Morrison-Knudsen Co. v. United States

84 F. Supp. 282, 113 Ct. Cl. 536, 1949 U.S. Ct. Cl. LEXIS 58
CourtUnited States Court of Claims
DecidedJune 6, 1949
Docket46770
StatusPublished
Cited by4 cases

This text of 84 F. Supp. 282 (Morrison-Knudsen Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrison-Knudsen Co. v. United States, 84 F. Supp. 282, 113 Ct. Cl. 536, 1949 U.S. Ct. Cl. LEXIS 58 (cc 1949).

Opinion

MADDEN, Judge.

The plaintiff made a contract with the Government to construct the Roza diversion dam, bench flume, and railroad bridge in the Roza Division of the Yakima Project of the Bureau of Reclamation, Department of the Interior. The work was near Yakima, Washington. Specifications for the work and invitations for bids were sent out on July 2, 193-8. Bids were opened on August 5. The plaintiff was the low bidder, and being satisfied that it would be awarded the contract in due course, it started work on August 15 at its own risk of not ultimately getting the contract. On August 29 it was awarded the contract which was dated August 30. The contract was based on unit prices bid by the plaintiff, so much, e. g., for placing a cubic yard of concrete. The contract prices, applied to the Government’s estimate of the number of units of work, gave an estimated cost of $526,860 for the performance of the contract.

The plaintiff was given notice to proceed on September 24, 1938. The contract provided that work should commence within 30 days after notice to proceed, and should be completed within 550 days thereafter. Thus the completion date was fixed at March 27, 1940. In fact, the work was accepted by the Government on December 28, 1939. On April 19, 1940, there was a settlement of the contract account, final payment was made to the plaintiff and it gave the Government a release in which, however, it reserved eight items of claim, which items constitute the subject of this suit. The suit alleges that in various ways the Government breached its contract with the plaintiff.

Transmission Line

As shown in our Finding No. 9, the Government, in the contract, agreed that it owned or would acquire a certain electric power transmission line which led to a point near the project, and would permit the contractor to use the line without charge in performing the contract work. This provision had been written into the proposed contract when it was sent out with invitations for bids, and remained in the contract made with the plaintiff. It so happened that this power line had been built by the power company some two years before under an arrangement with the plaintiff, which was then performing another contract with the Government and needed power. As soon as the plaintiff started work on the contract here in litigation, it made an arrangement with the power company to extend the line from its former terminus to a point near the new work, and to install the necessary equipment to make the power available. This was done. The Government did not actually obtain a deed for the power line until August 1940. The plaintiff claims that the Government, by not acquiring title to the power line immediately, breached its contract to make the line available without *284 charge, to the plaintiff’s damage. It claims some $1,800 as the rental, value for the period; or some $1,900 as reimbursement of payments made by it to the power company for the use of the line. The plaintiff is not. entitled to rent, since it did not own the line or any such interest in it as would form a basis for rent. Its - former arrangement with the power company had been to. reimburse the company for labor and depreciation when the line was dismantled, as it was then contemplated that it would be. In fact it was not dismantled,, but was bought by the Government, and, so far as appears, the plaintiff was never called upon to reimburse the power company. . As to the payments which the plaintiff says it made to the company, the evidence is not satisfactory, but it seems more probable that those payments were not for the use of the old line but for the extension and equipment of the new line, and hence were not covered by the Government’s promise to acquire and make available the old line. The plaintiff has not proved that it was harmed by the Government’s tardy acquisition of title to the old line, and cannot recover on this item.

Compacted Fills

The provisions of the contract relating to this item are quoted in Finding No. 12. The plaintiff says that the Government breached its contract in requiring it to use for these fills material excavated on this job, although this material contained more than 25% of oversize rock which had to be picked out of the material and disposed of before the material could be properly compacted. The plaintiff points to paragraph 46(b) of the specifications which says that, “Insofar as practicable, suitable material satisfactory to the contracting officer, obtained from required excavations” shall be used, “but where sufficient suitable material is not available from this source additional materials shall be obtained from borrow pits designated by the contracting officer”. It says it was not “practicable” within the meaning of the contract, to require the contractor to go to the expense of picking out the oversize rocks to make the excavated material, usable for compacting. It says that the Government showed this lack of consideration for the-interests of the- plaintiff- in order to save itself the extra cost, 50 cents per cubic yard, which it would have had to pay if new material had been taken from a borrow pit and used in place of the material already excavated and paid for. We do not say that such a lack of consideration for the interests of the plaintiff might not constitute a breach of contract, but we find the same impediment to recovery here as in the item of the claim' relating to the transmission line. The plaintiff has not shown that it was harmed by not being given the privilege. It has not shown that there was available any source of borrow material that could have been obtained at a cost less than the cost of picking out the oversize rock from the excavated material, considering, of course, the extra 50 cents per cubic yard which it would have- received for taking material from the borrow pit. The area of the work, as described in our Finding No. 23, was a short, narrow oval-shaped valley. If there was within this area an available borrow location, the plaintiff has not given evidence of its existence or location. If it would have been necessary to go outside this valley for borrow, the cost of hauling, as shown in Finding No. 33 would have soon accounted for any saving otherwise made. The .plaintiff not having proved that it was damaged, or, if damaged, how much, may not recover on this item of its claim.

Rock Protection

The contract called for the placing of rock protection in the forms of dumped riprap, placed riprap, and dry rock paving. The provisions of the contract are set out in Finding No. 22. As to the dumped riprap, which constituted the great preponderance of the cubic yardage of rock protection, the contract required that a considerable proportion of the rocks should contain six or more cubic feet. When the rock for. this work was blasted .at the quarry site, it did not produce rocks of this size. A change order reducing the size to four cubic feet and reducing the unit price from $1.40 to $1.30 per cubic yard was offered to the plaintiff, which refused to accept the reduction in price. It placed the smaller rock, and was ultimately paid the original *285 contract price and made a profit on this part of the rock protection work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
84 F. Supp. 282, 113 Ct. Cl. 536, 1949 U.S. Ct. Cl. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrison-knudsen-co-v-united-states-cc-1949.