Graham v. Cooper

86 A. 991, 119 Md. 358, 1913 Md. LEXIS 175
CourtCourt of Appeals of Maryland
DecidedJanuary 14, 1913
StatusPublished
Cited by2 cases

This text of 86 A. 991 (Graham v. Cooper) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graham v. Cooper, 86 A. 991, 119 Md. 358, 1913 Md. LEXIS 175 (Md. 1913).

Opinion

*359 Pattison, J.,

delivered the opinion of the Court.-

The appellant in this case, John S. Graham, a Lieutenant Commander in the IT. S. Bavy, and the owner of a lot of land at Wardour Bluffs, near the City of Annapolis, entered into a written contract with the appellant, Philip B. Cooper, a builder and contractor of Annapolis, Md., dated the 5 th day of May, 1910, by which the appellee was to build and construct for him a frame cottage on said lot of land. By this contract the appellee was not only to do the work, but was likewise to furnish the material to be used in the construction of said cottage. The work to be done and the material to be used were to conform to the specifications thereto attached and made a part of the contract. The house was to be completed not later than the 1st day of September, 1910, at which time, or upon its completion, ready for occupancy, the sum of $4,400 was to be paid therefor to the appellee by the appellant.

Upon the 1st day of September, 1910, the house was not completed and ready for occupancy, and on the 3rd of September following a supplemental agreement was entered into by and between the appellant and the appellee.

By the last agreement or contract the time in which the building was to be completed was extended to the 1st day of October, 1910, at which time it was to be completed and ready for occupancy. But the contract further provided, that should the appellee fail to complete the building at the time named therein, he was to pay to the appellant, as liquidated damages, the sum of five dollars per day, commencing with the 1st day of September, 1910, “until the building was completed and ready for occupation.” It was further provided therein, however, “That the said John S. Graham is not to be unreasonable in his interpretation of the phrase ‘completed and ready for occupation,’ but in matters of trifling moment may accept the said building, occupy the same and retain from tbe contract price such sum or sums of money as may be sufficient to complete the work in every *360 detail and particular.” In all other respects the original agreement or contract was unchanged and was to remain in full force and effect.

On October 1st, as alleged by the appellant, the building was still unfinished and not ready for occupancy. On October 13th, however, the appellant moved in and occupied the building; at which time, as he alleged, the building was still' incomplete and unfinished.

The record discloses by correspondence and otherwise that the- appellant was dissatisfied with the work done and material furnished by the appellee upon and in the erection of said house,- and contended that the work had not been completed,- and after the payment by him, in all, of the sum of $3,955.54,. the last payment being made on the 8th day of October, 1910, he refused to pay more so long as the conditions-of which he complained continued to exist.

On the 16th day of December, 1910, the balance of said contract price, $444.46, as claimed by the appellee, and the further sum of $25 for extra work likewise claimed -by the appellee, not having been paid, the appellee filed his mechanics’ lien against said house and lot of land for the sum of $469.46. On the 30th day of December he filed his bill in the. Circuit - Court for Anne Arundel County for the enforcement of his mechanics’ lien claim against the appellant and the “Workingmen’s Building and Loan Association .of Annapolis, Anne Arundel county, Maryland,” a corporation to which the appellant, by deed of mortgage, had ■conveyed said property to secure a loan from it to him. In his bill he asked for a sale of the property described in said lien, and that the proceeds thereof be distributed to him as lien or under’the order of the Court.

The defendant answered the bill, denying the allegation therein contained that the building was erected and completed in compliance with the terms of the contracts and ■specifications mentioned,, and alleged that it was at such time “in an incomplete condition, requiring and necessitating the expenditure of considerable sums of money to make *361 the same conform to the provisions, requirements and stipulations of said contracts, plans and specifications;” and that such incomplete condition of the building was due to the neglect and failure of the plaintiff to complete the same in accordance with the terms of said contracts, plans and specifications. And in his answer he denied that he was owing unto the appellee the sum of $469.46, as alleged in the bill, but charged that “by reason of his (plaintiff’s) neglect, mismanagement and flagrant disregard of the terms and requirements of the said contracts and specifications he has been.more than compensated for such work as he has done and materials furnished in and about the erection of said building.”

Upon the bill, answer and evidence the- Court below granted a decree as prayed, after first having- reduced the amount claimed to the extent of $35, of which $25 was for extra work, which the Court held had not been properly proven, and $10 for work that the appellee agreed to do and which was not done. It is from that decree that this appeal is taken.

The appellant contends:

First — That by a reasonable interpretation of the phrase “completed and ready for occupation,” found in the supplemental contract, the building was not .completed and ready for occupancy on the 1st day of October, 1910; and, therefore, by the provisions of said supplemental contract he was entitled to the liquidated damages of $5 for each and every day the -building remained incomplete and not ready for occupancy from the said first day of September until it was completed and ready for occupation, which was, as he alleges, not earlier than the 7th day of October, 1910.

Second — That the property has never been completed in conformity with the terms and provisions of the aforesaid -contracts and specifications, and that the amount required to complete the work in respect to those things which have not been done, and the loss and injury sustained by him by reason of the failure of the appellee to perform the work *362 that has been done, in accordance with the terms and provisions of the contract, together with the liquidated damages, to which he claims he is entitled by reason of the failure of the appellee to complete the building, ready for occupancy on the 1st day of October, is in excess of the amount of the contract price remaining unpaid; and thus no part of said contract price was, at the time of the filing of the mechanics’ lien or now, owing unto the said appellee.

We will first consider the second contention. We shall refer only to such parts of the specifications, which are quite voluminous, as are involved in the contentions as we have stated them.

The specifications first provided that “All work as described herein, or shown on the drawings and any work necessary to the thorough completion of the work so-described or shown, is to be executed in the most workmanlike manner, and where work and material are not specially mentioned they are to be of the highest grade and best adapted to the purpose. All materials are to be the best of their respective kinds in ample quantities.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parker v. Tilghman v. Morgan, Inc.
183 A. 224 (Court of Appeals of Maryland, 1936)
Baltimore Bridge Co. v. United Railways & Electric Co.
93 A. 420 (Court of Appeals of Maryland, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
86 A. 991, 119 Md. 358, 1913 Md. LEXIS 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graham-v-cooper-md-1913.