Smith v. City of Tahlequah

1926 OK 396, 245 P. 994, 117 Okla. 204, 1926 Okla. LEXIS 773
CourtSupreme Court of Oklahoma
DecidedApril 20, 1926
Docket16209
StatusPublished
Cited by7 cases

This text of 1926 OK 396 (Smith v. City of Tahlequah) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. City of Tahlequah, 1926 OK 396, 245 P. 994, 117 Okla. 204, 1926 Okla. LEXIS 773 (Okla. 1926).

Opinion

Opinion by

JONES, C.

This action was instituted in the district court of Cherokee county, Okla., by plaintiffs in error, as plaintiffs, against the defendant in error, as defendant, to recover the sum of $2.200, as balance due jtlaintiffs under a certain contract entered into by the plaintiffs and the defendant. The defendant files its answer, and as a defense avers that plaintiffs are indebted to defendant'in the sum of $2.200, the amount sued for by plaintiffs, by reason of a breach of contract sued on, which pro--vides that in the event plaintiffs did not fulfill the contract within the time specified, plain! iffs should pay to the de. endant the amount of $25 per day, for each day the completion of the work provided for under the terms of the contract was delayed, as liquidated damages. Defendant farther avers that there was a delay of 88 days in the completion of the work, incumbent upon plaintiffs under (he terms of the contract, and further avers that the defendant has overpaid plaintiffs in the sum of $1.250. for which amount it prays judgment; to which answer of the defendant, plaintiffs file a reply in the nature of a general denial. Upon the issue thus joined the cause was submitted to the court and jury, and at the-conclusion of plaintiffs’ evidence, the defendant interposed a demurrer to> the evidence of plaintiffs, and motion for instructed, verdict. The demurrer 'was sustained by the court, and the jury directed to return a verdict in favor of the defendant, and judgment *205 was rendered by the court iu accordance with the verdict of the j ary, from which judgment the plaintiffs prosecute this appeal, and assign numerous specifications o_ error.

This action grows out oí a contract entered in.o by Smith & Whitney, plaintiffs, with the city of Tahlequah, defendant, whereby plaintiffs agreed to install an electric light plant for the defendant, city of Tahlequah, and this controversy is based upon, the following provision contained in the contract:

“'The work shall be commenced within five ■days after the approval of bonds .by Attorney General, and shall be completed within seven months (plus the time necessary to transport engines and generators from the date thereof) and for each and every day the work remains uncompleted a.ter the expiration of time agreed upon for completion, the contractor shall pay to the purchaser .$20 as liquidated damages.”

AVe are inclined, however, to the opinion that the trial court committed error in sustaining the demurrer and motion for a directed verdict, and was in error in excluding the evidence offered by the plaintiffs, tending to excuse or justify the delay in the completion of the work.

The facts, as disclosed by the record, show that the defendant, the city of Tahlequah. entered into three different contracts with different parties to construct different parts of ¡he electric light plant. The construction of the building in which the plant was installed seems to have been let to one Burns. The plaintiffs made an offer of proof tending to show that there was a delay o: 30 days in installing the boiler, engines, and generators. which was incumbent nptm plaintiffs, caused by failure of the contractor, Burns, to complete the building within a reasonable time, and, according to the contract, the •evidence admitted by the court shows that there was a delay of 19 days, due to the fact that the engineer of the defendant', in charge of and supervising the work, requested plaintiffs to do certain additional work in connection with the installation of the machinery, which plaintiffs were not required to do under the terms of the contract. This fact is admitted by defendant as is disclosed by the following paragraph found in its brief:

“AAToo.'k was to begin March 16. 1920. seven months from that day is October 16. 1920, 23 days added as the time found to be the longest time required to transport any portion of the engines and generators, which brings it to November 8. 1920. From November 8th. to March 1, 1921, the date the plant was accepted, is 106 days; deduct from the 106 days the 19 days that the plaintiffs were allowed by reason of work that engineers required" them to do, that it after-wards developed should have been done by someone else, and we have left 87 days, the number of days deducted.”

Under this proof, which is admitted, and the proof tendered by plaintiffs upon the trial of the case, which we think should have been admitted, it is obvious that at least a substantial and material part of the-delay was caused by the defendant.

The trial court seems to have based its judgment on the following provision contained in the contract, providing for the giving of notice by plaintiffs to defendant of any delays occurring, as is disclosed by the following finding of the court in discussing the' following provision:

“That in order to avail themselves of any deduction of time by reason of delay that-they should have given the engineers notice in writing within 24 hours after it occurred.”

AAre cannot agree with the conclusion reached and judgment rendered by the trial court. The court was in error in excluding evidence offered by plaintiffs, tending to show that the de endant at least contributed to the delay, by reason of the contractor Burns' failure to completo the building in due time, and hence in error'in sustaining the demurrer to plaintiffs’ evidence in the face of the tender made, and evidence admitted disclosing that the defendant had contributed to the delay for the period of at least 19 days according to the evidence and its own admission.

In 8 K. O. L. page 578, section 126, the following rule is announced:

“The plaintiff cannot recover liquidated' damages for a breach for which he himself is responsible, or to which he has contributed. and as a rule there can be no apportionment of liquidated damages where both parties are at lault. Hence, if the parties are mutually responsible for the delays because of which the date 'fixed by the contract for completion is passed, the obligation for liquidated damages is annulled, and in the absence of some provision under which another, date can be substituted, it cannot be revived. And so it has b'eefi held that a provision in a contract, to the effect that deviations- may be made at the instance of the owner without annulling or invalidating the contract, does not operate to renew a right to liquidated damages for delay in completing the work after the provision therefor has been abrogated by delays to which the owner materially contributed.”

This seems to be a just and' equitable doctrine, and has been followed by the Supreme- *206 Court of New York and other states. In Mosier Safe Co. v. Maiden Lane Safe Deposit Co., 199 N. Y. 479, 93 N. E. 81, 37 L. R. A. 363, syllabus paragraph 3, the Supreme Court of New York held:

“The right of the owner of a building to liquidated damages for failure to complete a vault within a specified time is abrogated if he is responsible for a substantial part of the delay, and he cannot therefore recover such damages for delay beyond the time for which he is responsible.”

Under this rule the defendant would not be entitled to recover liquidated damages in this case, having contributed to the delay, therefore.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hutton Contracting Co. v. City of Coffeyville
487 F.3d 772 (Tenth Circuit, 2007)
San Ore-Gardner v. Missouri Pacific Railroad
496 F. Supp. 1337 (E.D. Arkansas, 1980)
Flour Mills of America, Inc. v. American Steel Building Co.
449 P.2d 861 (Supreme Court of Oklahoma, 1969)
Goodrum v. State
158 S.W.2d 81 (Court of Appeals of Texas, 1942)
Gillioz v. State Highway Commission
153 S.W.2d 18 (Supreme Court of Missouri, 1941)
Smith v. City of Tahlequah
1930 OK 425 (Supreme Court of Oklahoma, 1930)
Bauman v. Peters
231 N.W. 613 (Supreme Court of Minnesota, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
1926 OK 396, 245 P. 994, 117 Okla. 204, 1926 Okla. LEXIS 773, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-city-of-tahlequah-okla-1926.