Hogan & Associates Builders, Llc, a Wyoming Limited Liability Company v. Eiden Construction, Llc, a Wyoming Limited Liability Company and Amco Insurance Company, an Iowa Corporation

2024 WY 138, 561 P.3d 304
CourtWyoming Supreme Court
DecidedDecember 20, 2024
DocketS-24-0004
StatusPublished
Cited by7 cases

This text of 2024 WY 138 (Hogan & Associates Builders, Llc, a Wyoming Limited Liability Company v. Eiden Construction, Llc, a Wyoming Limited Liability Company and Amco Insurance Company, an Iowa Corporation) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hogan & Associates Builders, Llc, a Wyoming Limited Liability Company v. Eiden Construction, Llc, a Wyoming Limited Liability Company and Amco Insurance Company, an Iowa Corporation, 2024 WY 138, 561 P.3d 304 (Wyo. 2024).

Opinion

IN THE SUPREME COURT, STATE OF WYOMING

2024 WY 138

OCTOBER TERM, A.D. 2024

December 20, 2024

EIDEN CONSTRUCTION, LLC, a Wyoming limited liability company,

Appellant (Defendant/Counter-Plaintiff),

v.

HOGAN & ASSOCIATES BUILDERS, LLC, a Wyoming limited liability company,

Appellee (Plaintiff/Counter-Defendant).

HOGAN & ASSOCIATES BUILDERS, S-24-0003, S-24-0004 LLC, a Wyoming limited liability company,

Appellant (Plaintiff/Counter-Defendant),

EIDEN CONSTRUCTION, LLC, a Wyoming limited liability company and AMCO INSURANCE COMPANY, an Iowa corporation,

Appellees (Defendants/Counter-Plaintiffs).

Appeal from the District Court of Uinta County The Honorable Richard L. Lavery, Judge Representing Appellant: Nathan V. Graham, Bradley Arant Boult Cummings LLP, Houston, Texas.

Representing Appellee: Eric P. Lee and Matthew J. Pugh, Hoggan Lee Hutchinson, Park City, Utah. Argument by Mr. Lee.

Before FOX, C.J., and BOOMGAARDEN, GRAY, FENN, and JAROSH, JJ.

NOTICE: This opinion is subject to formal revision before publication in Pacific Reporter Third. Readers are requested to notify the Clerk of the Supreme Court, Supreme Court Building, Cheyenne, Wyoming 82002, of typographical or other formal errors so correction may be made before final publication in the permanent volume. JAROSH, Justice.

[¶1] Eiden Construction, LLC (Eiden) entered into an earthwork and utilities subcontract (Subcontract) with general contractor Hogan & Associates Builders, LLC (Hogan) on the Farson-Eden K-12 school construction project (Project). Hogan sued Eiden and its bonding company, AMCO Insurance Company (AMCO), for breach of contract to recover costs Hogan paid other contractors to complete Eiden’s scope of work under the Subcontract, including, among other things, draining existing sewage lagoons and completing a fire pond. Eiden defended by arguing it was not responsible for draining the lagoons and Hogan did not comply with the notice and opportunity to cure provision of the Subcontract. Eiden also filed a counterclaim asserting Hogan owed it money for work it performed on the Project. AMCO asserted it was not responsible under the performance bond because Eiden did not breach the Subcontract and Hogan did not provide AMCO proper notice of its claims.

[¶2] After a bench trial, the district court found for Hogan on its claim against Eiden for not draining the sewage lagoons but not on its claims regarding the fire pond or other work within Eiden’s scope under the Subcontract. The court also ruled AMCO was not liable under the bond because Hogan did not prove most of its claims against Eiden and did not provide notice to AMCO of Eiden’s failure to drain the sewage lagoons.

[¶3] Eiden and Hogan appealed. In general, Eiden claims the district court erred by finding it in breach of contract for failing to drain the sewage lagoons, and Hogan claims the district court erred by concluding it was not entitled to recover damages from Eiden and AMCO on its other claims. Hogan also challenges the district court’s calculation of prejudgment interest.

[¶4] We affirm.

ISSUES

[¶5] We restate the issues dispositive to Eiden’s appeal in S-24-0003 as:

1. Did the district court properly rule Eiden breached the Subcontract when it refused to drain the sewage lagoons by pumping the effluent and hauling it offsite for disposal?

2. Did the district court correctly determine Hogan was entitled to recover costs billed to the Utah office of another Hogan entity?1

1 Eiden also raises an issue about the district court’s decision on attorney fees. It asserts that, if we decide in Eiden’s favor on its other issues, the final judgment “will be a net balance in Eiden’s favor,” which will make it the prevailing party. In that case, Eiden requests that we remand the case to the district court for 1 We restate the issues dispositive of Hogan’s appeal in S-24-0004 as:

1. Did the district court err by concluding Hogan was not entitled to recover its costs to complete the fire pond and other work included in Eiden’s scope of work in the Subcontract because a) Hogan did not prove Eiden breached its responsibilities under the notice of default and cure provision of the Subcontract; and b) Hogan did not establish it was entitled to recover for common law breach of contract?2

2. Did the district court err by concluding Hogan was not entitled to recover its costs for purchasing and installing the fire pond liner?

3. Did the district court err by concluding AMCO was not liable under the performance bond for Eiden’s failure to complete the work in the Subcontract?

4. Did the district court correctly calculate prejudgment interest on Hogan’s award after offsetting the amount it owed Eiden?

FACTS

The Project and Contracts

[¶6] In January 2016, Sweetwater County School District No. 1 (School District) entered into a $19.6 million general contract with Hogan to construct a new Farson-Eden K-12 school and teacher residences. The new buildings were to be built adjacent to an existing school and teacher residences. The date for substantial completion of the entire Project was August 31, 2017. Substantial completion was defined in the general contract as “[t]he time at which the [w]ork [on the Project] has progressed to the point . . . the [w]ork is sufficiently complete [so that it] can be utilized for the purposes for which it is intended.” Under the terms of the general contract, the parties intended for the Project to be finished so the School District could start school in the new building in August 2017.

[¶7] Eiden was an earthwork company managed by Galen and Dustin Eiden. As general contractor on the Project, Hogan accepted Eiden’s bid to perform the earth and utilities work on the Project. On January 21, 2016, Hogan and Eiden entered into a $1.17 million Subcontract which defined the scope of Eiden’s work and incorporated other documents

recalculation of the attorney fees award. Because we affirm the district court in all respects, we will not address this issue. 2 Hogan also raises an issue as to whether the district court erred by concluding Hogan did not prove its damages for the cost to complete the fire pond and other work in Eiden’s scope of work with reasonable certainty. Because we affirm the district court’s conclusion that Hogan was not entitled to those damages, we will not address this issue.

2 associated with the Project, including, as relevant here, the general contract, Project specifications, and architectural drawings. Section 4.2 of the Subcontract included a change order process Hogan could use during construction to alter Eiden’s contractual responsibilities. Through the change order process, Eiden’s total work under the Subcontract increased to $1.2 million. AMCO issued a performance bond guaranteeing Eiden’s work.

[¶8] Although the extent of Eiden’s scope of work under the Subcontract is disputed in this case, Eiden was generally tasked with performing site earthwork, completing a new septic system, reclaiming the existing sewage system, and constructing a fire pond. The existing sewage system included two “wet” sewage lagoons and one “dry” percolation lagoon.3 When Eiden finished construction of the new septic system and it passed inspection by the Project engineer and the Wyoming Department of Environmental Quality (DEQ), sewage from the school was to be rerouted from the sewage lagoons to the new septic system. After the new septic system was in use and accepting all waste from the school and teacher residences, the existing sewage lagoons had to be drained. DEQ issued a permit to the School District prescribing the process for draining the effluent (liquid waste) out of the “wet” lagoons into the percolation lagoon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jeremy D. Jones v. Bethany D. Young
2025 WY 130 (Wyoming Supreme Court, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2024 WY 138, 561 P.3d 304, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hogan-associates-builders-llc-a-wyoming-limited-liability-company-v-wyo-2024.