Consolidated Cut Stone Co. v. Seidenbach

1941 OK 173, 114 P.2d 480, 189 Okla. 128, 1941 Okla. LEXIS 166
CourtSupreme Court of Oklahoma
DecidedMay 20, 1941
DocketNos. 29925, 28902.
StatusPublished
Cited by2 cases

This text of 1941 OK 173 (Consolidated Cut Stone Co. v. Seidenbach) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Cut Stone Co. v. Seidenbach, 1941 OK 173, 114 P.2d 480, 189 Okla. 128, 1941 Okla. LEXIS 166 (Okla. 1941).

Opinion

CORN, V. C. J.

Case No. 28902 is a second appeal, taken after the mandate of this court issued in No. 21661, Consolidated Cut Stone Company et al. v. Seidenbach, 181 Okla. 578, 75 P. 2d 442, a statutory lien foreclosure action instituted April 22, 1927, by Ed M. Light-foot, a labor lien claimant, against J. W. Wilson, the general contractor, and J. L. Seidenbach, the owner. As provided by statute, all lien claimants were originally made parties. The contract between Seidenbach and Wilson called for the construction and completion of a business building in Tulsa for $128,146. Delay damages of $125 per day were provided for on failure to complete the building by January 15, 1927, which time was extended to February 14, 1927. Wilson abandoned his contract with the building partially completed. April 2, 1927, Seidenbach, the owner, took over the work, completing the building on September 15, 1927. Wilson had failed to pay the appellants and other subcontractors supplying him with material and labor, and lien claims were filed to protect the same. The owner, Seidenbach, in the lien foreclosure ac *129 tion, claimed, as against the contract. price of the building, credit for delay damages as provided for in the contract, cost incurred in completing the building, defective work, managerial service and attorney fees. Due to the many lien claims filed and details in the nature of accounting presented, the case was referred to and tried by a referee, who made his report and findings, which were approved, judgment entered thereon, which judgment gave the owner, Seidenbach, as a credit on "the contract price, $26,625 delay damages, $55,-259.69 cost of completion, and amounts paid for labor; the total of such credits, when deducted from the contract price, left $26,335.22 as the fund available to lien claimants as provided by section 10977, O. S. 1931, that is, the amount he, Seidenbach, contracted to pay the original contractor, Wilson. The owner, Seidenbach, recovered judgment against Wilson for $26,308.33, which amount embraced the following items;

Amount paid to Wilson by the owner and unaccounted for by Wilson .$5,597.74
Difference between amount paid to materialmen of $12,616.69 and amount J. L. Seidenbach is entitled to on pro rata basis, which is $2,456.60, the difference being . 10,160.09
Conversion of I-Beams . 300.00
Damages to owner for faulty construction of roof . 250.00
Attorney fees . 10,000.00

No part of this embraced items charged or allowed to the owner as against the lien claimants. The referee allowed the lien claimants attorney fees, interest, and costs, but erroneously includes such items in determining the lienable amount. This court held that under section 10980, O. S. 1931, such items should not be so charged or included; that interest, court costs, and attorney fees could not be recovered as against the owner unless the lien claimant recovered the full amount of his claim. The trial court allowed the referee a fee of $10,000, which was held to be premature and excessive. The owner caused the Hartford Accident & Indemnity Company, surety on Wilson’s bond, to be made a party and pleaded that by its bond it had covenanted to save him from all damage that he might sustain by Wilson’s breaching his contract, pleaded Wilson’s failure to pay subcontractors, the filing of the several liens, the amount of delay damages, and cost of completion. The Hartford moved to be discharged as a party, pleading that it was neither a necessary nor proper party, which plea was sustained and judgment so entered. No appeal was taken from such judgment.

The appellants, Consolidated Cut Stone Company and the Patterson Steel Company, instituted separate actions against the Hartford Accident & Indemnity Company, seeking to recover on the theory and claim that its surety contract guaranteed that Wilson would perform his contract with Seidenbach, which contract, providing specifically that Wilson should pay for all labor and material, was a contract for their benefit. It was held in their action that the Hartford surety contract was made for the sole benefit and protection of the owner, Seidenbach, and not for the benefit of the subcontractors. See Consolidated Cut Stone Co. v. Hartford Accident & Indemnity Co. (C. C. A. 10) 62 Fed. 2d 975.

The owner, Seidenbach, sued the Hartford Accident & Indemnity Company on its surety bond while the former appeal was pending in this court. In that appeal the subcontractors challenged the action of the trial court in allowing Seidenbach credit, as against them, for delay damages and disallowing, as against the owner, interest, court costs, and attorney fees. Seidenbach in his suit against the Hartford Accident & Indemnity Company pleaded all the items of damages that he had set out in the lien foreclosure case, to wit, delay damages, cost of completion, and set out each of the lien claims filed, including interest, costs, and attorney fees allowed them, alleging that he had thereby been damaged in a sum in excess of the penal amount of the bond. Had this court sustained the claim of appellants in the last appeal as to crediting delay damages and charged Seiden-bach with the interest, court costs, and *130 attorney fees, Seidenbach’s loss or damage would have been increased more than $40,000 over and above the amount of his judgment against Wilson. Before this court had disposed of the last appeal, and after the United States Circuit Court of Appeals had rendered its opinion holding that the Hartford Accident & Indemnity Company surety bond was not for the use and benefit of subcontractors, Seidenbach, on February 13, 1933, settled his claim or suit against the Hartford Accident & Indemnity Company for $46,250. Thereafter these appellants asked this court in the former appeal to appoint a referee and hear evidence in support of their claim that all or a part of the sum so paid by the Hartford Accident & Indemnity included the delay damages and other items the owner, Seidenbach, had been allowed credit for on his contract as against the lien claimants. This court held that such an inquiry was foreign to its appellate jurisdiction. The appellants filed a separate suit against Seidenbach in the Tulsa district court, No. 29925, Consolidated Cut Stone Company, a Corporation, etc., v. J. L. Seidenbach et al., wherein they asked that Seidenbach account to them for the money received from the Hartford Accident & Indemnity Company, which suit was pending when this appeal was taken. When the trial court entered judgment on the mandate issued on the former appeal the appellants made application for leave to file amended pleadings, pleading the Hartford Accident & Indemnity Company settlement and seeking to require Seiden-bach to either account to them for the money so received or to have the same added to the fund found available for the payment of liens. The trial court denied the application and they have appealed.

The judgment entered by the trial court conformed to the opinion and mandate of this court. In the former appeal the liability of the owner and the amount due each lien claimant were definitely fixed. The fee to be allowed the referee being a part of the court costs, which this court held must be borne by the lien claimants, not being chargeable against the owner, consideration of the question did not affect the defendant Seidenbach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cook v. McCullough
735 S.W.2d 464 (Court of Appeals of Tennessee, 1987)
P. & E. Finance Co. v. Globe & Republic Ins. Co. of America
1951 OK 92 (Supreme Court of Oklahoma, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
1941 OK 173, 114 P.2d 480, 189 Okla. 128, 1941 Okla. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-cut-stone-co-v-seidenbach-okla-1941.