Steele v. Pacesetter Motor Cars, Inc.

2003 WI App 242, 672 N.W.2d 141, 267 Wis. 2d 873, 52 U.C.C. Rep. Serv. 2d (West) 405, 2003 Wisc. App. LEXIS 964
CourtCourt of Appeals of Wisconsin
DecidedOctober 14, 2003
Docket03-0640
StatusPublished
Cited by15 cases

This text of 2003 WI App 242 (Steele v. Pacesetter Motor Cars, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steele v. Pacesetter Motor Cars, Inc., 2003 WI App 242, 672 N.W.2d 141, 267 Wis. 2d 873, 52 U.C.C. Rep. Serv. 2d (West) 405, 2003 Wisc. App. LEXIS 964 (Wis. Ct. App. 2003).

Opinion

SCHUDSON, J.

¶ 1. William J. Steele, Jr., appeals from the judgment, following a two-day bench trial, awarding him damages of $1972 for Pacesetter Motor Cars, Inc.'s breach of a service contract to repair, restore and refurbish Steele's car. He argues that the trial court made several errors leading it to deny him the $14,281.98 he claimed. We conclude that the trial court erred, as a matter of law, in ruling: (1) that Steele, who had repeatedly taken his car back to Pacesetter for it to complete the restoration and repair work for which he and Pacesetter had contracted, was precluded from recovering amounts he paid for repair services rendered by Uptown Motorcars, Inc., to which he subsequently brought his car, because he had not first given Pacesetter one more opportunity to fix it; and (2) that Allis Machine, the subcontractor to which Uptown sent Steele's engine (and to which Pacesetter, coincidentally, had subcontracted some of its work on the car), not Pacesetter, was the party potentially liable for Steele's additional repair costs. Accordingly, we reverse and remand for the trial court's consideration of the evidence under the correct legal standards. 1

*877 I. BACKGROUND

¶ 2. In 1989, Steele bought a 1963 Chevrolet Impala with the intention of restoring it to its original condition. After doing much of the disassembling work himself, Steele, in 1996, met Patrick Murray, an instructor in the automotive program at Waukesha County Technical College, who had employment experience with General Motors and at a local Chevrolet dealership. Murray expressed interest in restoring the engine; he and Steele contracted for Murray's company, Pacesetter, to do the work, initially estimated at $3,343.84.

¶ 3. From July 1996 through May 1999, Pacesetter worked on the engine and other aspects of the car's restoration. Pacesetter charged Steele more than $21,000 for the work, almost all of which he paid. Although Steele felt some frustration as the costs mounted and more and more time passed, he concluded that it would be best to allow Pacesetter to complete the work. Upon "completion," however, the troubles began.

¶ 4. When Steele picked up the car from Pacesetter in May 1999, the engine backfired each time it was turned off. Steele complained, and Murray instructed him on how to turn off the engine to prevent backfiring. While deeming such special instructions "ridiculous," Steele, anxious to finally drive the car home, left without insisting on further repair. As Steele and his son drove home, however, they noticed that the car was not operating well and that the engine was unusually loud. And when they parked at home, they soon saw oil on the driveway, apparently leaking from the engine. They immediately returned the car to Pacesetter.

¶ 5. Pacesetter took the car back and continued working on it for two weeks, solving some problems, *878 charging for some additional services and not charging for others. Steele remained dissatisfied, however, particularly with what Murray explained would be some unavoidable oil leakage. And, when Steele then attempted to drive the car, the engine would not start. Murray opened the hood, took off the air cleaners, and attempted to start the car, only to see flames shooting from the carburetor and singeing the hood insulation. Steele refused to accept the car.

¶ 6. Murray then sent the car to a carburetor shop and, a few weeks later, advised Steele that it was ready. On delivery, however, Steele still was not pleased with its condition and performance. So when he took the car to Uptown Motorcars for realignment, he also asked that Uptown take "a quick look at the engine because it still seemed to be running very rough." Steele paid Uptown $993.55 for its services, almost all of which related to alleged adjustments to and corrections of Pacesetter's work.

¶ 7. But Steele, still not satisfied with the way the car was running, took it to another Uptown dealership for additional mechanical and body work. From July 1999 through February or March 2000, Uptown then performed extensive work, charging Steele $4,710.82 for body work to "redo previous work done by another shop best as possible," and $8,577.61 to fix the engine. To accomplish that engine work, Uptown sent the engine to Allis Machine, a company that routinely performed engine work on a subcontract basis, and coincidentally, the very company to which Pacesetter had sent the engine for some of the earlier engine restoration.

¶ 8. Having been informed by Uptown's mechanic and body shop manager that Pacesetter's work was deficient, and that it led to the need for most of the *879 subsequent services, Steele sued Pacesetter alleging violation of Wis. Admin. Code § ATCP 132, governing automobile repair practices, and breach of contract. Denying Steele's allegations, Pacesetter asserted that Allis Machine was responsible for the engine problems. Moreover, Pacesetter maintained that Steele should have given it another chance to address the problems so that it could have returned the engine to Allis Machine for repairs. Pacesetter also contended that Steele's son's secret driving of the car had caused some of the problems.

¶ 9. Following a two-day bench trial, the court concluded that Pacesetter had not violated the administrative code, and had "performed all of its services . . . relative to the engine, clutch, power train ... in a good and workmanlike manner to the extent allowed by Steele." The trial court also found, however, that some of Pacesetter's work "with respect to the reassembling the vehicle, specifically aligning parts and the trim and carpet on the interior were not performed in a proper and workmanlike manner." For that, the court awarded Steele $1972. On appeal, Steele does not challenge the court's conclusion under the administrative code. He does, however, challenge the trial court's findings and conclusion under his breach-of-contract claim.

II. DISCUSSION

¶ 10. We will not reverse factual findings made by a trial court unless they are clearly erroneous. See Wis. Stat. § 805.17(2) (2001-02); Benn v. Benn, 230 Wis. 2d *880 301, 307, 602 N.W.2d 65 (Ct. App. 1999). 2 However, whether the facts found by the trial court constitute a breach of contract is a legal issue we review de novo. See Edwards v. Petrone, 160 Wis. 2d 255, 258, 465 N.W.2d 847 (Ct. App. 1990). In evaluating a breach of contract claim, a court must determine whether a valid contract exists, whether a party has violated its terms, and whether any such violation is material such that it has resulted in damages. See Management Computer Servs., Inc. v. Hawkins, Ash, Baptie Co., 206 Wis. 2d 158, 178-83, 557 N.W.2d 67 (1996).

¶ 11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Vincent Durrey Haynes
Court of Appeals of Wisconsin, 2023
Hunt v. Bertrang
2019 WI App 21 (Court of Appeals of Wisconsin, 2019)
Butzlaff v. Reynolds
2018 WI App 71 (Court of Appeals of Wisconsin, 2018)
Schuetta v. Aurora National Life Assurance Co.
27 F. Supp. 3d 949 (E.D. Wisconsin, 2014)
In Re Classicstar Mare Lease Litigation
823 F. Supp. 2d 599 (E.D. Kentucky, 2011)
West Hills Farms, LLC v. ClassicStar, LLC
823 F. Supp. 2d 599 (E.D. Kentucky, 2011)
Tang v. C.A.R.S. Protection Plus, Inc.
2007 WI App 134 (Court of Appeals of Wisconsin, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2003 WI App 242, 672 N.W.2d 141, 267 Wis. 2d 873, 52 U.C.C. Rep. Serv. 2d (West) 405, 2003 Wisc. App. LEXIS 964, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steele-v-pacesetter-motor-cars-inc-wisctapp-2003.