This text of International Production Speci v. Schwing America Incorporated (International Production Speci v. Schwing America Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Production Speci v. Schwing America Incorporated, (7th Cir. 2009).

Opinion

In the

United States Court of Appeals For the Seventh Circuit

No. 07-3632

INTERNATIONAL P RODUCTION S PECIALISTS, INC.,

Plaintiff-Appellant, v.

S CHWING A MERICA, INC., Defendant-Appellee.

Appeal from the United States District Court for the Eastern District of Wisconsin. No. 05 C 621—Rudolph T. Randa, Chief Judge.

A RGUED S EPTEMBER 5, 2008—D ECIDED S EPTEMBER 2, 2009

Before F LAUM, R OVNER and W ILLIAMS, Circuit Judges. R OVNER, Circuit Judge. International Production Special- ists, Inc. (IPS) entered into a contract with Schwing Amer- ica, Inc. (Schwing) to make and install five silos to store and treat sludge at a wastewater treatment plant owned by the general contractor, North Shore Sanitary District (NSSD). Initially IPS’s piece of the process was to take about eight months. After several years of delays—some attributable to NSSD, some to IPS, and some to events 2 No. 07-3632

beyond anyone’s control—nearly three-and-a-half years after the parties signed the initial purchase order, the project still had not been completed. On February 11, 2005, Schwing notified IPS that it was cancelling the contract for cause. IPS responded by suing for breach of contract and Schwing countersued. The district court ruled in favor of Schwing, awarding damages in the amount of $467,140.02. We affirm, but remand in part to correct a small error in the calculation of damages.

I. This case comes to this court after a trial in the district court. The facts of this case, as determined by the trial court, are long and tedious, but necessary for a full under- standing of the intricacies of the relationship between the parties. Schwing and IPS were both subcontractors on a larger project to build a wastewater treatment facility. In 2001, NSSD hired Voest-Alpine Industries, Inc. (VA Tech) to work on the construction of its new wastewater treat- ment plant in Waukegan, Illinois, agreeing to pay it $6.6 million. VA Tech, in turn, entered into a $1.25 million subcontract with Schwing to supply and install two wet sludge silos, a dry granules silo (conical silos), two receiving bins, and other associated equipment for the NSSD facility. Pursuant to the terms of the contract with VA Tech, Schwing obtained a performance bond. Schwing’s operations manager, Nancy Predatsch, decided to find a local contractor to fabricate the silos. A No. 07-3632 3

web search turned up IPS, a Wisconsin manufacturer of construction equipment, including standard and custom built bulk material handling equipment. On August 20, 2001, IPS and Schwing executed a purchase order in which, for payment of $666,372, IPS agreed to manu- facture and install at the NSSD Waukegan facility the five silos, incorporating the specifications and technical supplies from the VA Tech-Schwing contract. By attachment, the parties set forth a delivery, installa- tion, and payment schedule. (D. Exh. 1004 at p.4)1 . Accord- ing to the delivery schedule, IPS was to deliver all of the silos (the two receiving bins, the two wet storage, and the one dry storage) by December 28, 2001. The installa- tion schedule was labeled “approximate” and noted the following dates: Two (2) Sliding Frame Silos (Receiving Bin), Approxi- mately February 1, 2002 2 Two (2) Sliding Frame Silos (Wet Storage), Approxi- mately February 15, 2002

1 Exh. References are to district court trial exhibits; D. Exh. to the defendant, Schwing’s exhibits and Pl. Exh. to the plaintiff, IPS’s exhibits. Tr. references are to pages in the trial transcript. 2 The purchase order actually lists these dates as 2001, but it seems clear that this is a scrivener’s error and should be 2002. Of course the equipment could not be installed until after it was delivered. Furthermore, when the parties signed the purchase order on September 5, 2001, the February and April 2001 dates would have been nine and four months past, respectively. 4 No. 07-3632

One (1) Conical Silo (Dry Storage), Approximately April 15, 2002 Id. A note below the schedule states, “[a]ctual schedule will be dictated by progress on the plant construction contract. Installation activity will need to be co- ordinated with the site contractor.” Id. The delivery schedule contains no such approximate language. IPS’s Executive Vice President, Jordan Kopac, Jr. man- aged IPS’s work directly on site as IPS worked through the late summer and fall 2001. Schwing made progress payments to IPS totaling $595,692. In November 2001, NSSD decided to suspend work on the project. Consequently, on November 30, 2001, Schwing sent IPS a facsimile directing IPS to cease on-site work, but to continue fabricating the two receiving bin silos at the shop, as scheduled. Schwing also informed IPS that it could continue to deliver materials to the site and unload them, but they should not be fabricated on site. Schwing estimated that the work stoppage would continue for ninety days and asked IPS to inform Schwing of any cost changes associated with the schedule change. On April 11, 2002, VA Tech inspected IPS’s work on the silo parts. Representatives from VA Tech, NSSD, IPS, and Schwing attended the inspection. The next day, a Schwing representative sent out an e-mail identifying fifteen problems with the silos including improper painting and welding. (Pl. Exh. 17). A VA Tech represen- tative also prepared a memorandum noting manu- facturing defects , including poor painting and improper No. 07-3632 5

welding. (Pl. Exh. 18). At the time of the memorandum, 90% of the receiving bin silo manufacturing had been completed, as had 50% of the wet sludge silos and 40% of the dried granules silos. Of course, no installation had begun or was yet required. After the inspection, the project lay dormant for approximately two years—until about February 19, 2004, when VA Tech notified Schwing that NSSD had restarted the project at a new site in Zion, Illinois and that VA Tech expected Schwing to honor its contract. VA Tech did not increase its payment to Schwing. Schwing, in turn, informed IPS that the project was restarting and that Schwing expected IPS to honor its contract. Schwing’s project manager asked IPS to inform him of any additional expenses that IPS might incur as a result of the change of location. IPS responded that a “deep silo fabrication lay-down area”—in layman’s terms a work area—would be neces- sary at the Zion site and would be used to fabricate and store the wet sludge silos on site. It provided two field service quotations for a total of $210,500. In spring 2004, representatives from Schwing, IPS, VA Tech, and NSSD met to view the project site, coordinate the silo construction site, discuss scheduling, and review potential lay down sites where IPS could work on the silos. Schwing asked IPS’s vice president, Kopac, to identify IPS’s lay-down area preference and to present Schwing with a proposal for reimbursement of the addi- tional costs for relocating the project and transporting materials. 6 No. 07-3632

After the meeting, IPS’s Kopac called Schwing’s project manager, David Miller once, but did not identify his lay- down area preference. Miller left a number of unreturned messages for Kopac and eventually called IPS’s president, Jordan Kopac, Sr., who informed Schwing that IPS would not be participating in the project because the new site was problematic. IPS maintains that had a suitable work area been provided, IPS would have been able to complete the project in three to four months. The new area, however, was a full-blown construction site and IPS believed that the lay down area and roadways were insufficient to complete the project. Schwing solicited bids from other companies to complete IPS’s work, but those bids were high compared to Schwing’s contract with VA Tech, factoring in the payments Schwing already had made to IPS.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quest Medical, Inc. v. Apprill
90 F.3d 1080 (Fifth Circuit, 1996)
Klockner, Inc. v. Federal Wire Mill Corp.
663 F.2d 1370 (Seventh Circuit, 1981)
Jack E. Wright v. United States
139 F.3d 551 (Seventh Circuit, 1998)
Morley-Murphy Co. v. Zenith Electronics Corp.
142 F.3d 373 (Seventh Circuit, 1998)
United States v. Lake
500 F.3d 629 (Seventh Circuit, 2007)
Holmes v. Potter
552 F.3d 536 (Seventh Circuit, 2008)
Thorp Sales Corp. v. Gyuro Grading Co.
331 N.W.2d 342 (Wisconsin Supreme Court, 1983)
Delap v. Institute of America, Inc.
143 N.W.2d 476 (Wisconsin Supreme Court, 1966)
Ranes v. American Family Mutual Insurance
580 N.W.2d 197 (Wisconsin Supreme Court, 1998)
Peterson v. Cornerstone Property Development, LLC
2006 WI App 132 (Court of Appeals of Wisconsin, 2006)
Steele v. Pacesetter Motor Cars, Inc.
2003 WI App 242 (Court of Appeals of Wisconsin, 2003)
Management Computer Services, Inc. v. Hawkins, Ash, Baptie & Co.
557 N.W.2d 67 (Wisconsin Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
International Production Speci v. Schwing America Incorporated, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-production-speci-v-schwing-america-i-ca7-2009.