Pat's Construction Service, Inc. v. Insurance Co. of the West

141 P.3d 885, 2005 Colo. App. LEXIS 1954, 2005 WL 3211681
CourtColorado Court of Appeals
DecidedDecember 1, 2005
DocketNo. 04CA1085
StatusPublished
Cited by1 cases

This text of 141 P.3d 885 (Pat's Construction Service, Inc. v. Insurance Co. of the West) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pat's Construction Service, Inc. v. Insurance Co. of the West, 141 P.3d 885, 2005 Colo. App. LEXIS 1954, 2005 WL 3211681 (Colo. Ct. App. 2005).

Opinion

Opinion by:

Judge ROMAN.

In this surety bond action, plaintiff, Pat’s Construction Service, Inc., appeals the judgment entered on a directed verdict as to one claim in favor of defendant, Insurance Company of the West (ICW). ICW appeals the denial of its motion for attorney fees, the amount of prejudgment interest, and the costs awarded to Pat’s Construction as to another claim. We affirm in part, reverse in part, and remand for further proceedings.

Pat’s Construction, a subcontractor, entered into a contract with a general contractor to perform construction work at Warren Knapp Elementary School and Green Mountain High School. When Pat’s Construction requested payment for additional work on both projects, the general contractor refused. Pat’s Construction then demanded payment from ICW, which acted as the surety for both projects.

When ICW also refused to pay, Pat’s Construction commenced this action, asserting breach of contract against the surety only. Although this action is premised on the allegation that the general contractor initially breached its contract, Pat’s Construction did not name the general contractor as a defendant or attempt to have money withheld from the bond pending resolution of the dispute under the Colorado Public Works Act, § 38-26-101, et seq., C.R.S.2005.

After Pat’s Construction presented its case-in-chief, ICW moved for a directed verdict on the Green Mountain claim because the evidence showed it was brought “about 10 months after the statute of limitations had run.” ICW asserted that no legal authority existed for Pat’s Construction’s claim that “the 3-year statute of limitations on a [common law contract claim] applies rather than the statutory limit.” The trial court agreed and granted the motion.

The jury returned a verdict in favor of Pat’s Construction on the Warren Knapp claim and awarded $9,430.08 in damages. The trial court then awarded Pat’s Construction $3,028.91 in interest and $3,654.13 in costs.

I.

Pat’s Construction contends the trial court erred in directing a verdict on its Green Mountain claim. Specifically, Pat’s Construction argues that § 38-26-105, C.R.S. 2005, is not an exclusive remedy and that it can pursue claims under the common law and § 38-26-107, C.R.S.2005. Therefore, according to Pat’s Construction, the six-month limitation period in § 38-26-105, which the trial court relied upon, is inapplicable. We disagree.

A motion for a directed verdict should not be granted unless the evidence compels the conclusion that reasonable jurors could not disagree and that no evidence or inference has been received at trial upon which a verdict against the moving party could be sustained. The trial court must view the evidence in the light most favorable to the nonmoving party. We review a directed verdict de novo. Fair v. Red Lion Inn, 943 P.2d 431 (Colo.1997); Brossia v. Rick Constr., L.T.D. Liab. Co., 81 P.3d 1126 (Colo.App.2003).

Statutes of limitations serve to promote justice, discourage unnecessary delay, and forestall the pursuit of stale claims. Dean Witter Reynolds, Inc. v. Hartman, 911 P.2d 1094 (Colo.1996). In the absence of a clear expression of legislative intent to the contrary, a statute of limitations specifically addressing a particular class of eases will control over a more general or catch-all statute of limitations. Mortgage Invs. Corp. v. Battle Mountain Corp., 70 P.3d 1176 (Colo.2003).

As relevant here, § 38-26-101, et seq., provides two separate methods for subcontractors on public works projects to collect payment from a surety if the contractor fails to pay them.

First, § 38-26-105(1), C.R.S.2005, provides subcontractors with the right to bring an action against the principal and the surety of a public works payment bond “within six months after the completion of the work and not afterwards.”

Second, a subcontractor may file with the public entity a verified statement of amounts [888]*888due and unpaid until the date fixed for final settlement. Section 38-26-107. The subcontractor may then file an action under § 38-26-107 against either the contractor or the surety, but the suit must be commenced within ninety days of the date fixed for final settlement. Section 38-26-107(3), C.R.S. 2005; Rocky Mountain Ass’n of Credit Mgmt. v. Marshall, 44 Colo.App. 467, 615 P.2d 68 (1980).

A.

Pat’s Construction first argues that, as the third-party beneficiary of the bond between the general contractor and ICW, it has a common law breach of contract claim against ICW. Because common law contract claims are subject to a three-year statute of limitations, Pat’s Construction contends that the trial court improperly dismissed this claim under § 38-26-105. We reject this contention.

Section 13-80-101(l)(a), C.R.S.2005, is a general and broad provision that encompasses all common law contract actions, while § 38-26-105 is a specific provision that applies to actions to recover payment under a public works contractor’s performance bond. Sections 38-26-105 and 38-26-107 specifically apply to the construction project that is the subject of Pat’s Construction’s action. Therefore, the specific statute of limitations provision in § 38-26-105 controls over the general civil action provision in § 13-80-101(l)(a). See Mortgage Invs. Corp. v. Battle Mountain Corp., supra.

Nevertheless, Pat’s Construction argues that under Montezuma Plumbing & Heating, Inc. v. Housing Authority, 651 P.2d 426, 428 (Colo.App.1982), “failure to meet the statutory requirements of the public works statutes does not deprive it of its common law claims” against ICW. The Colorado Supreme Court rejected a similar contention, however, in General Electric Co. v. Webco Construction Co., 164 Colo. 232, 433 P.2d 760 (1967)(holding that the statutory six-month limitation in public works bond actions prevails over the common law limitation).

In General Electric Co. v. Webco Construction Co., the supreme court rejected the plaintiffs’ argument that the statutory six-month limitation did not apply to public works performance bonds for more than $1000. The supreme court held that “[sjuch an interpretation would be unreasonable and would thwart what we believe was the legislative intent to provide for prompt and speedy settlement of disputes involving laborers and materialmen on public buildings.” Gen. Elec. Co. v. Webco Constr. Co., supra, 164 Colo. at 238, 433 P.2d at 763.

To the extent that Montezuma Plumbing & Heating, Inc. v. Housing Authority supports a contrary conclusion, we conclude it is inconsistent with General Electric Co. v. Webco Construction Co., and therefore decline to follow it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Durango & Silverton Narrow Gauge R.R. Co. v. Wolf
411 P.3d 793 (Colorado Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
141 P.3d 885, 2005 Colo. App. LEXIS 1954, 2005 WL 3211681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pats-construction-service-inc-v-insurance-co-of-the-west-coloctapp-2005.