International Production Specialists, Inc. v. Schwing America, Inc.

580 F.3d 587, 2009 U.S. App. LEXIS 19842, 2009 WL 2767143
CourtCourt of Appeals for the Seventh Circuit
DecidedSeptember 2, 2009
Docket07-3632
StatusPublished
Cited by32 cases

This text of 580 F.3d 587 (International Production Specialists, Inc. v. Schwing America, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Production Specialists, Inc. v. Schwing America, Inc., 580 F.3d 587, 2009 U.S. App. LEXIS 19842, 2009 WL 2767143 (7th Cir. 2009).

Opinion

ROVNER, Circuit Judge.

International Production Specialists, Inc. (IPS) entered into a contract with Schwing America, Inc. (Schwing) to make and install five silos to store and treat sludge at a wastewater treatment plant owned by the general contractor, North Shore Sanitary District (NSSD). Initially IPS’s piece of the process was to take about eight months. After several years of delays— some attributable to NSSD, some to IPS, and some to events beyond anyone’s control- — -nearly three-and-a-half years after the parties signed the initial purchase order, the project still had not been completed. On February 11, 2005, Schwing notified IPS that it was cancelling the contract for cause. IPS responded by suing for breach of contract and Schwing counter-sued. The district court ruled in favor of, Schwing, awarding damages in the amount of $467,140.02. We affirm, but remand in part to correct a small error in the calculation of damages.

I.

This case comes to this court after a trial in the district court. The facts of this case, as determined by the trial court, are long and tedious, but necessary for a full understanding of the intricacies of the relationship between the parties.

Schwing and IPS were both subcontractors on a larger project to build a waste-water treatment facility. In 2001, NSSD hired VoesL-Alpine Industries, Inc. (VA Tech) to work on the construction of its new wastewater treatment plant in Waukegan, Illinois, agreeing to pay it $6.6 million. VA Tech, in turn, entered into a $1.25 million subcontract with Schwing to supply and install two wet sludge silos, a dry granules silo (conical silos), two receiving bins, and other associated equipment for the NSSD facility. Pursuant to the terms of the contract with VA Tech, Schwing obtained a performance bond.

Schwing’s operations manager, Nancy Predatsch, decided to find a local contractor to fabricate the silos. A web search turned up IPS, a Wisconsin manufacturer of construction equipment, including standard and custom built bulk material handling equipment. On August 20, 2001, IPS and Schwing executed a purchase order in which, for payment of $666,372, IPS agreed to manufacture and install at the NSSD Waukegan ■ facility the five silos, incorporating the specifications and technical supplies from the VA Tech-Schwing contract.

By attachment, the parties set forth a delivery, installation, and payment schedule. (D. Exh. 1004 at p. 4) 1 . According to the delivery schedule, IPS was to deliver all of the silos (the two receiving bins, the two wet storage, and the one dry storage) by December 28, 2001. The installation schedule was labeled “approximate” and noted the following dates:

Two (2) Sliding Frame Silos (Receiving Bin), Approximately February 1, 2002 2
*591 Two (2) Sliding Frame Silos (Wet Storage), Approximately February 15, 2002 One (1) Conical Silo (Dry Storage), Approximately April 15, 2002

Id. A note below the schedule states, “[ajctual schedule will be dictated by progress on the plant construction contract. Installation activity will need to be coordinated with the site contractor.” Id. The delivery schedule contains no such approximate language.

IPS’s Executive Vice President, Jordan Kopac, Jr. managed IPS’s work directly on site as IPS worked through the late summer and fall 2001. Sehwing made progress payments to IPS totaling $595,692.

In November 2001, NSSD decided to suspend work on the project. Consequently, on November 30, 2001, Sehwing sent IPS a facsimile directing IPS to cease on-site work, but to continue fabricating the two receiving bin silos at the shop, as scheduled. Sehwing also informed IPS that it could continue to deliver materials to the site and unload them, but they should not be fabricated on site. ' Sehwing estimated that the work stoppage would continue for ninety days and asked IPS to inform Sehwing of any cost changes associated with the schedule change.

On April 11, 2002, VA Tech inspected IPS’s work on the silo parts. Representatives from VA Tech, NSSD, IPS, and Sehwing attended the inspection. The next day, a Sehwing representative sent out an e-mail identifying fifteen problems with the silos including improper painting and welding. (Pl.Exh.17). A VA Tech representative also prepared a memorandum noting manufacturing defects, including poor painting and improper welding. (Pl.Exh.18). At the time of the memorandum, 90% of the receiving bin silo manufacturing had been completed, as had 50% of the wet sludge silos and 40% of the dried granules silos. Of course, no installation had begun or was yet required. After the inspection, the project lay dormant for approximately two years — until about February 19, 2004, when VA Tech notified Sehwing that NSSD had restarted the project at a new site in Zion, Illinois and that VA Tech expected Sehwing to honor its contract. VA Tech did not increase its payment to Sehwing.

Sehwing, in turn, informed IPS that the project was restarting and that Sehwing expected IPS to honor its contract. Schwing’s project manager asked IPS to inform him of any additional expenses that IPS might incur as a result of the change of location.

IPS responded that a “deep silo fabrication lay-down area”' — in layman’s terms a work area — would be necessary at the Zion site and would be used to fabricate and store the wet sludge silos on site. It provided two field service quotations for a total of $210,500.

In spring 2004, representatives from Sehwing, IPS, VA Tech, and NSSD met to view the project site, coordinate the silo construction site, discuss scheduling, and review potential lay down sites where IPS could work on the silos. Sehwing asked IPS’s vice president, Kopac, to identify IPS’s lay-down area preference and to present Sehwing with a proposal for reimbursement, of the additional costs for relocating the project and transporting materials. ■ •

After the meeting, IPS’s Kopac called Schwing’s project manager, David Miller once, but did not identify his lay-down area preference. Miller left a number of unreturned messages for Kopac and eventually called IPS’s president, Jordan Kopac, Sr., who informed Sehwing that IPS would not be participating in the project because the new site was problematic. IPS maintains that had a suitable work area been provided, IPS would have been able to complete the project in three to four months. The *592 new area, however, was a full-blown construction site and IPS believed that the lay down area and roadways were insufficient to complete the project.

Schwing solicited bids from other companies to complete IPS’s work, but those bids were high compared to Schwing’s contract with VA Tech, factoring in the payments Schwing already had made to IPS. Consequently, Schwing wrote to IPS on June 10, 2004, asking IPS to honor the contract and resume work, or, in the alternative, return all payments it received.

IPS responded that the agreement it had made was for the Waukegan site and not the Zion site, stating further,

IPS stands ready, willing and able to perform per its contract with Schwing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Agricann v. Natural Remedy
Court of Appeals of Arizona, 2022
Kreg Therapeutics, Inc. v. Vitalgo, Inc.
919 F.3d 405 (Seventh Circuit, 2019)
TA Operating LLC v. Comdata, Inc.
Court of Chancery of Delaware, 2017
Gecker v. Estate of Flynn (In re Emerald Casino, Inc.)
867 F.3d 743 (Seventh Circuit, 2017)
Kevin Larson v. Frances Gecker
Seventh Circuit, 2017
AVL Powertrain Engineering, Inc. v. Fairbanks Morse Engine
178 F. Supp. 3d 765 (W.D. Wisconsin, 2016)
William Gerhartz v. David Richert
779 F.3d 682 (Seventh Circuit, 2015)
Wells Fargo Business Credit v. Donald Hindman
734 F.3d 657 (Seventh Circuit, 2013)
Pacific Cycle, Inc. v. Powergroup International, LLC
969 F. Supp. 2d 1098 (W.D. Wisconsin, 2013)
Mattson Ridge, LLC v. Clear Rock Title, LLP
824 N.W.2d 622 (Supreme Court of Minnesota, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
580 F.3d 587, 2009 U.S. App. LEXIS 19842, 2009 WL 2767143, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-production-specialists-inc-v-schwing-america-inc-ca7-2009.