Pacific Coast Engineering Company, a Corporation v. Merritt-Chapman & Scott Corporation, a Corporation

411 F.2d 889, 1969 U.S. App. LEXIS 12447
CourtCourt of Appeals for the Ninth Circuit
DecidedMay 12, 1969
Docket22230, 22230A
StatusPublished
Cited by40 cases

This text of 411 F.2d 889 (Pacific Coast Engineering Company, a Corporation v. Merritt-Chapman & Scott Corporation, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Coast Engineering Company, a Corporation v. Merritt-Chapman & Scott Corporation, a Corporation, 411 F.2d 889, 1969 U.S. App. LEXIS 12447 (9th Cir. 1969).

Opinion

JAMES M. CARTER, Circuit Judge:

On October 19, 1959, Pacific Coast Engineering Company (hereafter Paceco) sued Merritt-Chapman & Scott Corporation (hereafter Merritt-Chapman) in the California Superior Court in two actions, one for breach of contract and one for money withheld and interest. 1 The actions were removed to the United States District Court in San Francisco. The district judge held that Paceco had committed an anticipatory breach and that Merritt-Chapman was justified in can-celling the contract. The court awarded damages to Merritt-Chapman on its counterclaim in the sum of $46,823.00. Pa-ceco appeals the judgment.

QUESTIONS PRESENTED

There are two questions involved in this appeal. One is whether the district court’s interpretation of the obligations of the parties under the terms of the contract is clearly erroneous; the other is whether Paceco was in breach of contract thus justifying Merritt-Chapman’s cancellation.

FACTS

The appellee, Merritt-Chapman, was the prime contractor in the Priest Rapids Project, which involved the construction of a dam on the Columbia River in the State of Washington. In the summer of 1957, Merritt-Chapman entered into a contract with Pacific Car & Foundry Co., (hereafter Pacific, and not a party hereto), in which Pacific agreed to manufacture and deliver dam gates for the project.

On August 7, 1957, Paceco submitted a bid for hoists to raise the gates to be made by Pacific. The prices in the bid were based upon pre-bid calculations made by Paceco for its own use only. On September 19, 1957, Merritt-Chapman accepted Paceco’s August 7 bid for the *891 hoists and issued a purchase order for them.

The capacity of the hoists to be built by Paceco necessarily depended upon the weight of the gates to be lifted. The particular gates were designed so that the force of gravity operated to close them, with the hoists used only to lift the gates into an open position. Therefore, in designing the hoists, Paceco was required to compute the weight of, the gates. The following clause appeared in the specifications of the gates.

“Gate Motion Factor of Safety. All gates shall have a minimum factor of safety in motion of 1.50 under normal loading conditions. This motion factor of safety shall be defined as equal to the ratio of the dead weight of the gate plus any ballast required divided by the sum of the resisting forces, (wheel friction, rolling friction, and seal friction).”

Contract Specifications 138-100, § 2-02,D,3

Between the time Paceco submitted its bid and Merritt-Chapman accepted it, on August 23, Pacific sent Paceco a statement of its hoist pull capacities. Paceco compared them to the calculations on which the August 7 bid was based and noted wide discrepancies. On August 29, Paceco requested Pacific’s underlying calculations. On September 9 Pacific returned the calculations which were prepared for it by a naval architect. Paceco decided that the capacities arrived at by the architect were irresponsible and disregarded them. On October 1 and on October 18, 1967, Paceco requested that Merritt-Chapman help to resolve the differences between its calculations on hoist capacities and those of Pacific. On October 29, 1967, Merritt-Chapman’s Project Engineer, Gothro, wrote a letter to Paceco advising that there was a “considerable discrepancy” between Pacific’s hoist capacities and those of Paceco. Gothro suggested that Paceco “review these [Pacific’s] calculations and your own so that we may arrive at final requirements for the hoists.”

Paceco replied to Gothro’s request on November 19, 1957. The letter stated in substance that Paceco’s hoist capacities were correctly computed on the basis of an understanding with a representative of Harza Engineering Company, the engineer for the project; this understanding apparently supported Paceco’s interpretation of the “gate motion factor safety.” The letter concluded, “on Items 8 and 9 we are proceeding on the design on the basis of the confirmation from Mr. Paul Maier of the operating conditions which establish the hoist capacity at the lower value.”

During the month of December 1957, Merritt-Chapman made certain comments on Paceco’s calculations; Paceco sent modified calculations which still were premised on its original understanding of the operating factors to which the gates were to be subjected. On January 16, 1958, Merritt-Chapman wrote to Pa-ceco and stated that Pacific’s calculations now agreed with Paceco’s. Copies of Paeeco’s and Pacific’s calculations were then forwarded to Harza Engineering Co., the Project Engineer. Harza subsequently telephoned Paceco and informed them that the capacities of the hoists as computed by Paceco were inadequate.

On February 21, 1958, Paceco wrote Merritt-Chapman that Paceco disagreed with Harza’s determination that the hoist pulls were inadequate. The following statement was included:

“If, however, the capacities to which we designed our hoists are changed, our present shipping schedule will of necessity be changed in that new designs will have to be made. This in turn will result in an extra charge for the engineering. All shipments will be set back correspondingly pending completion of any new design.” (emphasis added).

Merritt-Chapman wrote Paceco on February 24, 1958; included was a copy of the letter from Harza to Merritt-Chapman rejecting Paceco’s hoist pull computations. Harza’s letter pointed out Pa-

*892 ceco’s error. “In determining the pull the first item to be considered is the gate motion factor of safety. * * * The motion factor of safety must account for each leaf in movement and must be based on the starting friction factors.” (emphasis added) In its letter Merritt-Chapman asked for revisions of Paceco’s calculations as soon as possible.

On March 10, 1958, Paceco wrote Merritt-Chapman and restated its demand for extra compensations for engineering work. In addition, Paceco asserted that Pacific had the obligation to furnish the hoist pull capacities to Paceco. “As soon as we receive the revised capacities from Pacific Car and Foundry we will furnish the information requested in Harza Engineering Company’s letter, and at the same time will submit our prices for additional engineering, as well as our revised shipping schedule.” (emphasis added)

On March 25 and April 14, 1958, Merritt-Chapman sent revised computations for hoist breakaway loads to Paceco. On April 25, 1958, Paceco wrote to Merritt-Chapman. In the letter Paceco asserted that Merritt-Chapman had misinterpreted the meaning of the “gate motion factor of safety” clause. It then stated that someone else had the responsibility for determining the hoist capacities; so that until they were received, all work would cease. The demand for more compensation was reiterated; “Please be advised that revisions to the hoist capacities from those previously agreed upon in your letters of October 29, 1957 and January 16, 1958 will result in increased cost on the various units.” (emphasis added)

On May 16, 1958, Merritt-Chapman replied to Paceco’s demands.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TNT Cattle Co. v. Fife
304 Neb. 890 (Nebraska Supreme Court, 2020)
Beohm v. Pickel (In re Pickel)
493 B.R. 258 (D. New Mexico, 2013)
Shahani v. United Commercial Bank
457 B.R. 775 (N.D. California, 2011)
Mammoth Lakes Land Acquisition, LLC v. Town of Mammoth Lakes
191 Cal. App. 4th 435 (California Court of Appeal, 2010)
PAMI-LEMB I Inc. v. EMB-NHC, L.L.C.
857 A.2d 998 (Court of Chancery of Delaware, 2004)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
Ricketts v. Adamson
483 U.S. 1 (Supreme Court, 1987)
Snow v. Western Savings & Loan Ass'n
730 P.2d 204 (Arizona Supreme Court, 1987)
United California Bank v. Prudential Insurance Co. of America
681 P.2d 390 (Court of Appeals of Arizona, 1983)
Twenty-Four Collection, Inc. v. M. Weinbaum Construction, Inc.
427 So. 2d 1110 (District Court of Appeal of Florida, 1983)
Copylease Corp. of America v. Memorex Corporation
403 F. Supp. 625 (S.D. New York, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
411 F.2d 889, 1969 U.S. App. LEXIS 12447, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-coast-engineering-company-a-corporation-v-merritt-chapman-scott-ca9-1969.