Fuqua v. Tulsa Masonic Bldg. Ass'n

1928 OK 71, 263 P. 660, 129 Okla. 106, 1928 Okla. LEXIS 354
CourtSupreme Court of Oklahoma
DecidedJanuary 31, 1928
Docket17118
StatusPublished
Cited by10 cases

This text of 1928 OK 71 (Fuqua v. Tulsa Masonic Bldg. Ass'n) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fuqua v. Tulsa Masonic Bldg. Ass'n, 1928 OK 71, 263 P. 660, 129 Okla. 106, 1928 Okla. LEXIS 354 (Okla. 1928).

Opinion

RILEY, J.

Plaintiff below, Tulsa Masonic’ Building Association, a corporation, secured a judgment against the defendants below, J. R. Fuqua and Maryland Casualty Company, a corporation, in the sum of $14,410.41. The action was based upon a breach of a builder’s bond, wherein Fuqua was principal and the casualty company was a surety for hire.

On June 20, 1922, plaintiff entered into a written contract with Fuqua wherein the latter agreed to furnish the material and perform the labor in constructing the Masonic Temple at Tulsa, for the consideration of $77,450, in consideration of the faithful performance of the obligations of Fuqua. The plaintiff agreed in a written contract to pay the total sum of the consideration to Fuqua “during the progress of the work, on written certificates issued by the architect above mentioned based on the proper assessments of the actual work performed on the building less 15 per cent, as margin, which margin will be accumulated and lastly paid with the final certificate, which will not be issued until after the expiration of 21 days after the whole work under the contract is fully completed and accepted.” It was further agreed that the work called for by this contract should be delivered to plaintiff free from all liens, claims, or incumbrances of any description whatsoever, other than the right of Fuqua to his lien; that if the contractor neglected or was unable to proceed with the work, plaintiff, after giving 48 hours’ notice in writing, might furnish the material and labor for completing the work, “if the architect shall think proper,” and charge the same against the contract price, the contractor to make good any deficiency.

The indemnity bond executed by Fuqua and the Maryland Casualty Company bound them to the plaintiff in the sum of said contract price. It recited that Fuqua, the principal, had entered into said written contract, “a copy of which is hereto annexed, and which contract is made a part hereof, as fully as if recited at length herein.” The bond was to indemnify plaintiff against any loss or damage directly arising by failure of the principal to faithfully perform his contract. It provided that certain conditions were precedent to any right of recovery, among these that on default of the principal, the surety, upon notice and terms, might take over and complete the work; that the plaintiff should faithfully perform all the terms, covenants, and conditions to be performed by it in said contract.

Pursuant to his contract and bond Fuqua commenced the construction of the building. On April 29, 1923, he notified plaintiff that he would be unable to comply with his contract and that the unpaid bills at that time incurred in the performance of the contract amounted to the sum of $8,586.42. He itemized these bills. Thereupon plaintiff and the surety company from its office at Baltimore carried on correspondence whereby it was agreed between them that the surety company waived its right to assume the contract of Fuqua and to complete the building thereunder, and that plaintiff, Tulsa Masonic Building Association, should “proceed accordingly, * * * reserving, however, all the rights and privileges to recover damages from the bonding company and the contractor.” The plaintiff did thereafter complete the building. It paid the said sum of $8,486.42 of *108 itemized delinquent bills, which amount, together with other sums expended in completing the work, amounted to $15,680.19, for which amount plaintiff brought its action. During the trial plaintiff admitted that the sum of $1,269.75 had been expended for labor and materials for extra work not included in the contract, and judgment was rendered for the amount claimed less the amount expended for extras. The cause was tried to a jury. At the close of defendants’ evidence, on motion, the court instructed the jury to render a verdict in favor of the plaintiff in the sum of $14,410.41, which was accordingly done.

Fuqua has abandoned his appeal by failing to file briefs in support of his petition in error, consequently he is eliminated from the case.

The surety company has perfected its appeal.

The first assignment of error presented by the surety company in effect is that ir is not liable on its bond for failure of plaintiff. to prove the amount it paid out for completing such work, and to prove that such amounts were the reasonable and necessary costs of the material and labor actually used in completing the building.

It is to be noted that the contract was by express reference made a part of the bona sued upon. Under provisions of the contract it is to be noted that Fuqua was to perform the labor and furnish the material according to the plans and specifications, wnich by reference were also made a part of the contract, and such performance was to be to the entire satisfaction and under the direction of the architect named, and that plaintiff should make payment to Fuqua “during' progress of the work on written certificates issued by the architects, above named, based upon the proper assessments of the actual work performed on the building,” etc. It is conceded by the surety that all amounts for which plaintiff recovered were paid upon and in pursuance of written certificates issued by said architects.

In National Surety Co. v. Board of Education of City of Hugo, 62 Okla. 259, 162 Pac. 1108, it is held:

“Where the building contract provides that payments shall be made upon the certificate of the architect as the work progresses, and full payment upon the issue of the final certificate of the architect, ordinarily the issuance of the final certificate is conclusive upon the parties as to the performance of the building contract; but in order for this certificate to have this effect the architect must have exercised an honest judgment in issuing it, and any fraud or want of good faith on the part of the architect destroys the force of the certificate, and renders the same subject to impeachment.”

Such is the general rule. 9 C. J. 826; Southern Real Estate & F. Co. v. Bankers Surety Company (Mo.) 207 S. W. 506.

As to this general issue, it is neither-pleaded nor contended by the surety company that the architects in this case did not exercise an honest judgment in issuing the certificates for the work and labor done, nor is any fraud or want of good faith on their part pleaded or proven.

The first assignment must be overruled.

. It is next contended that plaintiff cannot recover because it failed to retain, as a margin, 15 per cent, of the payments upon the work, which margin was to have been accumulated and lastly paid with the final certificate -to be issued after the expiration of 21 days from the completion and acceptance of the work. The contract provided that the plaintiff should so retain such percentage. It is conceded by plaintiff that it did not fully comply with said provision in that it had advanced to Fuqua, prior to his surrendering the contract, for his accommodation in purchasing material, more than 85 per cent, of the amount due on the ivork at the time and retained only a pare of such 15 per cent, to be lastly paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lum v. Lee Way Motor Freight, Inc.
1987 OK 112 (Supreme Court of Oklahoma, 1987)
Consolidated Cut Stone Co. v. Seidenbach
1941 OK 173 (Supreme Court of Oklahoma, 1941)
Wooten v. Warmack
1941 OK 92 (Supreme Court of Oklahoma, 1941)
Western Construction Co. v. Austin
99 P.2d 932 (Washington Supreme Court, 1940)
Wright v. Fidelity Deposit Co. of Maryland
1935 OK 1215 (Supreme Court of Oklahoma, 1935)
Employers' Liability Assur. Corp. v. Cannon
1935 OK 795 (Supreme Court of Oklahoma, 1935)
Vogel v. City of Vinita
1934 OK 516 (Supreme Court of Oklahoma, 1934)
Metropolitan Casualty Ins. v. United Brick & Tile Co.
1934 OK 14 (Supreme Court of Oklahoma, 1934)
New York Indemnity Co. v. May
295 P. 314 (Arizona Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
1928 OK 71, 263 P. 660, 129 Okla. 106, 1928 Okla. LEXIS 354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fuqua-v-tulsa-masonic-bldg-assn-okla-1928.