Wiggins Construction Co. v. Joint School District No. 3

151 N.W.2d 642, 35 Wis. 2d 632, 1967 Wisc. LEXIS 1235
CourtWisconsin Supreme Court
DecidedJune 30, 1967
StatusPublished
Cited by11 cases

This text of 151 N.W.2d 642 (Wiggins Construction Co. v. Joint School District No. 3) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wiggins Construction Co. v. Joint School District No. 3, 151 N.W.2d 642, 35 Wis. 2d 632, 1967 Wisc. LEXIS 1235 (Wis. 1967).

Opinion

Hanley, J.

There are two issues presented by this appeal: (1) Did the trial court err in finding the work *637 as constructed by respondent defective as a matter of law, despite the jury verdict to the contrary; and (2) did the trial court in this case properly apply the Powers rule in assessing damages against respondent in the sum of $1,800?

The building contract requiring the roof deck to be constructed with a four-inch pitch to the east and to the west was of importance since it was to be used as a classroom and as a means of ingress and egress to the adjoining school building. Proper drainage was essential.

The evidence clearly demonstrates that not only did the roof as constructed lack the proper pitch, but had a reverse pitch so as to form low spots in which water, ice and snow accumulated.

Exhibits produced at trial leave no doubt whatsoever that the walking surface as provided on the roof deck was hazardous. This is true even though it was established that there was drainage away from the doorway.

We find no merit to respondent’s argument that the jury answer should stand because the jury believed that since there was some drainage away from the doorway the respondent sufficiently complied with the plans and specifications as amended by the architect.

In oral argument the point was raised by the respondent that the jury should have been able to believe that the architect could orally amend the written contract insofar as the requirements for pitch were concerned, thereby relieving the contractor from liability for work not strictly in conformance with specific requirements.

Under the facts of the instant case this argument is without merit.

A portion of Article 15 of the building contract in question, entitled “Changes in the Work,” reads as follows:

“In giving instructions, the Architect shall have authority to make minor changes in the work, not involving extra cost, and not inconsistent with the purposes of the building, but otherwise, except in an emergency endangering life or property, no extra work or change shall be *638 made unless in pursuance of a written order from the Owner signed or countersigned by the Architect, or a written order from the Architect stating that the Owner has authorized the extra work or change, and no claim for an addition to the contract sum shall be valid unless so ordered.”

There was no written order from the owner authorizing a change in the pitch requirement and it is our opinion that this requirement is not a minor but, in fact, a major change in the building contract with regard to the concrete deck.

In an annotation in Anno. 66 A. L. R. 649, entitled Building Contracts: Effect of Stipulation that Alterations or Extras Must Be Ordered in Writing, it is stated, at page 651:

“Stipulations in building and construction contracts requiring written orders for any alterations or extra work are universally held to be valid and binding upon the parties, in the absence of a waiver, modification, or abrogation thereof.”

The appellant in the instant case did not waive, modify or abrogate the stipulation that changes must be authorized by written order.

The trial court, in its memorandum decision, stated:

“While the work was substantially performed in conformity with the contract documents, and in a good and workmanlike manner, as found by the jury in answer to questions 1 and 2 of the special verdict, it is undisputed that the deck did not have drainage or pitch to the outward sides of the deck, in much of its area, inasmuch as water stood in depressions in the top of the deck over a substantial area. Thus, that work was defective, as a matter of law, . . .
". . .
“. . . Plaintiff went ahead and put on the deck, which has a slight pitch outward in places and backward in others, so that, following the first rainfalls, water stood on large areas of the top surface of the deck. Since the *639 deck was to be used for foot traffic, which is obvious because of the door in the then existing building opening onto the deck, standing water would create hazards of various kinds, as disclosed by the evidence.”

In Hennington v. Valuch (1965), 27 Wis. (2d) 130, 133 N. W. (2d) 824, this court found a breach of contract because the contractor failed to perform exactly his part of the agreement. Moreover, in that case as in the instant case, the jury found that the job had been performed in a workmanlike manner.

Hennington, supra, is authority for affirming the trial court’s decision that the contractor’s work was defective by law. In the instant case, the terms of the contract had not been fulfilled.

After the jury had determined that there was no breach of contract, they were not required to answer any question on damages.

The trial court reasoned that the jury had impliedly found the respondent’s damages to be $6,214, which was the unpaid balance on the contract, and $289.50, the answer to question 3 of the special verdict as to the counter which was installed separately from the contract, plus interest from date of demand, and costs and disbursements.

The trial court used this figure, $6,503.50, as the jury’s verdict and to this amount applied the Powers rule after having determined said amount to be excessive. Powers v. Allstate Ins. Co. (1960), 10 Wis. (2d) 78, 102 N. W. (2d) 393.

The trial court then held that $1,800 was the amount by which the judgment of $6,503.50 would be excessive.

The finding of the trial court, if based on initially correct premises, was determined by the proper method of measuring damages, namely, what was the reasonable cost of remedying the defects as are remedial without unreasonable expenditure? Ashland, Lime, Salt & Cement Co. v. Shores (1899), 105 Wis. 122, 81 N. W. 136; Stern *640 v. Schlafer (1943), 244 Wis. 183, 11 N. W. (2d) 640, 12 N. W. (2d) 678.

The trial court allowed the appellant as a setoff the sum of $1,800.

We are of the opinion that the trial court erred and that there must be a new trial on the issue of damages alone. The respondent in this case was not suing for damages. This action was brought to recover the unpaid balance on the construction contract.

In the instant case, the jury has not answered the question of damages nor the reasonable method of correcting the defect.

It is peculiarly within the jury’s province to answer the question of the reasonable cost of correcting the defect once the court instructs the jury that a defect exists by law.

The jury obviously never considered the issue of damages nor, more particularly, the most reasonable method for curing the defect insofar as it related to the appellant’s damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Roy C. O'Neal
Court of Appeals of Wisconsin, 2020
American Standard, Inc. v. Meehan
517 F. Supp. 2d 976 (N.D. Ohio, 2007)
Lien v. McGladrey & Pullen
509 N.W.2d 421 (South Dakota Supreme Court, 1993)
Allen & O'hara, Inc. v. Barrett Wrecking, Inc.
898 F.2d 512 (Third Circuit, 1990)
Allen & O'Hara, Inc. v. Barrett Wrecking, Inc.
898 F.2d 512 (Seventh Circuit, 1990)
Goebel v. National Exchangors, Inc.
277 N.W.2d 755 (Wisconsin Supreme Court, 1979)
S & M Rotogravure Service, Inc. v. Baer
252 N.W.2d 913 (Wisconsin Supreme Court, 1977)
Krause v. Milwaukee Mutual Insurance
172 N.W.2d 181 (Wisconsin Supreme Court, 1969)
Conklin v. Horner
157 N.W.2d 579 (Wisconsin Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
151 N.W.2d 642, 35 Wis. 2d 632, 1967 Wisc. LEXIS 1235, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wiggins-construction-co-v-joint-school-district-no-3-wis-1967.