials over the following weeks. Exhs. 13, 18, 21, 22, 26, 29, 33, 50. Thereafter, Greenfield responded with several installments of materials, the first of which was sent on September 26, 2000. Exh. 23. Likewise, on September 26, 2000, Greenfield requested that Seaboard undertake to perform and complete the Construction Contract itself, or through its agents or independent contractors pursuant to Paragraph 4.2 of the Bond. Id. Greenfield further stated that it believed Seaboard needed to render a decision no later than October 20, 2000, so the work could move forward by November 4, 2000. Id.

Once Seaboard received the initial installment of materials for its review, it arranged a meeting with Greenfield. Exh. 25. The meeting was held on October 11, 2000, and eventually led to the Emergency Work Agreement (“EWA”) to immediately enclose and protect the structure and to remedy the existing floor moisture problems. Exh. 32. The EWA was executed as of October 31, 2000, and Seaboard began to perform the emergency work pursuant to the EWA on November 6, 2000. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
266 F. Supp. 2d 189, 2003 U.S. Dist. LEXIS 9871, 2003 WL 21350451, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaboard-surety-co-v-town-of-greenfield-ex-rel-greenfield-middle-school-mad-2003.