Lykes-Youngstown Corporation v. The United States

420 F.2d 735, 190 Ct. Cl. 348, 1970 U.S. Ct. Cl. LEXIS 186
CourtUnited States Court of Claims
DecidedJanuary 23, 1970
Docket399-67
StatusPublished
Cited by8 cases

This text of 420 F.2d 735 (Lykes-Youngstown Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lykes-Youngstown Corporation v. The United States, 420 F.2d 735, 190 Ct. Cl. 348, 1970 U.S. Ct. Cl. LEXIS 186 (cc 1970).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS MOTION FOR SUMMARY JUDGMENT

SKELTON, Judge.

This is a suit by a steamship company against the United States for damages for an alleged breach of three construction-differential subsidy contracts involving the construction of twelve ships. (Four ships in each of the contracts.) 1

The plaintiff is now, and, at all times relevant to this case, has been engaged in the business of operating ocean-going cargo ships on regular routes found by the Maritime Subsidy Board to be essential trade routes of the United States between ports in this country and ports in foreign countries throughout the world. 2

These operations are conducted under an operating-differential subsidy contract (No. FMB-59) entered into pursuant to Title VI of the Merchant Marine Act of 1936, 49 Stat. 1985, as amended (46 U.S.C. §§ 1171-1183) by plaintiff *737 and the United States in 1957 for a term of twenty years beginning January 1, 1958. Under this contract, plaintiff is required to perform specified numbers of voyages annually on essential trade routes and to replace its existing ships by contracting to build new ones. The replacement program in the contract required plaintiff to build three groups of four ships each, construction of which was to commence on or about March 18, 1963, July 1, 1963, and July 1, 1964, respectively. Plaintiff’s obligation to have these ships constructed was conditioned upon the board’s policy to provide construction-differential subsidy pursuant to Title V of the Act for such new construction, and, if not provided, was to be deferred until such subsidy was provided.

The purpose of the construction-differential subsidy, which is a shipyard subsidy, is to equalize the cost of building ships in high-cost domestic United States shipyards with the lower cost of building such ships in foreign shipyards, from the standpoint of the owner, which is required by law and contract to have its ships built in the United States. The plaintiff filed applications for construction-differential subsidy covering each of the three groups of ships and the Board approved such applications and agreed to provide construction-differential subsidy in accordance with contracts entered into between the plaintiff and the defendant as described in the following paragraphs.

On April 4, 1963, November 21, 1963, and June 26, 1964, the plaintiff, as owner, and the Board entered into three construction-differential subsidy contracts Nos. MA/MSB-20, MA/MSB-31, and MA/MSB-37, each covering a group of four ships and each specifying the terms of the grant of subsidy by the Board in connection with the construction of said ships. At the same time, three construction contracts, Nos. MA/MSB-19, MA/MSB-30, and MA/MSB-36, were entered into between the plaintiff, as owner, and Avondale Shipyards, Inc., as contractor, and the Board, which provided for the construction of the twelve ships by the contractor. These construction contracts are only incidentally involved in this case. Each of the construction contracts contained the same provisions as those set forth below from contract No. MA/MSB-19, differing only in the amount of subsidy per vessel and the percentage for changes determined by the Board to be eligible for subsidy:

******

ARTICLE IY. Payment of Contract Price, (a) Progress payments on account of the Contract Price, adjusted as herein provided, shall be made to the Contractor by the Owner and the Board as the Contract work progresses. * * * Such progress payments shall be made at monthly intervals or at such other intervals as the parties agree and as follows:

(i) The Board shall pay the Contractor forty-nine and eight-tenths percent (49.8%) and the Owner shall pay the Contractor fifty and two-tenths percent (50.2%) of that portion of each progress payment on account of the Contract Price set out in Article 1(a) hereof (excluding, however, the sum of Three Thousand Three Hundred and Sixty Dollars ($3,360) of the Contract Price for the National Defense Features incorporated in the Vessels).

(ii) The Board shall pay the Contractor forty-nine and eight-tenths percent (49.8%) and the Owner shall pay the Contractor fifty and two-tenths percent (50.2%) of that portion of each progress payment on account of the net increase in Contract Price, pursuant to Article 4 of the General Provisions, for changes in the contract work approved by the Board as eligible for construction-differential subsidy; provided, however, in the event there is a net decrease in the Contract Price on account of such changes, the amounts otherwise payable by the Owner and the Board pursuant to this Article IV shall be reduced by the respective percentages of such net decrease.

*738 ******

(v) The Owner shall pay the Contractor one hundred percent (100%) of that portion of each progress payment covering increases in the Contract Price pursuant to Article 4 of the General Provisions hereof on account of changes of the Owner approved by the Board but not approved as eligible for construction-differential subsidy; provided, however, in the event there is a decrease in the Contract Price on account of such changes, the amounts otherwise payable by the Owner shall be reduced by the amount of such decrease. 3

* * * * * *

The contractor is not a party to this suit. When the dispute arose between the plaintiff and the Board, an agreement was signed between them to the effect that the plaintiff would make payments to the contractor in excess of the amounts which plaintiff contends should be paid by it and that the making of such payments should be without prejudice to the rights of the plaintiff to assert its contention in court to recover from the United States the amounts which the plaintiff claims it is entitled to as subsidy for the changes involved in this ease. Consequently, we are not required to determine any rights which the contractor may have had with respect to these construction contracts. However, the pertinent provisions of such contracts, which are quoted above, are included here so that the whole picture may be presented with respect to the claim of the plaintiff for subsidy payments arising out of the changes in its vessels described above.

Each of the three construction-differential subsidy contracts contained provisions that are pertinent to this case which are the same as those set forth below from contract No. MA/MSB-20, differing only in the amount of subsidy per vessel and the percentage for changes determined by the Board to be eligible for subsidy: 4

ARTICLE 1. Grant of Construction-Differential Subsidy. (a) The Board grants, in compliance with the provisions of Sections 501 and 502 of the Act, a construction-differential subsidy to aid in the construction of the Vessels by the Owner in the total sum of the following:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The United States v. Human Resources Management, Inc.
745 F.2d 642 (Federal Circuit, 1984)
Farrell Lines Inc. v. United States
499 F.2d 587 (Court of Claims, 1974)
Canadian Commercial Corp. v. United States
202 Ct. Cl. 65 (Court of Claims, 1973)
Sun Shipbuilding & Dry Dock Co. v. United States
461 F.2d 1352 (Court of Claims, 1972)
Perry and Wallis, Inc. v. The United States
427 F.2d 722 (Court of Claims, 1970)
Lockheed Aircraft Corporation v. The United States
426 F.2d 322 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
420 F.2d 735, 190 Ct. Cl. 348, 1970 U.S. Ct. Cl. LEXIS 186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lykes-youngstown-corporation-v-the-united-states-cc-1970.