City of Gillette v. Hladky Const., Inc.

2008 WY 134, 196 P.3d 184, 2008 Wyo. LEXIS 139, 2008 WL 4889653
CourtWyoming Supreme Court
DecidedNovember 14, 2008
DocketS-07-0291 to S-07-0293
StatusPublished
Cited by39 cases

This text of 2008 WY 134 (City of Gillette v. Hladky Const., Inc.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Gillette v. Hladky Const., Inc., 2008 WY 134, 196 P.3d 184, 2008 Wyo. LEXIS 139, 2008 WL 4889653 (Wyo. 2008).

Opinion

196 P.3d 184 (2008)
2008 WY 134

CITY OF GILLETTE, Wyoming, Appellant (Defendant),
v.
HLADKY CONSTRUCTION, INC., Appellee (Plaintiff).

Nos. S-07-0291 to S-07-0293.

Supreme Court of Wyoming.

November 14, 2008.

*189 Representing Appellant: Raymond B. Hunkins and Amanda Hunkins Newton of Jones, Vines & Hunkins, Wheatland, Wyoming.

Representing Appellee: Patrick Murphy of Williams, Porter, Day & Neville, P.C., Casper, Wyoming; Tad T. Daly of Daly Law Associates, P.C., Gillette, Wyoming.

*190 Before VOIGT, C.J., and GOLDEN, HILL, KITE, and BURKE, JJ.

KITE, Justice.

[ś 1] A jury awarded Hladky Construction, Inc. (HCI) damages in the amount of $1,125,436.77 against the City of Gillette (City) for breach of the implied covenant of good faith and fair dealing. The district court entered judgment on the verdict and, subsequently, awarded HCI attorney fees and costs pursuant to the parties' contract.

[ś 2] In its first appeal, the City claims HCI did not comply with the Wyoming Governmental Claims Act in presenting its notice of claim and, therefore, the district court lacked subject matter jurisdiction to consider its claims. Alternatively, the City claims the district court erred in several respects in not granting its motions for judgment as a matter of law and in failing to adequately instruct the jury. In its second and third appeals, the City claims the district court erred in awarding attorney fees. We find no reversible error and affirm.

STATEMENT OF THE ISSUES

[ś 3] In its first appeal, the City presents the following issues:

A. Where it is established in a breach of construction contract suit that the City of Gillette, the owner, neither did anything forbidden by the contract nor failed to do something required by the contract, may Hladky Construction, Inc., the contractor, still recover for breach of an implied covenant of that contact?
B. Where the City of Gillette did not breach its contract with Hladky Construction, Inc., could delay and breach of contract, "total cost" damages be awarded for breach of an implied covenant, where the contract provided for an exclusive remedy of time extension and where Hladky Construction, Inc. failed to prove the predicate for using the total cost method.
C. Where Hladky Construction, Inc. asked for and received a change order, without reservation of rights, and accepted $71,133.00 in extra compensation for changing from its problematic supplier, is Hladky Construction, Inc. allowed to accept the change order, take the money, change suppliers and then later bring suit and be awarded additional damages allegedly caused by choosing the wrong supplier?
D. Must the trial court enforce contract procedures for asserting a claim which are conditions of bringing suit, and if it fails to do so must it at least instruct on them and allow relevant evidence bearing on the conditions to be admitted?
E. Did the trial court (and does this court) have subject matter jurisdiction?

[ś 4] HCI rephrases the issues as follows:

A. Has Wyoming already held that a party can breach its implied covenant of good faith and fair dealing without breaching the express terms of its contract?
B. Did the trial evidence support the jury's verdict that the City of Gillette breached its implied covenant of good faith and fair dealing?
C. Where the contract does not contain a "no damages for delay" clause, is the contractor entitled to recover delay damages?
D. Did the district court correctly instruct the jury on proper damage calculation methods when multiple calculation methods were presented at trial?
E. Did the trial evidence support the jury's verdict that HCI complied with all the contractual conditions precedent to pursuing its claim for delay damages?
F. Did the trial court correctly conclude that the City of Gillette failed to prove that change order No. 2 was an accord and satisfaction, or waiver, of HCI's claim for delay damages?
G. Did the district court properly exercise its discretion when it precluded the City from presenting evidence of HCI's conduct on two prior and unrelated claims?
H. Did HCI's governmental claim contain sufficient information to vest the district court with subject matter jurisdiction?

[ś 5] In its second and third appeals, the City presents the following issues:

A. Where a contractual provision allows for reasonable attorneys' fees, and *191 costs of suit to be awarded to the prevailing party in a suit to enforce rights under the Contract Documents, does a finding that the party against whom suit was filed was not in breach of the contract, preclude the award of those attorneys' fees to the plaintiff?
B. Where Hladky Construction, Inc. disclaimed the Contract's provisions at the trial of this matter, can it simultaneously seek the benefits of the Contract's fee-shifting provision allowing reasonable attorneys' fees, and costs of suit?
C. Whether Hladky Construction, Inc. brought two claims against the City of Gillette, failing on one claim, and succeeding on the other claim, is it required, as a matter of law, to segregate its fees between its successful and unsuccessful claims, and does its failure to segregate its fees preclude the award?
D. Whether the District Court abused its discretion by: (1) allowing Hladky Construction, Inc. to increase the hourly rate for its attorney once the Jury's decision became known; (2) awarding substantial attorneys' fees to Hladky Construction, Inc. for dispositive motions that were untimely, and not heard by the Court; and (3) awarding Hladky Construction, Inc. its electronic research charges?
E. Did the District Court (and does this Court) have subject matter jurisdiction?

HCI re-states substantially the same issues.

FACTS

[ś 6] In 2000, the City embarked on a project to remodel and expand City Hall. The City hired Schutz Foss Architects, P.C., (Schutz Foss) as the project architect. Schutz Foss assigned its employee, Kyle Gillette, to act as project manager on site during construction. HCI, a Gillette construction company owned and operated by Mike and Judy Hladky, was one of four companies that submitted a bid for the project.

[ś 7] The project specifications required precast concrete exterior panels to be installed on the new part of the building to match the panels on the existing structure. The specifications provided: "[T]he precast concrete manufacturing plant shall be certified by the Precast/Prestressed Concrete Institute, Plant Certification Program, prior to the start of production." Bill Oakey, a structural engineer retained by Schutz Foss for the City Hall project, added the italicized language to what was otherwise a standard American Institute of Architects (AIA) provision after learning that only one certified precast concrete manufacturing plant, Gage Brothers Concrete Productions, Inc. (Gage Brothers), planned to bid on the project. In order to promote competitive bidding and keep Gage Brothers from artificially inflating its bid, Mr. Oakey added the italicized language so that other uncertified manufacturing plants could bid and be considered for the project and become certified later, before beginning production of the precast panels.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelly Wilcox v. Security State Bank
2023 WY 2 (Wyoming Supreme Court, 2023)
Janet G. Peterson v. Meritain Health, Inc.
2022 WY 54 (Wyoming Supreme Court, 2022)
Woodie v. Berkshire Hathaway
Tenth Circuit, 2020
Kira Kay Olson v. Ronald Russell Schriner
2020 WY 36 (Wyoming Supreme Court, 2020)
Schell v. Scallon
433 P.3d 879 (Wyoming Supreme Court, 2019)
Essex Holding, LLC v. Basic Props., Inc.
427 P.3d 708 (Wyoming Supreme Court, 2018)
Bear Peak Resources, LLC v. Peak Powder River Resources, LLC
2017 WY 124 (Wyoming Supreme Court, 2017)
Denbury Onshore, LLC v. Christensen
101 F. Supp. 3d 1147 (D. Wyoming, 2015)
Ultra Resources, Inc., a Wyoming Corporation
2015 WY 40 (Wyoming Supreme Court, 2015)
Shannan Krietemeier Wright
2015 WY 37 (Wyoming Supreme Court, 2015)
Northwest, Inc. v. Ginsberg
134 S. Ct. 1422 (Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2008 WY 134, 196 P.3d 184, 2008 Wyo. LEXIS 139, 2008 WL 4889653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-gillette-v-hladky-const-inc-wyo-2008.