Montezuma Plumbing & Heating, Inc. v. Housing Authority of Montezuma County

651 P.2d 426, 1982 Colo. App. LEXIS 838
CourtColorado Court of Appeals
DecidedMay 6, 1982
Docket81CA0798
StatusPublished
Cited by11 cases

This text of 651 P.2d 426 (Montezuma Plumbing & Heating, Inc. v. Housing Authority of Montezuma County) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montezuma Plumbing & Heating, Inc. v. Housing Authority of Montezuma County, 651 P.2d 426, 1982 Colo. App. LEXIS 838 (Colo. Ct. App. 1982).

Opinion

TURSI, Judge.

Appellants seek to set aside summary judgments dismissing their respective claims. We affirm in part and reverse in part.

In actions consolidated for trial, appellants, Montezuma Plumbing & Heating, Ken Wegher, Durango Ornamental Iron, and Mountain Gravel & Construction Company, are unpaid suppliers of labor and materials for a housing project of which the Housing Authority was the owner and Col-vet, Inc., the principal contractor. Pursuant to the contract between Colvet and the Housing Authority and the statutory requirements of the public works statutes, §§ 38-26-105 and 38-26-106, C.R.S.1973 (1981 Cum.Supp.), Colvet obtained a performance bond and a labor and material bond from Balboa.

The project in issue was commenced in Spring 1979. It was substantially completed on November 7, 1979, and deemed complete and accepted by the Housing Authority on November 20, 1979. Following published notice, final settlement was made on December 20, 1979.

MONTEZUMA PLUMBING & HEATING

Montezuma Plumbing & Heating argues that, although it has no remedy under the public works statutes, §§ 38-26-105 through 38-26-107, C.R.S.1973 (1981 Cum. Supp.), for failure to file timely claims, it has common law rights under both bonds as a third-party beneficiary, and has rights to the funds retained by the Housing Authority under a quantum meruit theory.

Montezuma Plumbing & Heating filed its initial complaint on April 4,1980, seeking to foreclose a mechanic’s lien filed against the Housing Authority’s property. On March 5, 1981, it asserted, as counterclaims and cross-claims against Colvet, Balboa, and the *428 Housing Authority, a claim on the labor and material bond and the retainage.

Montezuma Plumbing & Heating does not appeal the dismissal of the mechanic’s lien claim.

We agree with Montezuma Plumbing & Heating that failure to meet the statutory requirements of the public works statutes does not deprive it of its common law claims against Colvet and Balboa. Flaugh v. Empire Clay Products, Inc., 157 Colo. 409, 402 P.2d 932 (1965); Continental Casualty Co. v. Rio Grande Fuel Co., 108 Colo. 472, 119 P.2d 618 (1941).

Montezuma Plumbing & Heating claims that its rights as a third-party beneficiary arise out of the contract between the Housing Authority and Colvet. That contract required Colvet to provide and pay for all labor and materials and to furnish a performance bond and a labor 4nd material bond. It claims relief under both bonds— the performance bond because obstensibly Colvet did not fully perform until the subcontractors were paid, and the labor and material bond because they were intended beneficiaries of the bond. The latter proposition concerning the labor and material bond is correct.

Balboa and the Housing Authority claim that privity of contract is required between the labor and materials claimant and the owner in order to prevail on a third-party beneficiary contract. We do not agree.

“Colorado follows the rule that one may enforce a contractual obligation made for his benefit although he was not a party to the agreement,” and the promise to be enforced is apparent from express provisions of the agreement. Cox v. Fremont County Public Building Authority, 415 F.2d 882 (10th Cir. 1969); Borwick v. Bober, 34 Colo.App. 423, 529 P.2d 1351 (1974). See Fourth & Main Co. v. Joslin Dry Goods Co., Colo.App., 648 P.2d 178 (1982). As to the labor and material bond, its express provisions and § 38-26-105, which requires that it be furnished, indicate that all persons supplying the contractor or his subcontractors with labor or materials are intended beneficiaries of the contract.

However,, no claim arises under the performance bond which contains the following language:

“No right of action shall accrue on this bond to or for the use of any person or corporation other than the Owner named herein [Housing Authority].. .. ”

Cf. Corn Construction Co. v. Aetna Casualty Co., 295 F.2d 685 (10th Cir. 1961). (Labor and materials claimant could sue on performance bond where contract contained express provisions enjoining contractor to pay labor and materials suppliers).

Balboa contends that the one-year limitation on actions contained in the bond is superseded by the six-month limitation found in § 38-26-105 and applicable to § 38-26-106 pursuant to General Electric Co. v. Webco Construction Co., 164 Colo. 232, 433 P.2d 760 (1967). We do not agree.

In General Electric, a one-year limitation was contained in the bond, but the statutory six-month limitation was applied presumably because of a “provision that ‘any law controlling’ should be deemed to amend the one year provision if such law required a shorter period of time within which the action must be brought.”

Here, the labor and material bond contains the following provision:

“No suit or action shall be commenced hereunder by any claimant. . . .
(b) After the expiration of one (1) year following the date on which Principal ceased work on said Contract, it being understood, however, that if any limitation embodied in this bond is prohibited by any law controlling the construction hereof such limitation shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law.”

Here, the language of the bond prohibits a shorter limitation of time than permitted by law, whereas in General Electric, the bond provision specifically stated that a shorter statutory limitation applied. Because we do not read §§ 38-26-105 and *429 38-26-106 as prohibiting a longer period of limitation in a labor and material bond, we hold that the one-year limitation contained in the bond applies here.

The project here was complete in November 1979 and Montezuma Plumbing & Heating did not make any claim on the bond until March 1981. Therefore, summary judgment was properly entered against Montezuma Plumbing & Heating on that issue.

Montezuma Plumbing & Heating further contends that it has a claim to the funds retained by the Housing Authority pursuant to § 38-26-107 on the theory of quantum meruit. We disagree.

In the absence of privity, subcontractors have no claim based on quantum meruit against a governmental body for retained funds when an appropriate bond has been furnished pursuant to statute. Kennedy Electric Co. v. U. S. Postal Service, 367 F.Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pat's Construction Service, Inc. v. Insurance Co. of the West
141 P.3d 885 (Colorado Court of Appeals, 2005)
Davis Oil Company v. Ts, Inc.
145 F.3d 305 (Fifth Circuit, 1998)
C M Warehouse v. Eastern Trucking, No. Cv93-052412 S (Sep. 27, 1994)
1994 Conn. Super. Ct. 9819 (Connecticut Superior Court, 1994)
Galie v. RAM Associates Management Services, Inc.
757 P.2d 176 (Colorado Court of Appeals, 1988)
Autocon Industries, Inc. v. Western States Construction Co.
728 P.2d 374 (Colorado Court of Appeals, 1986)
Travelers Insurance Co. v. Savio
706 P.2d 1258 (Supreme Court of Colorado, 1985)
Savio v. Travelers Insurance Co.
678 P.2d 549 (Colorado Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
651 P.2d 426, 1982 Colo. App. LEXIS 838, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montezuma-plumbing-heating-inc-v-housing-authority-of-montezuma-county-coloctapp-1982.