Harley v. Mapes Reeves Construction Co.

33 Misc. 626, 68 N.Y.S. 191
CourtNew York Supreme Court
DecidedJanuary 15, 1901
StatusPublished
Cited by9 cases

This text of 33 Misc. 626 (Harley v. Mapes Reeves Construction Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harley v. Mapes Reeves Construction Co., 33 Misc. 626, 68 N.Y.S. 191 (N.Y. Super. Ct. 1901).

Opinion

Gaynor, J.:

After a careful reading of the agreed statement of facts and the other evidence I find as a matter of fact that when the contractor abandoned the .work the surety informed the board of education that it would go on with the work and complete the contract, and that thereupon it did so with the consent of the said board.

When the contractor abandoned the contract, viz., on November 13th, 1899, its surety had the right to take its place and carry out the contract. This was so by the terms of the contract; and also as a general proposition of law. The surety as a third party to the contract bound itself for the performance of the contract and had the right to perform it if its principal failed. That is what its suretyship was for.

If the surety had failed to continue the work after the contractor’s default, and service on both of them of the notice provided for by the contract that unless the work proceeded the contract would be forfeited, the board of education would have had to re-advertise the remaining work for bidders and relet it to the lowest bidder (L. 1897, Ch. 378, sec. 419). The surety would [628]*628then have been liable for any excess in the cost. The contention that this section of the charter relates only to the board of public improvements, because it comes under that head and chapter in the charter, cannot be sustained. It expressly applies to all of the departments of the city government. In construing a scientific instrument of government a court would be inclined to limit the scope of its provisions according to the heads under which they were classified; but this can have no application to a mere bungle like the charter of the city of New York.

Instead of submitting to a forfeiture of the contract, the surety on receiving the said notice gave the board of education notice on November 20th, 1899, and thereafter, that it would complete the contract, and it proceeded to do so. This is the sum and substance of all that occurred. The forms and formalities resorted to make it neither more nor less.

Though no new agreement was necessary, the surety being bound by the original contract to complete the work, a written agreement was thereafter executed, viz., on January 17th, 1900, by the board of education and a person produced by the surety as its representative, for the completion of the original contract by him on payment as they came due of the remaining installments thereof, aggregating $24,000; and to this new agreement the surety signed again as surety. This agreement added nothing to the surety’s already existing obligation under the original contract. It was a mere matter of form in the carrying out of the original contract by the surety, it being conceded on the trial," and now in the requests of the defendant surety to find, that the nominal contractor stood in place of and for the surety; and this was understood at the time by all concerned as plainly appears from all that occurred.

Why the so-called new contract was made at all is not apparent, for it created no new obligation whatever. Twelve days afterwards, viz., on January 29th, the building committee of the board of education on the request of the attorney at law of the ■ surety, and the advice of the corporation counsel that it would be proper, passed a resolution declaring the original contract voided and forfeited”; but it does not seem that this could have changed the status which the surety had already assumed in relation to the original contract and the default of the contractor thereunder; at all events in respect of third persons. And [629]*629plainly there was no snch change. The surety was already engaged in carrying out the original contract and it continued therein to the end. There had been no forfeiture by it, but only by the contractor; and this resolution had reference to no other. It created no new forfeiture; it only affirmed an existing condition. The object of the surety in procuring this unnecessary resolution is not apparent, unless it grew out of an afterthought to try to get rid of all previous mechanic’s liens. But it is too much to believe that the committee of the board lent itself to such a purpose, after the surety had elected to complete the contract, and was actually at work doing so. If they did, their action was legally in bad faith and collusive.

When the surety elected to complete the contract, it took the place of the contractor. The law is not that it thereby only took the possible benefits of that position. Its position was no different to that of an assignee of the contract. Such an assignee would take subject to all prior mechanic’s liens; and so did the surety. The surety as well as the contractor was primarily bound from the beginning to complete the contract. Every person who furnished work or material to the contractor did so in view of this, and of the legal right and possibility of the surety electing to go on with the contract if the contractor failed. If the surety had refused to do so, the lien of the existing mechanic’s liens would thereby have been limited to any amount due to the contractor when he abandoned the work; but on electing to complete the contract the surety could not evade such liens; they continued valid against every installment to come due on the contract, the same as though the contractor had not failed. Such liens as soon as filed were equally valid against the contractor and the surety. Each of them had the right to carry out the contract, and it mattered not to the lienors which should do so. The contract was in fact carried out and completed. That the first half of it was done by the contractor and the second half by the surety is of no more concern to the lienors than if the first half had been done by the surety and the second half by the contractor, or all of it had been done by the surety or by the contractor, or they had done it together. They were each primarily bound by the contract from the beginning that the work would be done (Brant on Sur. sec. 1; Baylies on Sur. 134, sec. 2). The plaintiff and the other lienors did work and [630]*630furnished material with that in view; and under the lien law, and for the purpose of their liens they were as much in privity with the surety as with the principal.

The case of Knapp v. Swaney (56 Mich. 345) was like the present one. The contractors defaulted and the sureties took their place and went on and completed. They sought to compel payment to them by mandamus without regard to prior liens filed for work done for the contractors. The only difference of fact is that they took an assignment of the contract from the contractors. But I do not see how that could make any legal difference; at all events in the present case. This present surety did not need such an assignment; it was a party to the contract, bound for its fulfilment, and had the right to go on with it without leave or license from the contractor after the latter had abandoned the contract. In the case cited Chief Justice Cooley said: “ The claims ” (liens) “ in this case appear to be claims against Allen & Yan Tassel ” (the defaulting contractors), “ not against the relators ” (the sureties). “ In our opinion that is an immaterial fact. The relators step into the shoes of the contractors, and can claim nothing under the contract which Allen & Yan Tassell themselves could not have claimed.”

Two cases are cited against the foregoing, Weisemair v. City of Buffalo (57 Hun, 48) and McChesney v. City of Syracuse (75 Hun, 503); but they are not in point. In the former the learned reporter says:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MacDonald, Etc. v. Calumet Supply Co.
19 N.E.2d 567 (Indiana Supreme Court, 1939)
David Lupton's Sons Const. Co. v. Hugger Bros. Const.
148 So. 610 (Supreme Court of Alabama, 1933)
National Surety Co. v. Wallace
221 A.D. 506 (Appellate Division of the Supreme Court of New York, 1927)
City of New York v. Duffy
129 Misc. 251 (New York Supreme Court, 1927)
Electric Transmission Co. v. Pennington Gap Bank, Inc.
119 S.E. 99 (Supreme Court of Virginia, 1923)
Audley Clarke Co. v. W. F. Plass & Bro.
107 Misc. 722 (New York Supreme Court, 1918)
Maneely v. City of New York
119 A.D. 376 (Appellate Division of the Supreme Court of New York, 1907)
Martin v. Flahive
112 A.D. 347 (Appellate Division of the Supreme Court of New York, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
33 Misc. 626, 68 N.Y.S. 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harley-v-mapes-reeves-construction-co-nysupct-1901.