Smith v. City of Tahlequah

1930 OK 425, 291 P. 981, 145 Okla. 103, 1930 Okla. LEXIS 172
CourtSupreme Court of Oklahoma
DecidedSeptember 23, 1930
Docket19431
StatusPublished
Cited by2 cases

This text of 1930 OK 425 (Smith v. City of Tahlequah) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. City of Tahlequah, 1930 OK 425, 291 P. 981, 145 Okla. 103, 1930 Okla. LEXIS 172 (Okla. 1930).

Opinion

LEACH. C.

This action was commenced in the district court of Cherokee county by the plaintiffs in error against the defendant in error, as defendant, to recover the sum of $2.200 alleged to be due plaintiffs as a balance under a contract between the parties relating to the construction of a certain portion of an electric light plant.

It was alleged in part in plaintiffs’ amended petition that at an election in the defendant city the erection of Ian electric light plant was duly authorized and bonds voted in payment therefor; that:

“Pursuant to said election and authority therein granted, the mayor and city council of the defendant, after duly advertising for bids in accord with law, accepted the bid of the plaintiffs as being the highest and best bid for the purpose of erecting section ‘B’ of the specifications for said electric light plant and * * * said defendant duly entered into a contract in writing, a copy of which is attached * * *”

—and further alleged that the plaintiffs performed all the conditions required of them in said contract and were entitled to the consideration named therein less certain credits; further alleged that the city council of the defendant city by resolution increased the compensation provided for in such contract in the sum of $1.250; a portion of such minutes or resolution being as follows :

“Resolved, That the council allow Smith and Whitney of Dallas, Texas, represented by Mr. Connor, to change the contract for furnishing engines for the electric light plant to subst’tute the Ames Uniflow engine for the Nordberg Uniflow engines, as per statements specified, and to allow Smith and Whitney an increase of $1.250 on their contract on account of the advance in prices of the machinery since contract was made on account of the delay of the Attorney General in approving the bonds.”

The defendant city for defense to the action alleged that the plaintiffs failed to complete the work required of it within the time specified under the contract, and referred to that portion of the contract which provided for the payment of ,$25 per day as liquidated damages for failure to complete the work within the time specified, and alleged that the amount of such liquidated damages was in excess of the sum claimed by plaintiffs; further alleged that the resolution of the city council wherein it agreed to pay the plaintiffs an additional sum above the original contract price, was void and that the city was not bound by such action of the council and prayed recovery against the plaintiffs for the sum of $1,259

At the first trial of the cause an instructed verdict was rendered for defendant and judgment entered accordingly, from which the plaintiffs prosecuted an appeal to this court, where such judgment was reversed on the ground that the trial court erred in excluding evidence offered by plaintiffs tending to show that the defendant contributed to the delay in the completion of the work. The opinion of the court on that appeal, which is found in 117 Okla. 204, 245 Pac. 994, concluded in the following language:.

“We therefore find that the ease should be, and the same is hereby, reversed and remanded to the trial court for such furthei proceeding as may be in accord with thif opinion.”

*104 On remand of the ease to the district court the defendant city was granted leave to file an amended answer wherein it specifically denied any liability under the contract on the ground that the same was void and of no force and effect for the reason that the price or compensation contracted to be paid the plaintiffs was in excess of the aggregate amount of the estimated cost of the improvements as compiled by the city engineer and on which the bids were submitted and contract awarded; further alleged that the contract was let on competitive bids and that the plaintiffs fraudulently procured the adoption of a resolution by the council whereby an increase of $1,250 on the contract price was awarded without notice to the public or other1 bidders.

Prior to the second trial of the case the plaintiffs moved for judgment in their favor on the mandate from the Supreme Court, also moved to strike the amended answer of the defendant, demurred thereto, and objected to the introduction of evidence thereon on the grounds that the amended answer was permitted to be filed toy a judge who had previously filed his disqualification to hear the cause and that the answer raised new issues in the cause and was a departure from and in conflict with the defense originally pleaded, all of which were overruled, and the cause proceeded to a second trial before the court without a jury.

It is shown by the record presented that the estimate as prepared by the city engineer and filed with the council prior to the letting of the contract fixed the estimated cost of the work and materials to be done and furnished by the plaintiffs under their contract' at $51,587.90, and that the plaintiffs’ bid and contract price for such work and material was $59,477, which latter sum, together with the increase of $1,250, as shown by the resolution of the city council, was in excess of the estimate as submitted by the city engineer in an amount of $10,139.10.

Judgment was entered for the plaintiffs at the second trial for the sum of $950, and each of the parties, plaintiffs and defendant, filed motion for a new trial, which were overruled, and the plaintiffs bring this appeal and complain of the action of the trial court in permitting defendant to file its amended answer and in denying plaintiffs’ claim in full with interest, and the defendant has filed its cross-petition in error, wherein' it complains of the action of the trial court in rendering judgment for the plaintiffs and asserts, in accordance with its amended answer, that the plaintiffs are not entitled to recover any sum because the contract price and amount paid plaintiffs were in excess of the estimate of the city engineer and in violation of section 4577, O. O. S. 1921.

The first six propositions set forth and argued in the brief of the plaintiffs relate to the alleged errors of the trial court in permitting ’ the defendant to amend its answer, thereby pleading the invalidity of the contract, and the action of the trial court in denying plaintiffs’ motion to strike the same, error in overruling their demurrer thereto, and their objection to the introduction of the evidence by defendant in support thereof.

Plaintiffs concede that the granting or refusal of permission to file amended pleadings rests in the judicial discretion of the trial court where no departure from the original pleadings exists, but say the amended answer in the instant case was permitted to toe filed by a judge of the district court who had previously certified his disqualification to hear the cause, and for that reason the amended answer and filing thereof was void.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rose Brothers, Inc. v. City of Alva
1960 OK 231 (Supreme Court of Oklahoma, 1960)
Leonard v. City of Wagoner
1936 OK 781 (Supreme Court of Oklahoma, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
1930 OK 425, 291 P. 981, 145 Okla. 103, 1930 Okla. LEXIS 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-city-of-tahlequah-okla-1930.