Skyrise Construction Group LLC v. Annex Construction LLC

CourtCourt of Appeals for the Seventh Circuit
DecidedApril 21, 2020
Docket19-1461
StatusPublished

This text of Skyrise Construction Group LLC v. Annex Construction LLC (Skyrise Construction Group LLC v. Annex Construction LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skyrise Construction Group LLC v. Annex Construction LLC, (7th Cir. 2020).

Opinion

In the

United States Court of Appeals For the Seventh Circuit No. 19-1461

SKYRISE CONSTRUCTION GROUP, LLC, Plaintiff-Appellant,

v.

ANNEX CONSTRUCTION, LLC, Defendant-Appellee.

Appeal from the United States District Court for the Eastern District of Wisconsin. No. 2:18-cv-00381 — Nancy Joseph, Magistrate Judge.

ARGUED SEPTEMBER 25, 2019 — DECIDED APRIL 21, 2020

Before RIPPLE, ROVNER, and BRENNAN, Circuit Judges. ROVNER, Circuit Judge. Skyrise Construction Group, LLC, a subcontractor, sued Annex Construction, LLC, a general contractor, for breach of contract, promissory estoppel, negligent misrepresentation, violation of the Illinois Consumer Fraud and Deceptive Business Practices Act, 815 ILCS 505/1 et seq., and violation of the Wisconsin Deceptive Trade Practices 2 No. 19-1461

Act, Wis. Stat. 100.18. The district court granted summary judgment in favor of the defendants on all claims. We affirm. I. In the early summer of 2017, Annex Construction, LLC (“Annex”), issued a request for bids from subcontractors for a project to construct housing units near the University of Wisconsin-Oshkosh (“Project”). Skyrise Construction Group, LLC (“Skyrise”) answered that call for bids by submitting a proposal on July 7, 2017, to supply the rough framing carpen- try labor for the Project at a price of $899,662. Skyrise submit- ted a second bid that same day for $970,000, revised to include a charge for “stick building.”1 Annex rejected the July 7 bids, and Skyrise followed up with a July 19 bid for $950,000. The July 19 bid caught Annex’s interest, and Tom Tomaszewski, the President of Annex, responded that same day with an emailed “Letter of Intent” (“Letter”) to John Trojan, Skyrise’s project manager. In that Letter, Tomaszewski expressed “the intention of Annex” to “enter into a contract with Skyrise” for the rough carpentry work for the Project, and informed Skyrise that Annex would “work on getting you contract documents in the near future.” R. 19, at 12. On the basis of that Letter, Skyrise immediately blocked out the Project on its calendar and declined to pursue or accept other work during the period that it expected the Project to proceed.

1 “Stick building” involves constructing all of the framing on site, as opposed to modular building, which employs prefabricated components. See https://en.wikipedia.org/wiki/Stick-built_construction (last visited April 14, 2020). No. 19-1461 3

On August 2, Annex emailed the promised contract to Skyrise. The draft document (hereafter “Proposed Contract”) consisted of a six-page “Agreement Between Contractor and Subcontractor,” containing the general parameters of the agreement; a fourteen-page Exhibit A labeled “Subcontract General Conditions,” consisting of eleven articles and numer- ous sub-articles detailing subjects such as design, construction, timing, payment terms, insurance, modifications, and dispute resolution; Exhibit B, a page labeled “The Construction Documents,” with a link to an internet site; Exhibit C, a page labeled “The Project Schedule,” which was otherwise blank; and Exhibit D, a page labeled “Lien Waiver and Contractor’s Affidavit Forms,” which was also otherwise blank. The Proposed Contract declared, in part, that it represented the entire agreement between the parties, superceding all prior negotiations in any form. R. 19, at 17. Skyrise believed that the framing work was scheduled to begin in the first week of October, but the subcontractor delayed signing and returning the Proposed Contract.2 More than a month later, on September 6, Annex again emailed the Proposed Contract to Skyline. The next day, Trojan sent an

2 The timing provisions of the Proposed Contract specified that the work would proceed according to the Project Schedule, a document that was blank when the Proposed Contract was initially presented to Skyrise. Those same timing provisions warned that Annex retained the right to modify the schedule and the sequence of the work, and that the subcontractor would be expected to accommodate those changes. On summary judgment, we must credit Skyrise’s assertion that Tomaszewski orally represented to Skyrise that the Project would be ready for Skyrise to begin the framing work in early October 2017. 4 No. 19-1461

email to Tomaszewski explaining that he (Trojan) was “still reviewing the contracts and ... should have it back to you tomorrow.” R. 18, at 8. But instead of returning the Proposed Contract the next day, Trojan sent a request a week later on behalf of Skyrise’s managing member, Ignacio Garcia: Trojan asked that Tomaszewski “sign our proposal and return [it] to Skyrise Construction while he [Garcia] is reviewing your contract documents.” R. 19, at 15. On September 22, Tomaszewski complied with this request, signing the July 19 bid proposal and writing on the face of the document, “Con- tract exhibit A.” R. 19, at 13–14. Skyrise still did not sign and return the Proposed Contract. Annex requested that Skyrise personnel attend a meeting at the construction site on October 9, and Skyrise complied. Skyrise personnel saw that the project was not ready for framing, and the parties began to discuss a possible expanded role for Skyrise in getting the Project completed on schedule. A few days later, on October 11, Tomaszewski received an email containing the Proposed Contract, signed by Garcia and marked with handwritten edits to the payment terms and also to two items involving the scope of the work to be completed.3 Garcia later asserted that Tomaszewski had orally agreed to the edits regarding payment terms, and that Garcia was merely fixing errors in the terms related to the scope of work. Annex never signed this revised version of the Proposed Contract.

3 Skyrise asserts that it signed and mailed a hard copy of the Proposed Contract on August 10. Apparently, that document was sent to an old address for Annex. Tomaszewski received a scanned copy by email on August 11. No. 19-1461 5

Throughout October, the parties continued to discuss a potentially broader scope of work for Skyrise. On October 31, Skyrise submitted a vastly expanded proposal seeking a contract for framing, siding, windows, and drywall, totaling $3,864,643. On November 2, Tomaszewski sent an email to Trojan and Garcia stating: We are going to go ahead and pass on this guys. I appreciate the hard work however I am going to bring in a large framing company we have a very good relationship with and can meet our timeframe and schedule at a much lower cost. I will have our council [sic] get you a letter on the original contract that you signed in the near future. R. 19, at 62. The very next day, Annex’s general counsel sent by email and overnight mail a letter formally rejecting Skyrise’s October 31 proposal and also stating that Annex “will not be accepting and countersigning the Agreement as marked-up by Subcontractor and is therefore null and void.” R. 19, at 63. Skyrise then filed this diversity suit against Annex, seeking damages for breach of contract, promissory estoppel, negligent misrepresentation, violation of the Illinois Consumer Fraud and Deceptive Business Practices Act, 815 ILCS 505/1 et seq. (“Illinois Act”), and violation of the Wisconsin Deceptive Trade Practices Act, Wis. Stat. 100.18 (“Wisconsin Act”). On cross- motions for summary judgment, the district court granted judgment in favor of Annex on all counts and denied Skyrise’s motion. Skyrise appeals. 6 No. 19-1461

II. On appeal, Skyrise contends that fact disputes preclude judgment on every count.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Fednav International Ltd. v. Continental Insurance
624 F.3d 834 (Seventh Circuit, 2010)
Nature Conservancy v. Wilder Corp. of Delaware
656 F.3d 646 (Seventh Circuit, 2011)
All-Tech Telecom, Inc. v. Amway Corporation
174 F.3d 862 (Seventh Circuit, 1999)
RLI Insurance Company v. Conseco, Inc.
543 F.3d 384 (Seventh Circuit, 2008)
Drennan v. Star Paving Co.
333 P.2d 757 (California Supreme Court, 1958)
Kramer v. Alpine Valley Resort, Inc.
321 N.W.2d 293 (Wisconsin Supreme Court, 1982)
NBZ, INC. v. Pilarski
520 N.W.2d 93 (Court of Appeals of Wisconsin, 1994)
Green Spring Farms v. Kersten
401 N.W.2d 816 (Wisconsin Supreme Court, 1987)
Malzewski v. Rapkin
2006 WI App 183 (Court of Appeals of Wisconsin, 2006)
American National Property & Casualty Co. v. Nersesian
2004 WI App 215 (Court of Appeals of Wisconsin, 2004)
Hoffman v. Red Owl Stores, Inc.
133 N.W.2d 267 (Wisconsin Supreme Court, 1965)
Bicknese v. Sutula
2003 WI 31 (Wisconsin Supreme Court, 2003)
De Bouse v. Bayer AG
922 N.E.2d 309 (Illinois Supreme Court, 2009)
Steele v. Pacesetter Motor Cars, Inc.
2003 WI App 242 (Court of Appeals of Wisconsin, 2003)
Household Utilities, Inc. v. Andrews Co.
236 N.W.2d 663 (Wisconsin Supreme Court, 1976)
Steven Yahnke v. County of Kane, Illinois
823 F.3d 1066 (Seventh Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Skyrise Construction Group LLC v. Annex Construction LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skyrise-construction-group-llc-v-annex-construction-llc-ca7-2020.