Ledbetter Bros. v. North Carolina Department of Transportation

314 S.E.2d 761, 68 N.C. App. 97, 1984 N.C. App. LEXIS 3208
CourtCourt of Appeals of North Carolina
DecidedMay 1, 1984
Docket8310SC192
StatusPublished
Cited by9 cases

This text of 314 S.E.2d 761 (Ledbetter Bros. v. North Carolina Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ledbetter Bros. v. North Carolina Department of Transportation, 314 S.E.2d 761, 68 N.C. App. 97, 1984 N.C. App. LEXIS 3208 (N.C. Ct. App. 1984).

Opinion

BECTON, Judge.

This case involves a challenge, by a general contractor and the surety for a subcontractor on a State highway project, to a Superior Court judgment upholding the Department of Transportation’s (DOT’s) assessment of liquidated damages from contract retainages. We affirm the judgment.

I

Ledbetter Brothers (Ledbetter) entered into a general contract with the DOT to perform some $3,300,000 in highway renovation. The work was to be completed by 1 December 1977. Part of it involved moving and replacing signs and guardrails. Ledbetter subcontracted the sign and guardrail work to SMS, Inc. (SMS), and, as required by the general contract, SMS provided a performance bond issued by Hartford Accident and Indemnity Company (Hartford) guaranteeing its performance.

The sign and guardrail work was not completed by the contract date, although the highway was open to the public. SMS completed the guardrail work by 5 January 1978, and it relocated and replaced all required signs by 16 February 1978. Shortly after 16 February 1978, the DOT inspected the new and relocated signs and found many of them to be defective and, accordingly, rejected *99 them. In particular, reflectorized replacement signs were not sufficiently legible at night. At about the same time, SMS defaulted on the work remaining under the subcontract (including replacement and correction of the rejected signs), filed bankruptcy, and abandoned work on the project. Hartford, as surety for SMS, arranged to have the defective work corrected, and the DOT accepted the project on 15 May 1978.

The general contract contained a liquidated damages provision which stipulated damages at a rate of $300.00 per day. Upon final payment to Ledbetter in December 1978, the DOT withheld $49,500.00, representing damages at the contract rate for the 165 days from 1 December 1977 to 15 May 1978. Ledbetter and Hartford sought recovery of the liquidated damages by administrative appeal. The claim was disallowed by the DOT on 20 July 1979. Ledbetter and Hartford then brought the present action in Wake County Superior Court. The trial court, sitting as trier of fact, found the liquidated damages withheld valid and proper, and dismissed the claims, finding that neither party had standing in any event. From this judgment, Ledbetter and Hartford appeal.

II

We first address the standing questions. The trial court found that Ledbetter had assigned its unliquidated claim to Hartford, and that, therefore, Hartford was the real party in interest. It found that such an assignment was void under N.C. Gen. Stat. § 147-62 (1983), the “anti-assignment” statute; that Hartford did not have any subrogation rights against the DOT; and that Hartford, therefore, could not sue the DOT. Apparently because Ledbetter was not the real party in interest, the trial court ruled that Ledbetter’s claim should be dismissed. Ledbetter and Hartford complain that this ruling places them in an untenable “catch-22” situation. We agree only as to Ledbetter, and hold that Ledbetter had standing to sue and hence to bring the present appeal.

A.

The contract entered into between Ledbetter and the DOT included by reference the Standard Specifications for Roads and Structures (1972) (SRSS) issued by the North Carolina State Highway Commission, DOT’s predecessor. These specifications contain the following provision, SSRS § 108-6:

*100 The Contractor shall not sublet, sell, transfer, assign, or otherwise dispose of the contract or any portion thereof, or of his right, title, or interest therein, without written consent of the Engineer. . . . The approval of any subcontract will not release the Contractor of his liability under the contract and bonds, nor will the Subcontractor have any claim against the Commission by reason of the approval of the subcontract.

This Court has recently and clearly interpreted this language to mean that had SMS itself remedied the defective work, it would have had no cause of action against the DOT, nor would Ledbet-ter be entitled to bring such a suit in SMS’ behalf, to recover liquidated damages. Warren Bros. Co. v. Dep’t of Transp., 64 N.C. App. 598, 307 S.E. 2d 836 (1983). Does Hartford, which remedied the defective work in SMS’ behalf as its surety, have a better right?

Hartford argues that having performed in the stead of SMS, it has, by subrogation, a right to proceed against the liquidated damages retained by the DOT. “Subrogation is the substitution of one person in the place of another with reference to a lawful claim or right. ... A party can acquire no better right by subrogation than that of the principal.” Dowdy v. Southern Ry. Co., 237 N.C. 519, 525, 75 S.E. 2d 639, 643 (1953); see also Employers Mut. Cas. Co. v. Griffin, 46 N.C. App. 826, 266 S.E. 2d 18, disc. rev. denied, 301 N.C. 86 (1980). When Hartford completed the work which SMS had contracted to do, it therefore acquired no cause of action against the DOT. Warren Bros. Co. v. Dep’t of Transp. As surety for SMS, the defaulting principal, Hartford could also attempt to recover its payments from the estate of the bankrupt. See generally 74 Am. Jur. 2d Suretyship §§ 168-177 (1974). However, Hartford has shown no authority for its assertion that it is entitled to recover against the DOT itself, and therefore the ruling dismissing its claim was correct.

B.

With respect to the dismissal of Ledbetter’s claim, on the other hand, the trial court committed error. The contract between SMS and Ledbetter contained a “hold harmless” clause. Subsequent to the default of SMS, Ledbetter and Hartford entered into an agreement incorporating a similar provision. The trial court apparently confused these provisions with the separate obligation *101 on the part of SMS and then Hartford to actually complete the work, and ruled that they constituted a void assignment of a claim against the State under G.S. § 147-62 (1983), the “anti-assignment” statute. That statute provides in relevant part:

All transfers and assignments made of any claim upon the State of North Carolina or any of its departments, bureaus or commissions or upon any State institution or of any part or share thereof or interest therein, whether absolute or conditional and whatever may be the consideration therefor and all powers of attorney, orders or other authorities for receiving payment of any such claim or any part or share thereof shall be absolutely null and void unless such claim has been duly audited and allowed and the amount due thereon fixed and a warrant for the payment thereof has been issued; and no warrant shall be issued to any assignee of any claim or any part or share thereof or interest therein

The appellate courts of this State have not construed this language to date. However, certain principles are clear. An “assignment” involves a transfer from one to another, usually in exchange for some consideration. Black’s Law Dictionary 109 (5th ed. 1979); Morton v. Thornton, 259 N.C. 697, 131 S.E. 2d 378 (1963).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Jackson v. Mv Realty Pbc, LLC
2026 NCBC 2 (North Carolina Business Court, 2026)
42 East, LLC v. D.R. Horton, Inc.
722 S.E.2d 1 (Court of Appeals of North Carolina, 2012)
High Rock Lake Partners, LLC v. North Carolina Department of Transportation
693 S.E.2d 361 (Court of Appeals of North Carolina, 2010)
Redding v. Shelton's Harley Davidson, Inc.
534 S.E.2d 656 (Court of Appeals of North Carolina, 2000)
Love v. United States
889 F. Supp. 1548 (E.D. North Carolina, 1994)
Reliance Insurance Co. v. Utah Department of Transportation
858 P.2d 1363 (Utah Supreme Court, 1993)
West Raleigh Group v. Massachusetts Mutual Life Insurance
809 F. Supp. 384 (E.D. North Carolina, 1992)
Bolton Corp. v. T. A. Loving Co.
380 S.E.2d 796 (Court of Appeals of North Carolina, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
314 S.E.2d 761, 68 N.C. App. 97, 1984 N.C. App. LEXIS 3208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ledbetter-bros-v-north-carolina-department-of-transportation-ncctapp-1984.