Dady v. City of New York

65 Misc. 382, 121 N.Y.S. 860
CourtNew York Supreme Court
DecidedDecember 15, 1909
StatusPublished
Cited by3 cases

This text of 65 Misc. 382 (Dady v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dady v. City of New York, 65 Misc. 382, 121 N.Y.S. 860 (N.Y. Super. Ct. 1909).

Opinion

Blackmar, J.

On the 16th day of August, 1905, the plaintiff and defendant made a contract whereby the plaintiff agreed to erect a pumping plant and infiltration gallery at Massapequa, to he paid for according to an agreed schedule of prices for the items of work done. The estimated amount of the contract was $327,800. On the 14th day of November, 1905, the same parties made a supplemental contract for the installation of manholes and pumping stations at an estimated cost of $7,160. During the progress of the [384]*384work the plaintiff, pursuant to oral orders of the chief engineer of the department of water, gas and electricity, performed certain other work in connecting wells driven by other parties with the pumping station erected by the plaintiff, in testing the same and in constructing a coal box to be used in measuring coal, etc. For the purpose of description and not of characterization, the work so performed under the oral orders of the engineer will be called “ extra work.” All the work required by the main and the supplemental contracts has been performed. During the progress of the work the engineer in charge included the items of extra work in the monthly estimates showing the progress of the work, and partial payments were made based upon such estimates. In the final estimate the items of extra work were stricken out. The plaintiff was paid the amount called for by the original and the supplemental contracts, but has never been paid for the extra work; and this action is brought to recover the value of the same. It is stipulated that such extra work was performed and materials furnished under the orders of the engineer and that the reasonable value thereof is $2,298.77.

As the city has received the benefit of the work done by the plaintiff, principles of justice would seem to require that he should be paid therefor. The Legislature evidently contemplated that cases may arise where claims are illegal or invalid because created in contravention of statutory requirements and yet that justice, propriety and the best interests of the city may be subserved by their payment; and it has therefore conferred upon the board of estimate and apportionment power to adjust and pay such claims. Laws of 1907, chap. 601. This authority is not conferred upon the courts, whose power in an action at law is limited to determining whether the claim is valid under the statutes regulating the manner in which legal obligations of the city may be created, for a municipal corporation can act only in the manner prescribed by the law of its creation.

Section 419 of the charter of Greater Hew York provides that, whenever any work is necessary to complete or perfect a particular job or any supply is needful for any particular [385]*385purpose and the several parts of such work or supply shall, together, involve an expenditure of more than $1,000, the same shall be by contract unless otherwise ordered by a vote of three-fourths of the board of aldermen, and that such contracts shall be entered into by the appropriate borough president or heads of departments and founded upon competitive bidding. It also provides that in any contract there may be inserted a provision that additional work may be done or supplies furnished for. the purpose of completing such contract, at an expense not exceeding five per centum of the amount of the contract, if such additional work or supply shall be ordered by the head of department. It further provides that no expenditure for work or supplies involving an amount for which no contract is required shall be made, except the necessity therefor be certified to by the head of the appropriate department, and the expenditure has been duly authorized and appropriated. The charter, therefore, provides four ways in which the city can be obligated to pay for contract work: (1), by contract authorized by the vote of three-fourths of the members of the board of aldermen; (2), where the work and'supplies involve an expenditure of more than $1,000, by contract founded upon competitive bidding; (3), by order of the appropriate head of the department for additional work for the purpose of completing any contract, at an expense not exceeding five per centum of the amount of such contract; and (4), by contract without competition, where the amount is less than $1,000 and the necessity therefor is certified to by the appropriate head of department and the expenditure has been duly authorized and appropriated.

The question is whether liability for the work in question has been incurred pursuant to the authority of any of these provisions of the charter. If the work performed is for the purpose of completing a contract already awarded and the expense thereof does not exceed five per centum of the amount of such contract, liability therefor may be created by the order of the said commissioner; and I believe this may be so, even if the amount of such extra work exceeds the sum of $1,000, provided it be not more than five per [386]*386centum of the amount of such original contract. It is, therefore, important to decide whether or not the work in question was done for the purpose of completing the contract of August sixteenth. This contract is described in the instrument itself as a contract “ for remodelling and extending the Massapequa pumping station near Massapequa, Long .Island, including the pumping plant, pump well and infiltration gallery system, together with the necessary appurtenances.” The first sentence of the specifications is as follows : The work comprised in this contract consists of furnishing a complete pumping plant and infiltration galleries.” It appears that near the pumping station erected by the plaintiff there were three wells driven by other parties called the Elliott and Marren wells. The extra work ordered by the engineer and performed by the contractor was, first, connecting the Elliott and Marren wells with the pumping station built by the plaintiff and testing the same, and second, building a box for measuring coal, laying a pipe under the road and making flume connections, etc. It is true that the ultimate purpose of constructing the pumping station and infiltration galleries and of the extra work in connecting the Elliott and Marren wells, testing them, and building the box for measuring coal was the same, namely, to supply the city of Brooklyn with water. But the plaintiff made no contract to supply the city with water. His contract was limited to the completion of certain physical structures. The test in determining whether the liability of the city can be created by the order of the commissioner is whether the work in question was “ additional work performed for the purpose of completing such contract.” I' find that the work so done was not furnished for the completion of the contract and had no relation to the original contract, except that the ultimate purpose of both was supplying the city with water. I have, therefore, reached the conclusion that, although the total cost of this work together with the supplemental contract referred to did not amount to five per centum of the original contract, the liability of the city could not he created by the mere order of the commissioner. The contract contains other requirements condi-' [387]*387tional to the ability of the city, namely, that the work shall he preceded by a written contract in which the prices shall be fixed in advance of performance and that claims therefor shall be made by the contractor upon the engineer on or before the fifteenth of the month following the performance of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zacharkow v. Berry
237 A.D. 362 (Appellate Division of the Supreme Court of New York, 1933)
Dady v. City of New York
133 N.Y.S. 1117 (Appellate Division of the Supreme Court of New York, 1912)
People ex rel. Dady v. Prendergast
144 A.D. 308 (Appellate Division of the Supreme Court of New York, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
65 Misc. 382, 121 N.Y.S. 860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dady-v-city-of-new-york-nysupct-1909.