General Electric Company v. Webco Construction Co.

433 P.2d 760, 164 Colo. 232, 1967 Colo. LEXIS 785
CourtSupreme Court of Colorado
DecidedNovember 20, 1967
Docket21806
StatusPublished
Cited by16 cases

This text of 433 P.2d 760 (General Electric Company v. Webco Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Electric Company v. Webco Construction Co., 433 P.2d 760, 164 Colo. 232, 1967 Colo. LEXIS 785 (Colo. 1967).

Opinion

Opinion by

Mr. Justice Day.

The parties are here in the same order that they appeared in the trial court and will be referred to as *234 follows: Plaintiff in error as plaintiff or as G.E.; the defendants in error as defendants or Webco and National Union, respectively.

In November, 1962, Webco, as general contractor, was awarded a contract by School District No. 1 in Arapahoe County, Colorado, for the construction of some new classrooms and to make other alterations to the Flood Junior High School building in Englewood, Colorado. Pursuant to C.R.S. 1963, 86-7-6, Webco, through National Union as surety, delivered to the school district a performance bond and labor and material payment bond. One undertaking was for the faithful performance of the contract and the other bound the principal and surety to make prompt payment to suppliers for all labor and material used or required to be used in the performance of the general contract. The latter bond protection extended to suppliers of either the principal contractor or the subcontractors.

The bond provided that no action by a claimant thereunder could be instituted after the expiration of one year following the date on which the work called for in the contract was completed, but it had another provision that “any law controlling” should be deemed to amend the one year provision if such law required a shorter period of time within which the action must be brought.

Currier Electric Co., Inc. was engaged by Webco to perform the electrical work required by the principal contract. In the performance of its subcontract, the Currier company purchased material and electrical equipment from G.E.

Plaintiff instituted suit against Currier as the primary debtor and joined Webco and National Union under the provisions of the labor and material payment bond. The action was commenced on June 18, 1964 after there had been negotiations between the attorneys of the respective parties for many months. Because the Currier firm was involved in bankruptcy proceedings in the *235 federal district court, all proceedings in the action with respect to that defendant were stayed by the bankruptcy court. In both the trial court and here the action has continued only against Webco and National Union under the bond.

The trial court entered judgment for the defendants. Although finding that a balance of $14,110.10 was owing the plaintiff for materials sold and delivered to Currier, the trial court nevertheless ruled that there could be no judgment against Webco and National Union because under the provisions of C.R.S. 1963, 86-7-4, plaintiff was required to commence its action on the material and labor bond within six months after the completion of the work under the principal contract; that more than six months had elapsed between the time the principal contract work was completed and the date of the commencement of the action; and that therefore the action against the principal and surety was barred.

As grounds for reversal of the judgment, plaintiff advances three arguments:

I. An action on a public works contractor’s bond for more than $1000 is not subject to a six months statute of limitations;
II. The actual completion of the work was less than six months prior to the bringing of the suit; and
III. Defendants, by the conduct of their attorneys, were estopped to raise the defense of the six months statute of limitations.

We will discuss plaintiff’s contentions in that order.

I.

For a resolution of the problem as to whether there is a six months statute of limitations which barred this action, an analysis of several sections of the statutes involving public construction is called for. One is C.R.S. 1963, 86-7-4. It was originally enacted as chapter 135 of the Session Laws of 1915 and provides that before commencing any work the “person” to whom a public *236 works'contract is awarded is required to furnish a bond conditioned that there shall be-prompt payment -to all persons ■ furnishing labor or materials, whether to the principal contractor or subcontractors. The .section is concluded with the following language:

“* *■ * Subcontractors,. materialmen, mechanics and others, may have a right of action for amounts lawfully due them- from the contractor or subcontractor, directly against the principal and surety of such bond. Such ■ action for material furnished or • labor rendered shall be brought 'within six months after the completion of the work and not afterwards.” (Emphasis added.)

Subsequent sections of C.R.S. 1963, 86-7-5 through 7, retained by the Revisor of Statutes and reenacted in the 1953- and 1963 Colorado Revised Statutes were originally enacted as Chapter 155 of the Session Laws of 1923. Section 86-7-5 defines what is meant by a “contractor” of public works contract. Section 86-7-6 provides that on all contracts of more than $1000 the principal contractor shall deliver a performance bond, i.e., binding the principal and surety .to the public agency for the faithful performance of the public works project. There is an . additional provision to protect laborers and materialmen, not only against the bond but when read with 86-7-7 provides for - them another remedy • whereby their unpaid claims may be filed for payment with the public agency. The latter is thereafter required for a period of no longer than ninety days following a date fixed and published for final settlement with the principal contractor to withhold payment on the contract in an amount sufficient to cover any such claims. There is no repetition of the requirement to commence action within six months.

Therefore, the question presented is: Did the legislature by its 1923 enactment repeal by implication 86-7-4 as to all contracts over $1000; and does there remain only the bond required by 86-7-6 on- all contracts over $1000? We answer this question in the *237 negative because of the following legislative history:

The 1923 act dealing with public contracts contained four sections which were not republished by the Statutory Revisor in presenting the Revised Statutes for reenactment. One of the original sections in the 1923 enactment provided:

“Nothing in this Act shall be held to repeal Chapter 135 of the Session Laws of 1915, approved April 12, 1915, but the requirement of said Chapter 135 shall be construed with the requirements of the within Act to the end that the privileges, requirements and remedies of both shall be available to all concerned.” (Emphasis added.)

From this language it is plain that 86-7-4 applied to all contracts regardless- of amount and still does. It was not repealed by implication. In fact, the contrary is expressly stated. With the intention of the legislature so clearly spelled out at the time of the additional provisions in the Act of 1923, it is axiomatic that this court must give full force and effect to the legislative mandate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weize Co. v. Colorado Regional Construction, Inc.
251 P.3d 489 (Colorado Court of Appeals, 2010)
Preferred Fire Protection, Inc. v. Joseph Davis, Inc.
954 A.2d 20 (Superior Court of Pennsylvania, 2008)
Pat's Construction Service, Inc. v. Insurance Co. of the West
141 P.3d 885 (Colorado Court of Appeals, 2005)
Tucker Ex Rel. Edwards v. Gorman
944 P.2d 653 (Colorado Court of Appeals, 1997)
McHargue v. Stokes Division of Pennwalt Corp.
649 F. Supp. 1388 (D. Colorado, 1986)
Rocky Mountain Ass'n of Credit Management v. Marshall
615 P.2d 68 (Colorado Court of Appeals, 1980)
ROCKY MOUNTAIN ASS'N v. Marshall
615 P.2d 68 (Colorado Court of Appeals, 1980)
Fountain Sand & Gravel v. Chilton Const. Co.
578 P.2d 664 (Colorado Court of Appeals, 1978)
Matter of the Estate of Colacci
549 P.2d 1096 (Colorado Court of Appeals, 1976)
City & County of Denver v. Blue
500 P.2d 970 (Supreme Court of Colorado, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
433 P.2d 760, 164 Colo. 232, 1967 Colo. LEXIS 785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-electric-company-v-webco-construction-co-colo-1967.