Christopher J. Brekken v. Hegland Custom Construction, Inc.

CourtCourt of Appeals of Wisconsin
DecidedSeptember 4, 2024
Docket2023AP000675
StatusUnpublished

This text of Christopher J. Brekken v. Hegland Custom Construction, Inc. (Christopher J. Brekken v. Hegland Custom Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Christopher J. Brekken v. Hegland Custom Construction, Inc., (Wis. Ct. App. 2024).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. September 4, 2024 A party may file with the Supreme Court a Samuel A. Christensen petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2023AP675 Cir. Ct. No. 2020CV104

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT III

CHRISTOPHER J. BREKKEN,

PLAINTIFF-APPELLANT-CROSS-RESPONDENT,

V.

HEGLAND CUSTOM CONSTRUCTION, INC.,

DEFENDANT-RESPONDENT-CROSS-APPELLANT.

APPEAL and CROSS-APPEAL from an order of the circuit court for Pierce County: ELIZABETH L. ROHL, Judge. Affirmed.

Before Stark, P.J., Hruz and Gill, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3).

¶1 PER CURIAM. Christopher J. Brekken appeals from the circuit court’s order, entered following a bench trial, dismissing Brekken’s breach of No. 2023AP675

contract claim against Hegland Custom Construction, Inc.1 Brekken contracted with a general contractor, Gordon Larson and Gordon Larson Construction LLC (collectively, Larson), which thereafter engaged Hegland’s services as a subcontractor. Hegland cross-appeals from the court’s order, which also dismissed Hegland’s counterclaim against Brekken for unjust enrichment. For the reasons that follow, we reject Brekken’s arguments and affirm the court’s order. Therefore, we need not address Hegland’s cross-appeal, which was brought to seek alternative relief if we reversed the court’s decision on Brekken’s direct appeal.

BACKGROUND

¶2 Brekken entered into a construction contract with Larson to build Brekken’s home in Prescott, Wisconsin (hereinafter, the GLC contract). Larson then subcontracted with Hegland to perform framing and carpentry work (hereinafter, the Hegland-Larson contract). According to the Hegland-Larson contract, Hegland’s services were to be completed for the agreed-upon price of $129,769.83, but “changes or additions” were to be addressed “in a change order” and billed at $55.00 per hour “unless otherwise agreed upon.”

¶3 During construction of the home, Hegland would submit invoices to Larson for payment. Larson would then include the invoices with “draw requests” that would be submitted to a title company that paid the draw requests through Brekken’s construction loan. Both Brekken and Larson needed to approve the draw requests before payments were made.

1 Adam Hegland is the owner and president of Hegland Custom Construction, Inc. We will refer to them collectively as “Hegland.”

2 No. 2023AP675

¶4 According to Hegland, Larson requested that Hegland perform additional work on the home, and these additional items were included on the invoices Hegland submitted to Larson and were sometimes listed on those invoices as “change orders.” At trial, Hegland testified regarding multiple issues with the project that necessitated this additional work.2

¶5 Brekken claimed, however, that he did not approve any change orders or additional charges for the work to be completed by Larson or Hegland, and he maintained that the GLC contract and the Hegland-Larson contract were for a fixed fee. In fact, on the draw request dated January 24, 2020, Brekken handwrote a message, stating, “I do not agree with [the] change orders, but I will deal with this going forward on the next draw request.” (Formatting altered.)

¶6 Ultimately, on May 8, 2020, Hegland and Larson entered into an amendment to the Hegland-Larson contract. The May 8 amendment stated: “Due to the numerous change orders to the Brekken residence, the contract needs to be revised to accommodate for the overages.” The amendment increased the per-hour payment rate and identified a list of extra work that was not included in the original bid. There is no dispute that Brekken was not aware of the May 8 amendment signed by Hegland and Larson until after this lawsuit commenced.

¶7 Eventually, Brekken refused to make any further payments to Hegland, and, as a result, Hegland stopped its work on the home in June 2020.3

2 James Edward Sabin, owner of Artisan Building Company LLC, worked with Hegland on the home, and he also testified at trial regarding these issues. 3 Later, Larson also discontinued work on the home, stating in a letter to Brekken that he was “shutting down Gordon Larson Construction LLC” due to financial issues.

3 No. 2023AP675

Hegland informed Larson by e-mail on June 28, 2020, that it would not continue working on the home until it received payment on the invoices that had previously been submitted. This information was communicated to Brekken. Instead of paying those amounts, Brekken hired another company to complete the remaining work required.

¶8 Thereafter, Brekken filed this lawsuit against Hegland, asserting claims for breach of contract, conversion, and theft by contractor. 4 According to the complaint, Hegland “ha[d] not completed the work required under the [Hegland-Larson contract] and ha[d] been overpaid for the work that ha[d] actually been completed by Hegland.” Brekken asserted that he was “an expressly named third[-]party beneficiary” of the Hegland-Larson contract. He sought monetary damages as well as costs and attorneys’ fees.

¶9 Hegland responded with a counterclaim, alleging a cause of action for unjust enrichment. According to Hegland’s counterclaim, Hegland was “asked to provide more services than contemplated by the [Hegland-Larson] contract that was in place,” and, “[a]s a result, [Hegland was not] paid for all labor, services and materials that [it] provided.”

¶10 The parties filed cross-motions for summary judgment. Brekken sought summary judgment on his breach of contract claim and dismissal of Hegland’s unjust enrichment counterclaim. Hegland’s motion argued that all three of Brekken’s claims should be dismissed.

4 Brekken filed a separate suit against Larson and, based on an agreement between the parties, obtained a judgment in the amount of $74,682.

4 No. 2023AP675

¶11 The circuit court held a nonevidentiary hearing5 on the motions. Based on the written submissions and arguments of the parties, the court denied summary judgment to both Brekken and Hegland on the breach of contract claim; granted partial summary judgment to Hegland, dismissing Brekken’s conversion and theft by contractor claims; and denied Brekken’s motion as to Hegland’s unjust enrichment counterclaim.6

¶12 The circuit court then held a two-day bench trial on the parties’ remaining claims. Brekken, Hegland, and Sabin testified. The court entered a written decision and order concluding, first, that Brekken had failed to prove his breach of contract claim because there was no enforceable contract between Brekken and Hegland. The court also determined that even if there were an enforceable contract between the parties, Brekken had failed to establish either a breach of that contract or damages. Finally, the court concluded that Hegland had also failed to meet its burden to prove its unjust enrichment counterclaim. The court ordered both the claim and the counterclaim dismissed. Brekken appeals, and Hegland cross-appeals.7

5 The transcript from the summary judgment hearing was not included in the record on appeal. 6 The parties do not challenge the circuit court’s summary judgment ruling on appeal. 7 Hegland repeatedly refers to the parties by party designation, rather than by name, throughout its appellate briefs, in violation of WIS. STAT. RULE 809.19(1)(i) (2021-22). We caution Hegland’s counsel to avoid similar future violations of the Rules of Appellate Procedure. See WIS.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amjad T. Tufail v. Midwest Hospitality, LLC
2013 WI 62 (Wisconsin Supreme Court, 2013)
State v. Pettit
492 N.W.2d 633 (Court of Appeals of Wisconsin, 1992)
Associates Financial Services Co. of Wisconsin v. Brown
2002 WI App 300 (Court of Appeals of Wisconsin, 2002)
Schell v. Knickelbein
252 N.W.2d 921 (Wisconsin Supreme Court, 1977)
Linden v. Cascade Stone Company, Inc.
2005 WI 113 (Wisconsin Supreme Court, 2005)
Noll v. Dimiceli's, Inc.
340 N.W.2d 575 (Court of Appeals of Wisconsin, 1983)
Schilling v. Employers Mutual Casualty Co.
569 N.W.2d 776 (Court of Appeals of Wisconsin, 1997)
Becker v. Crispell-Snyder, Inc.
2009 WI App 24 (Court of Appeals of Wisconsin, 2009)
A.O. Smith Corp. v. Allstate Insurance
588 N.W.2d 285 (Court of Appeals of Wisconsin, 1998)
Steele v. Pacesetter Motor Cars, Inc.
2003 WI App 242 (Court of Appeals of Wisconsin, 2003)
Brew City Redevelopment Group, LLC v. Ferchill Group
2006 WI App 39 (Court of Appeals of Wisconsin, 2006)
Royster-Clark, Inc. v. Olsen's Mill, Inc.
2006 WI 46 (Wisconsin Supreme Court, 2006)
Severson v. Milwaukee Automobile Insurance
61 N.W.2d 872 (Wisconsin Supreme Court, 1953)
Pierce Associates, Inc. v. Nemours Foundation
865 F.2d 530 (Third Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Christopher J. Brekken v. Hegland Custom Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/christopher-j-brekken-v-hegland-custom-construction-inc-wisctapp-2024.