Howard P. Foley Co. v. United States

63 F. Supp. 209, 105 Ct. Cl. 161, 1945 U.S. Ct. Cl. LEXIS 120
CourtUnited States Court of Claims
DecidedDecember 3, 1945
Docket45739
StatusPublished
Cited by5 cases

This text of 63 F. Supp. 209 (Howard P. Foley Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard P. Foley Co. v. United States, 63 F. Supp. 209, 105 Ct. Cl. 161, 1945 U.S. Ct. Cl. LEXIS 120 (cc 1945).

Opinion

WHALEY, Chief Justice.

The plaintiff had a contract with the Civil Aeronautics Authority to furnish and install the field lighting at the Washington National Airport.

The airport was constructed at Gravelly Point, Virginia, and was on “made land.” The site was created by hydraulic dredging and one of the problems, before the Government engineers was how to expedite stabilization of the dredged material, which of course was heavily charged with watera Instead of using the conventional method of erecting boundary dykes and pouring the dredged material within the boundary thus made, with overflowing water, the engineers conceived the idea of pouring the dredged material directly on the location of the projected runways, letting the finer materials flow off to the sides. Even with this expedited process there were difficulties that retarded the work, for pockets of fines would inevitably form, and, where two dredges worked toward each other, there would be fine material at the point of union, which had to be excavated and replaced with compactible material, necessary for the foundation of the runway. The runways were to bear the burden of heavy traffic, the landing and taking off of planes.

Plaintiff’s work could not proceed until the ground was ready. Plaintiff claims that its work, or some of it, could have proceeded before the final surface had been finished, but that was a matter for de *215 fendant’s engineers, not the plaintiff, to decide. Plaintiff’s work was essentially a “follow-up” job, just as is that of a plumber.

Article 1-11 of the specifications gave direction of the work to the Government’s representative.

Regardless of any eventual practical considerations in the field, plaintiff knew beforehand that releases would be made to it only as paving of runways and rough-grading of shoulders were completed. Article 5-2 of the specifications gave priority to .such paving and rough-grading.

Plaintiff’s complaint, however, is not that the work was released to it in sections, but that the releases were so far apart as to •extend its time for performance unduly and •unreasonably.

The contracting officer seems to attribute ■some of the delay to the paving contractor, 'but the plaintiff does not rely on the paving contractor’s responsibility for tardiness and we are without factual information with regard thereto.

The Government’s representatives and ■operating force acted with great, if not unusual, diligence. They availed themselves •of novel methods to assure expedition. No fault is or can be attributed to them.

The contracting officer’s findings of fact •charge delay in releasing certain stabilized areas to “unforeseen” soil conditions. This job involved an hydraulic fill. In every respect operations appear to have proceeded according to plan, a novel plan, and the plan, so pursued, expedited matters greatly.

But charging delay to “unforeseen” conditions is not charging them to “unforeseeable” conditions, which Article 9 of the contract provides for. There is nothing present in the contract situation, as evidenced here, that made soil conditions unforeseeable. Apparently the fill was just what was expected, the coarser material remaining in the runway, the fines sloughing off to the side, precisely as planned.

There is no other conclusion than that the original time limitation of 120 days was a mistaken calculation, neither more nor less. It turned out that way, whether the Government’s contracting officer knew it in the beginning or not.

This case is to be distinguished from Crook Co. v. United States, 270 U. S. 4, 46 S.Ct. 184, 70 L.Ed. 438. In that case it was said, referring to a time limitation .such as we have here: “But it was obvious on the face of the contract that this date was provisional. The Government reserved the right to make changes and to interrupt the stipulated continuity of the work.” Id., 270 U.S. at page 6, 46 S.Ct. 184, 70 L.Ed. 438. We understand this to mean that the provisional nature of the time limitation, is just that, “provisional” not independent, and what makes it provisional is the reservation of “the right to make changes and to interrupt the stipulated continuity Of the work." What the Supreme Court was considering was the interlocking of two contracts, the construction or prime contract and the follow-up contract. In the instant case there is no construction or prime contract, except as plaintiff’s contract may be considered the “prime” contract.

In the Crook case, supra, the right to make changes in the prime contract was operative and that is what the Supreme Court obviously had in mind. The construction work was being done by the prime contractor, the Crook Company’s work of installing a heating system being dependent upon the prime contractor’s progress. The fact that the basic work of construction was being done by another contractor brought the provision for changes into play.

The Government does not order itself to make changes. The contracting officer’s findings of fact indicate that the grading was done by “force account,” that is, by a force of men hired by the Government, and not done through a contractor, except as to paving, in respect to which there is no record upon which any material finding can be made. Under these circumstances, there was no room for changes. There was no prime contract to be changed.

The time limitation in plaintiff’s contract therefore, under this view, was not provisional, because provisionally was dependent upon the existence of an operative change clause in the prime contract. This change clause is here wholly absent, and the Government’s obligation is fixed accordingly.

It would be a strained construction to take the contract here in suit as allowing one of the contracting parties, the defending Government, an unlimited time for performance.

The Government set the time for performance, 120 days, and both parties had certain things to do within that time. The period of actual performance turned out to be 277 calendar days, as compared with the *216 original contract time of 120 days. As appears by the findings of fact, plaintiff’s was a follow-up contract, so that the period of 277 days represents practically the time consumed by both parties running concurrently. The extra time of 157 days is not chargeable to delays, strictly speaking, for defendant’s engineers were “skillful and diligent in their work.” It is not chargeable to changes, for there were none. It is not chargeable to any act committed or omitted by the plaintiff.

There is no prime contractor here that might have delayed the plaintiff’s work, a situation present in the Crook Co. case, supra, which would give a provisional character to the time clause. In the Crook case the presence of a prime contractor made the time clause in the follow-up contract provisional, because the prime contractor might not keep up to time. In the Crook case “the contract,” as the Court said, “showed that the specific buildings referred to were in process of construction by contractors who might not keep up to time.” We cannot twist this statement into reading : “by the Government, which might not keep up to time.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cedar Lumber, Inc. v. United States
32 Cont. Cas. Fed. 72,561 (Court of Claims, 1984)
L. L. Hall Construction Company v. The United States
379 F.2d 559 (Court of Claims, 1966)
United States v. Howard P. Foley Co.
329 U.S. 64 (Supreme Court, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
63 F. Supp. 209, 105 Ct. Cl. 161, 1945 U.S. Ct. Cl. LEXIS 120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-p-foley-co-v-united-states-cc-1945.