Rosellini v. Banchero

517 P.2d 955, 83 Wash. 2d 268, 1974 Wash. LEXIS 908
CourtWashington Supreme Court
DecidedJanuary 3, 1974
Docket42840
StatusPublished
Cited by36 cases

This text of 517 P.2d 955 (Rosellini v. Banchero) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rosellini v. Banchero, 517 P.2d 955, 83 Wash. 2d 268, 1974 Wash. LEXIS 908 (Wash. 1974).

Opinion

Brachtenbach, J.

Plaintiff, a contractor, and defendant, a property owner, entered into an oral contract in June 1969, for the construction of a building for defendant. The work was to be done on a time and materials basis, but with a maximum cost of $56,146, plus sales tax, plus extras as ordered by defendant. A unique feature was that any reduction in cost below that estimated in plaintiff’s bid, such as lower subcontract costs, would accrue to defendant’s benefit. In short, all savings benefited defendant, while plaintiff ran the risk of costs exceeding the ceiling.

Construction began and plaintiff submitted invoices for labor, materials and subcontractors which totaled $28,412.83 by September 9, 1969. Defendant promptly paid these without question. On October 15, 1969, plaintiff submitted an invoice of $16,719.65. At this point the building was about 90 percent completed. The defendant contended that at that point he was unhappy with the whole job, that he was concerned about possible liens, that plaintiff’s workers “just weren’t doing the work” and “the thing wasn’t just being run right and something may happen.” On October 17, 1969, the parties signed a written agreement lowering the maximum cost to $52,000 plus sales tax.

The building was completed less than three weeks after the October 17th contract was signed. Plaintiff’s actual cost was $64,155.79. Plaintiff, after disputes with defendant as to the balance due, recorded a lien and began a foreclosure suit.

The trial court held that the October 17th contract was void for want of consideration and because it was signed under duress. Therefore, the original ceiling was control *270 ling. The court found payment of $2,265.91 was due for extras. The original maximum, plus extras, plus sales tax totaled $61,040.45. Defendant had paid $51,437.42 so the court awarded the plaintiff a judgment of $9,603.03, plus $1,500 attorney’s fees under the lien foreclosure statute, plus interest from the due date of the last invoice and plaintiff’s costs.

The Court of Appeals reversed on the grounds that there was consideration and that there was no duress or business compulsion. It also reversed the award of attorney’s fees and directed that interest should run from the date of judgment. Rosellini v. Banchero, 8 Wn. App. 383, 506 P.2d 866 (1973).

In finding that there was consideration for the October 17th contract, the Court of Appeals relied on the principle that the settlement of a bona fide dispute or a doubtful claim, if made in good faith, is sufficient consideration for the compromise. Rogich v. Dressel, 45 Wn.2d 829, 843, 278 P.2d 367 (1954). The trial court made no finding as to the existence of a bona fide dispute or a doubtful claim. The court did find that defendant’s dissatisfaction with job progress and the amount paid to that time caused defendant to initiate the October 17th contract. There is substantial evidence that defendant had no dispute with specific items of the plaintiff’s progress billings, but rather a general dissatisfaction that “the thing wasn’t just being run right.” In fact after plaintiff signed the October 17th contract, defendant immediately paid the October 15th voucher. It is apparent that there was no bona fide dispute or doubtful claim; indeed that is implicit in the court’s finding of a lack of consideration.

The part that consideration plays in determining the validity of so-called modification contracts is in a state of confusion in Washington. Professor Shattuck characterizes our cases on this point as “a tangle of diverse language and results.” Shattuck, Contracts in Washington 1937-1957, 34 Wash. L. Rev. 24, 57 (1959). As will be demonstrated and as outlined by Professor Shattuck, this court has adopted *271 diametrically opposed principles in this area of contract law, with conflicting results which cannot be reconciled.

In one line of cases we start with Tingley v. Fairhaven Land Co., 9 Wash. 34, 39, 36 P. 1098 (1894), where there was legal consideration flowing from the agreement to change the delivery point of logs and reduce the price, yet the court added that the modification was enforceable “without the actual payment of any consideration.” This error was expanded in Long v. Pierce County, 22 Wash. 330, 348, 61 P. 142 (1900), where the court said:

But no express or independent consideration was necessary. “The contract, when modified by the subsequent oral agreement, is substituted for the contract as originally made, and the original consideration attaches to and supports the modified contract.”

(Citations omitted.) Again, the result was correct, but for the wrong reason; the case actually involved waiver of an express condition which does not require a new contract.

This erroneous reasoning came to full bloom in Stofferan v. Depew, 79 Wash. 170, 139 P. 1084 (1914), where Long v. Pierce County, supra, was relied upon to enforce a second agreement expanding the obligor’s duty without new consideration. Inman v. W.E. Roche Fruit Co., 162 Wash. 235, 298 P. 342 (1931), reached an equally faulty result where the court upheld a modification relieving one party of a contractual obligation and imposing the same duty on the other party without any change in compensation or the furnishing of any other consideration. As recently as Meyer v. Strom, 37 Wn.2d 818, 226 P.2d 218 (1951), the court repeated that the original consideration is sufficient to support a subsequent modification.

At the same time a totally divergent line of authority developed. In Wright v. Tacoma, 87 Wash. 334, 348, 151 P. 837 (1915), the court said: *272 As pointed out by Professor Shattuck at page 60 of the cited law review article, the words “which does not form any part of the original contract” are unfortunate, unnecessary and erroneous.

*271 There is no doubt of the rule that a subsequent agreement, which does not form any part of the original contract, is of no force or validity unless supported by a new consideration.

*272 Tacoma & E. Lumber Co. v. Field & Co., 100 Wash. 79, 170 P. 360 (1918), and Stauffer v. Northwestern Mut. Life Ins. Co., 184 Wash. 431, 51 P.2d 390 (1935), spoke of the necessity of consideration for a modification agreement if the contract had been executed on one side.

Queen City Constr. Co. v. Seattle, 3 Wn.2d 6, 99 P.2d 407 (1940), and Westland Constr. Co. v. Chris Berg, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tien Thach, M.d. v. Matrix Anesthesia, P.s.
Court of Appeals of Washington, 2019
Work-Force Solutions, Inc. v. Antoine Creek Farms, LLC
Court of Appeals of Washington, 2018
Baker v. City of Seatac
994 F. Supp. 2d 1148 (W.D. Washington, 2014)
Lokan & Associates, Inc. v. American Beef Processing, LLC
311 P.3d 1285 (Court of Appeals of Washington, 2013)
Lokan & Associates, Inc. v. American Beef Processing
Court of Appeals of Washington, 2013
Duncan v. Alaska USA Federal Credit Union, Inc.
148 Wash. App. 52 (Court of Appeals of Washington, 2008)
Labriola v. Pollard Group, Inc.
152 Wash. 2d 828 (Washington Supreme Court, 2004)
Vehicle/Vessel, L.L.C. v. Whitman County
122 Wash. App. 770 (Court of Appeals of Washington, 2004)
VEHICLE/VESSEL LLC, DRA v. Whitman County
95 P.3d 394 (Court of Appeals of Washington, 2004)
Ago
Washington Attorney General Reports, 1998
Pacific Erectors, Inc. v. Gall Landau Young Construction Co.
813 P.2d 1243 (Court of Appeals of Washington, 1991)
Hibbert v. Centennial Villas, Inc.
786 P.2d 309 (Court of Appeals of Washington, 1990)
CH2M Hill, Inc. v. Greg Bogart & Co.
735 P.2d 1330 (Court of Appeals of Washington, 1987)
Barnett v. Buchan Baking Co.
724 P.2d 1077 (Court of Appeals of Washington, 1986)
Boardman v. Dorsett
685 P.2d 615 (Court of Appeals of Washington, 1984)
Thompson v. St. Regis Paper Company
685 P.2d 1081 (Washington Supreme Court, 1984)
Ebling v. Gove's Cove, Inc.
663 P.2d 132 (Court of Appeals of Washington, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
517 P.2d 955, 83 Wash. 2d 268, 1974 Wash. LEXIS 908, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rosellini-v-banchero-wash-1974.