Queen City Construction Co. v. City of Seattle

99 P.2d 407, 3 Wash. 2d 6
CourtWashington Supreme Court
DecidedFebruary 23, 1940
DocketNo. 27705.
StatusPublished
Cited by16 cases

This text of 99 P.2d 407 (Queen City Construction Co. v. City of Seattle) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Queen City Construction Co. v. City of Seattle, 99 P.2d 407, 3 Wash. 2d 6 (Wash. 1940).

Opinion

Beals, J.

The city of Seattle having called for bids for the construction of the Henderson street trunk sewer, unit No. 9, as authorized by ordinance No. 64831, the plaintiff, Queen City Construction Company, a corporation, submitted its bid, in accordance with the city’s prepared proposals, subdivided into thirty-one distinct items, comprising estimated quantities, for the purpose of comparing bids, only. The specifications called for a sixty-inch monolithic reinforced concrete sewer 6,629 feet in length. Besides resting upon solid earth, the monolithic sewer was to rest upon curved concrete saddles, ten feet apart, each saddle to rest upon three piles. Several bids were received, and, that of plaintiff having been accepted, December 30, 1937, a contract was entered into between plaintiff and the city, calling for the construction of the sewer.

As the concrete which was to form the monolithic sewer was to be poured in place, it was, of course, necessary that the green concrete, while hardening, be kept dry. In order that prospective bidders might *8 have some information concerning the nature of the soil in which the sewer was to be laid, the city dug or drilled eleven test pits, most of which showed that the ground water level was higher than the top of the proposed sewer.

By the city’s proposal, bidders were notified to examine the instructions thoroughly, together with the proposal, the form of contract, and the plans and specifications. In its bid or proposal, the contractor certified that it had personally and carefully examined the plans and specifications, form of contract, and instructions for the construction of the particular sewer bid upon.

Items Nos. 1 and 2 of the proposal cover the following:

“Item No. Unit Price Amount
1 6,629 60" Monolithic Reinforced Lin.Ft. Concrete Sewer, Incl.: 75 — 8" Sewer Inlets, at Twenty-nine Dollars and Thirty-one Cents per Lin.Ft. 29.31 194,295.99
2 15 60" Monolithic Reinforced Lin.Ft. Concrete ' Sewer on Curves at Twenty-nine Dollars and Eighty-one Cents per Lin.Ft. 29.81 447.15”

The contract provided that the work should be done in all respects in accordance with plans on file, and in accordance with the standard plans and specifications of the city of Seattle, in so far as the latter should be applicable. The special specifications contained the following pertinent provisions:

“(6.0) Trenching for Sewer: . . .
“The City Engineer has excavated test pits in the locations shown on the plans and the ground conditions encountered are shown thereon for the contractor’s information, and shall not be construed as a guarantee of similar conditions in excavating the trench.
“The contractor shall provide a method of draining the trenches that will secure a firm bottom foundation for constructing the sewer. If a satisfactory well-point drainage system is used and the drainage water does *9 not carry any appreciable quantity of earth, the contractor will be allowed to drain such water into existing sewers where such facilities are available. . . .
“Payment for trenching shall be included in the price bid for the sewer.”
“(9.6) Placing Concrete:
“Before any concrete is deposited, all water shall be removed from the excavation. The water level shall be kept below the green concrete for a period of at least twenty-four (24) hours after placing.”
“(9.9) Payment:
“Payment for 60" Monolithic Reinforced Concrete Sewer will be made at the price bid per linear foot therefor, which shall be in full for all labor, materials and requirements necessary for the completed sewer, in accordance with the plans and specifications. Measurement will include the sewer under the three-foot manholes.”

Claims for extras were provided for, no such claim to be recognized unless a memorandum of the work be signed by the contractor and approved by the city engineer.

In § 1 of the standard plans and specifications is found the following:

“The special specifications and detailed plans accompanying the proposal are intended to modify, and shall take precedence over the standard specifications and standard plans.”

Section 127 of the standard plans and specifications reads as follows:

“In wet ground a subdrain shall be constructed when so directed by the city engineer, of sewer pipe of the size indicated, laid with open joints and surrounded with gravel. At proper intervals, the subdrain may be connected to the sewer if suitable provision is made to prevent sand and other material from running out and undermining the adjacent masonry. After the completion of the sewer the connections between the subdrain and the sewer shall be filled with concrete *10 or brick work, surfaced and finished, in the same manner as the sewer.
“Payment shall include all excavation, pipe, gravel, and other material, and shall be made at the price bid per linear foot. Measurement shall be made on the slope.”

Nine bids for the work were submitted. The lowest bid, submitted by the plaintiff, was just under $250,000; the highest bid a little over $350,000.

It appears that the plaintiff anticipated that the trench in which the sewer was to be constructed could be kept dry by means of the use of well-points, a well-point consisting of perforated pipes surrounded by screens, these being driven into the ground, the water collects therein, and is pumped out.

The first work which plaintiff performed under the contract was the digging of a sump. In the course of the excavation for the sump, about four feet of clay was found, and as the presence of clay would render the well-point system of drainage unsatisfactory, other methods of drainage were considered. Seven or eight hundred feet of the sewer trench were excavated, and three hundred feet of subdrain were installed, beginning at the sump which had been constructed, in which a pump was installed to draw the water from the sub-drain. The subdrain consisted of unjointed clay pipe placed below the grade of the trench. This method proved satisfactory, and the then city engineer prepared plans for such a drain. The plaintiff agreed to place the same, for a consideration of two dollars per linear foot, to be paid by the city. This agreement was made about April 8, 1938.

In May, 1938, the city engineer who had, up to that time, been in charge of the construction, was succeeded by C. L. Wartelle, who, after inspection and investigation, wrote the plaintiff a letter, which, after identify *11 ing the work, and stating that the former engineer had authorized the construction of the subdrain and agreed to pay therefor, stated that payment under this agreement would be allowed for the work already performed (such payment being made in due time), continuing:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fred Meise v. Michele Jaderlund, Grant County Auditor
413 P.3d 577 (Court of Appeals of Washington, 2018)
Crown Plaza Corp. v. Synapse Software System, Inc.
962 P.2d 824 (Court of Appeals of Washington, 1997)
Ferrer v. Taft Structurals, Inc.
587 P.2d 177 (Court of Appeals of Washington, 1978)
Rosellini v. Banchero
517 P.2d 955 (Washington Supreme Court, 1974)
Northern State Construction Co. v. Robbins
457 P.2d 187 (Washington Supreme Court, 1969)
Gannon v. Emtman
405 P.2d 254 (Washington Supreme Court, 1965)
Warburton v. Tacoma School District No. 10
350 P.2d 161 (Washington Supreme Court, 1960)
United States ex rel. T. M. Page Corp. v. Hensler
125 F. Supp. 887 (S.D. California, 1954)
Westland Construction Co. v. Chris Berg, Inc.
215 P.2d 683 (Washington Supreme Court, 1950)
Robberson Steel Co. v. Harrell
177 F.2d 12 (Tenth Circuit, 1949)
Harris v. Morgensen
196 P.2d 317 (Washington Supreme Court, 1948)
Thayer v. Brady
184 P.2d 50 (Washington Supreme Court, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
99 P.2d 407, 3 Wash. 2d 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/queen-city-construction-co-v-city-of-seattle-wash-1940.