Joblin v. Illinois Surety Co.

182 S.W. 143, 193 Mo. App. 132, 1916 Mo. App. LEXIS 12
CourtMissouri Court of Appeals
DecidedJanuary 4, 1916
StatusPublished
Cited by4 cases

This text of 182 S.W. 143 (Joblin v. Illinois Surety Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joblin v. Illinois Surety Co., 182 S.W. 143, 193 Mo. App. 132, 1916 Mo. App. LEXIS 12 (Mo. Ct. App. 1916).

Opinions

REYNOLDS, P. J.

Action on contract and bond for the erection of a building to be occupied as a residence by plaintiff, who seeks to recover $1728.28 as ex- . cess necessarily paid out by him over the contract price to mechanics and materialmen in order to complete the building, the contractor, Banner Land & Building Company, as it is alleged, having abandoned the work before its completion. The action was originally brought against the contractor as well as against the Illinois Surety Company, .surety on the bond, but was dismissed as to the contractor, no service of process having been made upon it and it not appearing to the action. The trial was before the court, a jury hav[138]*138ing been waived, and at its conclusion the court found in favor of defendant and entered up judgment accordingly, from which plaintiff appealed.

At the close of the' case defendant offered a demurrer and it is stated in the abstract prepared by appellant that the court sustained this demurrer.' That statement is obviously incorrect. The demurrer was offered but no action of the court upon it anywhere appears. Moreover a memorandum filed by the court in announcing its decision, as well as the judgment itself, which appears in the short transcript filed with us, negatives the idea that the case went off on demurrer. ' The judgment recites the appearance of plaintiff and the Illinois Surety Company by their respective attorneys, the waiver of a jury, and then recites that the parties submit the cause'to the court “upon the pleadings, the 'evidence and the proof adduced, and the court having heard and duly considered the same, and being fully advised in the premises, doth find the issues in favor of the defendant Illinois Surety Company, wherefore, it is considered and adjudged,” etc. Obviously, this is not a judgment upon a demurrer. In fact we do not understand that beyond- this recital in the abstract learned counsel for appellant so contend.

In rendering his decision in the case the learned trial judge- filed a memorandum which has been brought up by appellant. As this finding or memorandum was not made at the request of either party, and does not therefore fall within the provisions of section 1972, Revised Statutes 1909, it has not the effect of a finding under that statute, that is, does not have the' effect of a special verdict, as do such findings (South St. Joseph Land Co. v. Bretz, 125 Mo. 418, l. c. 423, 28 S. W. 656), and is to be treated as a general verdict. [See Lesan Advertising Co. v. Castleman, 265 Mo. 345, 177 S. W. 597.] As was said by our Supreme [139]*139Court in Mead v. Spaulding, 94 Mo. 43, 6 S. W. 384, •while such opinion cannot he made to take the place of instructions, or a finding of facts given as an instruction, “the opinion of the trial court may be cited and used in the consideration of the case presented by the record, and in that respect is often of great value to us; but it is not part of the record upon which the case must be determined in this court. ’ ’ That the appellate courts have availed themselves of such memorandum without having been bound by it as a part of the record, appears in very many cases.

In the case at bar no declarations of law were asked unless the demurrer to the evidence which we have before referred to as not having been passed upon may be considered as such; no declarations of law as such were given. It is clear that this case was determined by the trial court largely on the weight of evidence, the evidence being conflicting. Where that is the case, if no error has been made in the application of law, the finding of the trial court is conclusive upon bur court. [Jordan v. Davis and other cases post.]

We cannot state the case better bn its facts or on its law than stated by the learned trial judge, and hence avail ourselves of the memorandum filed by him, not, as before said, as conclusive upon us, or as part of the record proper, but as a correct and succinct statement of facts and of the law. For a better understanding, however, of one of the principal points of controversy in the case, it is well to say that article III of the contract and bond, in substance, provides that no alterations shall be made in the work, nor extra work done, except upon written order of the architects, and article Y, in substance, provides:

“Should the contractor at any time refuse or neglect to supply a sufficiency of properly-skilled workmen, or of materials of the proper quality, or fail in [140]*140any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architects, the owner shall be at liberty after three days’ written notice to the contractor to provide any such labor or materials, and to deduct the cost thereof from any money then due, or thereafter to become due to the contractor, under this contract; and if the architects shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work and to enter upon the premises and take possession, for the purpose of completing the work included under the contract, of all materials, tools and appliances thereon, and to employ any other person or persons to finish the work, and to provide the materials thereof; . . . The expense incurred by the owner herein provided, either for furnishing materials or for finishing the work, and any damages incurred through such default shall be audited and certified by the architects, whose certificate thereof shall be conclusive and binding upon the parties.”

The architects here referred to are Mariner & La Beaume, and the member of that firm who seems to have had charge of this particular work was Mr. Mariner. This by way of explanation.

We use so much of the memorandum of the court above referred to as we think material and necessary, as follows:

“Otn the 12th day'of August, 1907, plaintiff A. H. Joblin entered into a contract with the defendant, the Banner Land and Building Company, for the erection of a certain dwelling house, for the faithful performance of which contract the Banner Land and Building Company and its codefendant, the Illinois Surety Company, entered into a bond in the sum of [141]*141$2849. The contract and bond were in the nsnal form and provided for the work being done under the supervision of Mariner & LaBeaume, architects, and for the making of alterations and payments under the contract on the certificates of such architects.
“The work progressed under the contract in'the usual way until some time in the latter part of November,' or the first of December, when, the evidence discloses, the plaintiff visited the work and found no work being done and so reported to the architect, Mr. Mariner.
“The architects then, under date of December 9,. 1907, gave to the defendant Banner Land and Building Company a notice, as provided in the contract,.'that owing to the fact that no work had been done on the building for some time past, they begged to call attention to article V of the contract and to notify said defendant that unless this work was started within three days from date that they would take other means to complete the contract.
“So far, there is no controversy in the evidence. The evidence discloses that then the architect sought to locate Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. State Social Security Commission v. Estate of Butler
181 S.W.2d 768 (Supreme Court of Missouri, 1944)
Lessner v. Monarch Fire Insurance
153 S.W.2d 129 (Missouri Court of Appeals, 1941)
State Ex Rel. Gordon v. Becker
49 S.W.2d 146 (Supreme Court of Missouri, 1932)
Meridian Lumber Co. v. Lowry Lumber Co.
229 S.W. 267 (Missouri Court of Appeals, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
182 S.W. 143, 193 Mo. App. 132, 1916 Mo. App. LEXIS 12, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joblin-v-illinois-surety-co-moctapp-1916.