Dakota Intertek Corp. v. City of Wausau

CourtCourt of Appeals of Wisconsin
DecidedSeptember 29, 2020
Docket2019AP000591
StatusUnpublished

This text of Dakota Intertek Corp. v. City of Wausau (Dakota Intertek Corp. v. City of Wausau) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dakota Intertek Corp. v. City of Wausau, (Wis. Ct. App. 2020).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. September 29, 2020 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2019AP591 Cir. Ct. No. 2016CV397

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT III

DAKOTA INTERTEK CORP.,

PLAINTIFF-APPELLANT,

V.

CITY OF WAUSAU,

DEFENDANT-RESPONDENT.

APPEAL from a judgment of the circuit court for Marathon County: JILL N. FALSTAD, Judge. Affirmed.

Before Stark, P.J., Hruz and Seidl, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3).

¶1 PER CURIAM. Dakota Intertek Corp. appeals a judgment dismissing its breach of contract claim against the City of Wausau. Dakota, which No. 2019AP591

had been awarded a service contract from the City, settled an outstanding invoice from a supplier by virtue of a mutual release that specifically included Dakota’s claim against the City. Nonetheless, Dakota argues that its claim against the City—or at least certain damages theories—survived the execution of the release. Dakota also argues the circuit court erroneously awarded the City attorney fees as a sanction for Dakota’s conduct in continuing to pursue a frivolous claim.

¶2 We reject Dakota’s arguments. The City was an express third-party beneficiary to the release agreement between Dakota and its supplier. Moreover, the release included the breach of contract claim and all associated damages theories advanced by Dakota in this lawsuit. Finally, Dakota offers no independent basis for challenging the circuit court’s sanctions award, and we perceive no basis to reverse that award. Accordingly, we affirm.

BACKGROUND

¶3 In August 2014, Dakota entered into a contract with the City relating to a riverfront redevelopment project. A geotechnical study revealed ground contamination on the project site that required remediation. Following a bid process, the City awarded the remediation contract to Dakota. The work bid by Dakota involved it chemically treating the contaminated soil before removing it for disposal. The City gave Dakota a list of four approved chemical suppliers, one of which was Regenesis Bioremediation Products, Inc.

¶4 After being awarded the contract, Dakota immediately began negotiating with Regenesis in an attempt to secure a favorable price for the purchase of the chemicals. On September 8, 2014, Dakota placed an order for

2 No. 2019AP591

approximately half of the chemicals it anticipated needing for the project.1 Dakota consulted neither the City nor its general contractor on the project, Stantec, prior to making the purchase, although it is undisputed Dakota was not prohibited from making advance purchases.

¶5 The purchase occurred prior to the City issuing a limited notice to proceed, which happened on September 11, 2014. Stantec, Dakota, and the Wisconsin Department of Natural Resources (DNR) had, by that point, been in discussions about the efficacy of the chemical formula Regenesis had proposed during the bidding process. According to Paul Herbert, a Dakota vice president, the DNR was concerned that the formula “would not bring the contaminant levels down low enough, and that a test pit or a test area would need … to be done to test the theory.” Accordingly, the limited notice to proceed authorized Dakota to begin “mobilization, erosion control measures, asphalt removal and concrete removal.” The notice further stated that the soil remediation and capping components of the project would require City approval, which would be given “when Stantec and [the DNR] have given the City approval to move forward.”

¶6 Following pilot testing, Stantec determined that a greater amount of chemicals than initially thought would be required to effectively treat the soil. As a result, Stantec and the DNR did not believe the project should move forward with the chemical remediation, and Stantec began exploring other options, including landfilling the contaminated soil. On November 19, 2014, Dakota

1 The chemicals were delivered to the remediation site on September 22, 2014. Dakota placed a single order in the designated quantity to save on transportation costs.

3 No. 2019AP591

provided Stantec with a “Request for Information” form RFI 0014 outlining the cost of the landfilling plan. The landfill option was subsequently approved.

¶7 The matter of Dakota’s chemical purchase from Regenesis, however, remained unresolved. The purchase contract between Dakota and Regenesis required payment for the chemicals within thirty days of delivery. The contract stated Dakota was allowed to return the chemicals within ninety days of delivery, subject to freight charges and a fifteen percent restocking fee. Regenesis notified Dakota that, pursuant to these terms, Dakota could return the chemicals to Regenesis at Dakota’s expense at any time before December 21, 2014, accompanied by the payment of a restocking fee of approximately $6,800.

¶8 By December 21, 2014, Dakota had neither paid for nor returned the chemicals to Regenesis. Around the same time as Dakota provided Stantec with the RFI 0014 form, it began negotiating with Regenesis regarding a potential extension of the return window for the chemicals. Regenesis agreed to extend the payment term to March 31, 2015, but it refused to alter the ninety-day return window.2 Dakota elected not to return the chemicals within the return window based on its beliefs that the landfilling option “didn’t seem feasible based on costs at the time” and that the chemicals would ultimately be used for the project.3

¶9 As of February 19, 2015, Regenesis still had not been paid for the chemicals, and it sent a “Notice of Nonpayment” to the City, Stantec, and Dakota,

2 Indeed, the agreement to extend the payment term required Dakota to waive the right to return the chemicals after December 21, 2014. 3 Herbert testified that he mistakenly believed the extension of time for payment also applied to the return window, but he also testified that this mistaken belief was not the reason for Dakota retaining possession of the chemicals.

4 No. 2019AP591

threatening a lien on the City’s property or project funds if the invoice remained outstanding. In late March, Herbert e-mailed Stantec to confirm that the chemicals would not be used on the project, which Stantec confirmed. Dakota then unsuccessfully attempted to negotiate a return of the chemicals with Regenesis, but before Regenesis would consider the request, it demanded payment from Dakota for supplies it had provided on other projects involving Dakota.

¶10 In June 2015, Dakota requested that the City pay for the chemicals in full. The City’s Board of Public Works unanimously denied the request. Dakota submitted a notice of claim with the City in the amount of $139,000, an amount representing the cost of the chemicals as well as lost profits due to the City’s alleged “descoping” of the remediation project. The City denied the claim.

¶11 Meanwhile, Dakota and Regenesis continued to negotiate the payment for the chemicals. On October 29, 2015, Dakota and Regenesis entered into a settlement agreement entitled “Mutual Release of Regenesis and Dakota Intertek Corp. for All Legal and Contractual Issues.” Dakota agreed to pay Regenesis $30,000, and both parties agreed to release all claims against one another relating to the City project. Importantly, the release stated the parties were also releasing all claims against the City.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bettendorf v. Microsoft Corp.
2010 WI App 13 (Court of Appeals of Wisconsin, 2009)
Charolais Breeding Ranches, Ltd. v. FPC Securities Corp.
279 N.W.2d 493 (Court of Appeals of Wisconsin, 1979)
Krenz v. Medical Protective Co.
204 N.W.2d 663 (Wisconsin Supreme Court, 1973)
Doe v. General Motors Acceptance Corp.
2001 WI App 199 (Court of Appeals of Wisconsin, 2001)
Segall v. Hurwitz
339 N.W.2d 333 (Court of Appeals of Wisconsin, 1983)
Brown v. Hammermill Paper Co.
276 N.W.2d 709 (Wisconsin Supreme Court, 1979)
Schilling v. Employers Mutual Casualty Co.
569 N.W.2d 776 (Court of Appeals of Wisconsin, 1997)
Becker v. Crispell-Snyder, Inc.
2009 WI App 24 (Court of Appeals of Wisconsin, 2009)
Sussex Tool & Supply, Inc. v. Mainline Sewer & Water, Inc.
605 N.W.2d 620 (Court of Appeals of Wisconsin, 1999)
Christopher Kieninger v. Crown Equipment Corporation
2019 WI 27 (Wisconsin Supreme Court, 2019)
Severson v. Milwaukee Automobile Insurance
61 N.W.2d 872 (Wisconsin Supreme Court, 1953)
Town Bank v. City Real Estate Development, LLC
2010 WI 134 (Wisconsin Supreme Court, 2010)
Meleski v. Schbohm LLC
2012 WI App 63 (Court of Appeals of Wisconsin, 2012)
Chapman v. B.C. Ziegler & Co.
2013 WI App 127 (Court of Appeals of Wisconsin, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Dakota Intertek Corp. v. City of Wausau, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dakota-intertek-corp-v-city-of-wausau-wisctapp-2020.