Reliance Insurance Co. v. Utah Department of Transportation

858 P.2d 1363, 219 Utah Adv. Rep. 14, 1993 Utah LEXIS 113, 1993 WL 314997
CourtUtah Supreme Court
DecidedAugust 16, 1993
Docket910413
StatusPublished
Cited by14 cases

This text of 858 P.2d 1363 (Reliance Insurance Co. v. Utah Department of Transportation) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliance Insurance Co. v. Utah Department of Transportation, 858 P.2d 1363, 219 Utah Adv. Rep. 14, 1993 Utah LEXIS 113, 1993 WL 314997 (Utah 1993).

Opinion

HOWE, Associate Chief Justice:

Reliance Insurance Company appeals from a judgment enforcing a liquidated damages provision in a construction contract against a contractor. We examine the validity of the liquidated damages provision and determine whether the doctrine of substantial completion applies to these facts.

FACTS

In the spring of 1985, the Great Salt Lake was rising to near-record levels and threatening a portion of Interstate Highway 80 which runs along the south shore of the lake, west of Salt Lake City. On April 30, 1985, the Utah Department of Transportation (“UDOT”) awarded a construction contract to L.A. Young Sons Construction Company (“Young”) to raise a section of the highway and protect it from the lake waters. The contract price for the entire project was approximately $9,941,000.

Young began work on May 2, 1985. The contract required that the project be completed by October 15, 1985. In relevant part, it stated:

When the contract completion time is an affixed calendar date, it shall be the date on which all work on the project shall be completed.

The contract also included a provision for liquidated damages of $600 for every day *1366 ' that work continued beyond the October 15 completion date:

[F]or each calendar day ... after a specified completion date that any work shall remain uncompleted ..., the sum specified below will be deducted from any money due the contractor, not as a penalty, but as liquidated damages for Department’s increased overhead.
[[Image here]]
When final acceptance has been duly made by the Engineer as prescribed, ... the daily time charge will cease.

On October 14, 1985, Young requested and received a 10-day extension to lay asphalt. The major work of the project was finished by October 25, 1985, and the highway was fully opened for travel. Still, further work remained, such as installing signs, furnishing topsoil, and seeding. The project also lacked some landscaping and permanent paint striping. These uncompleted requirements extended the work into the winter months, but due to weather conditions, no work was done between January 14 and February 24, 1986. Consequently, UDOT granted an additional 42-day extension for this winter time period.

Work on the project resumed on February 25, 1986, and continued intermittently until September 12, 1986. UDOT terminated time charges on June 13, 1986, after the topsoil was placed and the seeding and striping completed. Ultimately, UDOT granted an additional 43-day extension of time charges due to its own error in the process of clearing a materials site.

Plaintiff Reliance Insurance Company was surety on Young’s bond. Young eventually defaulted on several other projects, and Reliance intervened and made payments on behalf of Young. Reliance thereby became subrogated to Young’s claim against UDOT on this project. Reliance is the sole appellant in this case, and Young is not a party to this appeal.

Reliance and UDOT both agree that the sum of the allowed extensions was 85-days and that the final delay equaled 156 days. At $600 per day, the total liquidated damages withheld was $93,600. The project was federally aided and qualified for reimbursement of over ninety-four percent of the cost of approved contract items by the federal government. UDOT consulted with the Federal Highway Administration (“FHWA”) during the course of the project, and the FHWA was involved in granting extensions to the contracted time period.

Reliance brought this action to recover the $93,600 withheld by UDOT. Trial was had to the bench. The trial court upheld the liquidated damages provision as binding upon the parties. It also concluded that the doctrine of substantial performance raised by Reliance was inapplicable to these facts and therefore UDOT could retain the $93,600 as appropriate liquidated damages.

STANDARD OF REVIEW

This court gives deference to the trial court’s findings of fact, and we will not set them aside unless we find them to be clearly erroneous. Utah R. Civ.P. 52(a). Under this standard, we will not disturb factual findings unless they are against the clear weight of the evidence or we otherwise reach a definite and firm conviction that a mistake has been made. Western Kane County Special Serv. Dist. No. 1 v. Jackson Cattle Co., 744 P.2d 1376, 1377 (Utah 1987). We review the trial court’s legal conclusions for correctness, affording no deference. Ong Int’l (U.S.A.) v. 11th Ave. Corp., 850 P.2d 447, 452 (Utah 1993).

ANALYSIS

In determining the validity of a liquidated damages provision, this court has adopted section 339 of the Restatement of Contracts. Robbins v. Finlay, 645 P.2d 623, 626 (Utah 1982); Perkins v. Spencer, 121 Utah 468, 476-77, 243 P.2d 446, 450-51 (1952). Section 339 states in pertinent part:

*1367 (1) [A]n agreement, made in advance of breach fixing the damages therefor, is not enforceable as a contract and does not affect the damages recoverable for the breach, unless
(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach, and
(b) the harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.

Restatement of Contracts § 339 (1932) [hereinafter Restatement]. We will examine the validity of the UDOT provision for liquidated damages according to this standard.

I. REASONABLE FORECAST

The Restatement’s test first requires that the liquidated damages provision be a reasonable forecast of any actual increased overhead incurred by UDOT because of the delayed completion of the project. If it turns out that the liquidated damages and the actual increased overhead are reasonably related, this is persuasive evidence that the initial forecast was also reasonable. If, on the other hand, the liquidated damages are disproportionate to the actual compensatory damages sustained, this may be evidence of an unreasonable forecast and the provision may be deemed a penalty and not enforced. Young Elec. Sign v. United Standard West, 755 P.2d 162, 164 (Utah 1988) (citing Madsen v. Anderson, 667 P.2d 44, 47 (Utah 1983)). However, any disparity must be “grossly excessive” and must “shock the conscience” of this court before we declare the liquidated damages void. Allen v. Kingdon, 723 P.2d 394

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Larson v. Stauffer
2022 UT App 108 (Court of Appeals of Utah, 2022)
Anderson v. Amazon.com, Inc.
M.D. Tennessee, 2020
Smargon v. Grand Lodge Partners, LLC
2012 UT App 305 (Court of Appeals of Utah, 2012)
Mark Technologies Corp. v. Utah Resources International, Inc.
2006 UT App 418 (Court of Appeals of Utah, 2006)
In Re Estate of Flake
2003 UT 17 (Utah Supreme Court, 2003)
Bair v. Axiom Design, L.L.C.
2001 UT 20 (Utah Supreme Court, 2001)
Nunley v. Westates Casing Services, Inc.
1999 UT 100 (Utah Supreme Court, 1999)
Woodhaven Apartments v. Washington
942 P.2d 918 (Utah Supreme Court, 1997)
Woodhaven Apartments v. Washington
907 P.2d 271 (Court of Appeals of Utah, 1995)
Bagford v. Ephraim City
904 P.2d 1095 (Utah Supreme Court, 1995)
State in Interest of RAF