Becker v. Crispell-Snyder, Inc.

2009 WI App 24, 763 N.W.2d 192, 316 Wis. 2d 359, 2009 Wisc. App. LEXIS 17
CourtCourt of Appeals of Wisconsin
DecidedJanuary 14, 2009
Docket2008AP53
StatusPublished
Cited by11 cases

This text of 2009 WI App 24 (Becker v. Crispell-Snyder, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Becker v. Crispell-Snyder, Inc., 2009 WI App 24, 763 N.W.2d 192, 316 Wis. 2d 359, 2009 Wisc. App. LEXIS 17 (Wis. Ct. App. 2009).

Opinion

BROWN, C.J.

¶ 1. This case presents the flip side of Sussex Tool & Supply, Inc. v. Mainline Sewer and Water, Inc., 231 Wis. 2d 404, 605 N.W.2d 620 (Ct. App. 1999). Sussex Tool held that the complainant's business establishment was not a third-party beneficiary to a road construction contract since it was only incidentally located near the project like every other business on that street. Id. at 409, 416. But here, the town of Somers recruited Richard and Jon Becker to build a subdivision in the town and the oral contract between the town and the engineering firm, Crispell-Snyder, was made for the express purpose of furthering this subdivision development. Further, as a condition of development, the Beckers were obliged to pay Crispell-Snyder's bills, creating a creditor-debtor relationship. These facts gave the Beckers their third-party beneficiary status. The Beckers thus had standing to sue on the *364 contract between the town and Crispell-Snyder. We therefore affirm the judgment of the circuit court made upon a jury award of damages to the Beckers after hearing credible evidence that Crispell-Snyder billed the Beckers for unreasonable and unnecessary work.

¶ 2. Before we set forth the facts, it is important to note that while many of the facts we are about to relate were disputed, our review is limited to a search for any credible evidence that will support the jury verdict. Heikkinen v. United Servs. Auto. Ass'n, 2006 WI App 207, ¶ 42, 296 Wis. 2d 438, 724 N.W.2d 243, aff'd, 2007 WI 124, 305 Wis. 2d 68, 739 N.W.2d 489. Thus, our recap of the facts is in a light most favorable to the jury verdict. See Roach v. Keane, 73 Wis. 2d 524, 536, 243 N.W.2d 508 (1976).

¶ 3. This dispute began in 2000 when the Beckers were considering whether to purchase land in the town of Somers to develop a residential subdivision called "Somers Estates." The Beckers purchased the property after William Morris, the town's administrator, assured them that developing the parcel would be "very profitable." After purchasing the property, the Beckers hired an engineering firm to do the plat survey, staking, inspections and oversight with a bid of approximately $86,000.

¶ 4. In 2001, after having made a substantial investment in the subdivision, the town forced the Beckers to change engineers, telling them that they had to use Crispell-Snyder — the town's engineering firm for thirty years — or construction was going to be shut down and the subdivision was not going to happen. The Beckers objected, but Morris assured them that Crispell-Snyder's fees would be within 1 to 2% of the Beckers' choice of engineers and that the extra 25% in their line of credit would not actually be used. Based on *365 these assurances, the Beckers signed the developer's agreement with the town, making it so.

¶ 5. After the Beckers signed the agreement, construction was allowed to continue. Crispell-Snyder billed the town for its time spent on the Beckers' development, pursuant to its oral public works contract with the town. All the while, the agreement made the Beckers liable for Crispell-Snyder's invoices. 1 The town simply withdrew the money from the Beckers' line of credit. It approved every invoice, relying on CrispellSnyder's good faith to bill for only reasonable and necessary services. The Beckers voiced their objection to Morris, but he never responded. The Beckers did not see the invoices or have a chance to object to their payment until after the fact.

¶ 6. Crispell-Snyder's bills were high enough that the town ultimately withdrew all of the Beckers' line of credit and sent them a bill for $177,392.22. The town also billed the Beckers about $87,000 to settle a lawsuit involving the excavation contractor. The excavation contractor had claimed damages because it had to do more work than it had bid on. The jury determined that Crispell-Snyder's engineering negligence led to this mistake. The evidence showed that Crispell-Snyder put into the specifications an incorrect quantity of earth to be removed.

¶ 7. The Beckers sued Crispell-Snyder, claiming they were third-party beneficiaries to the town's contract with Crispell-Snyder. Crispell-Snyder moved for summary judgment asserting that, as a firm of engi *366 neering professionals, it was immune from suit. It also invoked the Sussex Tool case and claimed that the Beckers, like the complainant in Sussex Tool, could not claim third-party beneficiary status to its contract with the town. The circuit court ruled that Crispell-Snyder waived its immunity claim by not raising it as an affirmative defense, and even if it was not waived, public policy did not forbid the Beckers' claim. It also held that the Beckers were third-party beneficiaries. A trial was held and a jury awarded damages to the Beckers, finding that Crispell-Snyder completed more work than necessary, overcharged the Beckers for change orders and negligently handled the excavator's bid.

¶ 8. Crispell-Snyder appeals, claiming that the Beckers are incidental — not third-party — beneficiaries, that the jury had insufficient evidence to support its verdict, and that common-law immunity or public policy bars the Beckers' claims. We will address each, in turn.

THIRD-PARTY BENEFICIARY STATUS

¶ 9. A party wishing to enforce a contract must either be a party to that contract or a third-party beneficiary. See Schilling v. Employers Mut. Cas. Co., 212 Wis. 2d 878, 886-87, 569 N.W.2d 776 (Ct. App. 1997). In this case, the Beckers were a party to the developer's agreement, but not the public works contract. Crispell-Snyder was a party to the public works contract, but not the developer's agreement. Therefore, if the Beckers wanted to maintain a breach of contract claim against Crispell-Snyder, they had to prove that they were a third-party beneficiary to the public works contract. See id.

*367 ¶ 10. Crispell-Snyder claims that the Beckers were not third-party beneficiaries because they failed to show how the contract between the town and Crispell-Snyder directly and primarily benefited them. The facts regarding this particular issue are not in dispute and require applying the law to the undisputed facts. Therefore, we will review this claim de novo. See Szymczak v. Terrace at St. Francis, 2006 WI App 3, ¶¶ 10-11, 289 Wis. 2d 110, 709 N.W.2d 103 (addressing summary judgment).

¶ 11. A third-party beneficiary is one who the contracting parties intended to "directly and primarily" benefit. Winnebago Homes, Inc. v. Sheldon, 29 Wis. 2d 692, 699, 139 N.W.2d 606 (1966). A party proves its third-party beneficiary status by pointing to specific language in the contract establishing intent. Schilling,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
E.D. Wisconsin, 2026
Dakota Intertek Corp. v. City of Wausau
Court of Appeals of Wisconsin, 2020
Emirat AG v. High Point Printing LLC
248 F. Supp. 3d 911 (E.D. Wisconsin, 2017)
Scheurer v. Fromm Family Foods LLC
202 F. Supp. 3d 1040 (W.D. Wisconsin, 2016)
Apple, Inc. v. Motorola Mobility, Inc.
886 F. Supp. 2d 1061 (W.D. Wisconsin, 2012)
Felton v. Teel Plastics, Inc.
724 F. Supp. 2d 941 (W.D. Wisconsin, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2009 WI App 24, 763 N.W.2d 192, 316 Wis. 2d 359, 2009 Wisc. App. LEXIS 17, Counsel Stack Legal Research, https://law.counselstack.com/opinion/becker-v-crispell-snyder-inc-wisctapp-2009.