Beecher v. Schuback

1 A.D. 359, 37 N.Y.S. 325
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 1, 1896
StatusPublished
Cited by10 cases

This text of 1 A.D. 359 (Beecher v. Schuback) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beecher v. Schuback, 1 A.D. 359, 37 N.Y.S. 325 (N.Y. Ct. App. 1896).

Opinion

O’Brien, J.:

The last payment, out of which the appellants insist their liens-should be paid, by the terms of the contract was due when the buildings were completed. By the complaint and by the answers, not only of the owner, but also of the defendant lienors, who are appellants here, the issue tendered was whether or not the work on the buildings was substantially performed in accordance with the-plans and specifications. The confusion which has been introduced is due entirely to the failure to confine the proof to the issue thus-presented.

After the introduction of evidence by the lienors tending to support their contention of complete or substantial performance, they fearing that they might fail upon, their proof, were allowed, without an amendment of the pleadings and against the objection of the owner, to offer evidence excusing the failure of the contractor to perform, and tending to show that the -owner subsequently completed the buildings, and thus to shift their ground and tender an issue not presented by the pleadings. The case thus assumes a new phase, and we are referred to testimony in this voluminous record tending to show, as claimed by the lienors, that the owner, under a provision of the contract, gave notice to the contractors that, by reason of their failure to furnish a sufficiency of material and workmen, he elected himself to complete the work, and that he did so complete it for an amount which is nowhere proven or determined or found, but which, it is insisted, was less-than the last payment due under the contract. In passing, we may remark upon this question of performance by the owner, that, assuming the evidence tends to show that in some way the owner put the buildings into a habitable condition, nevertheless, such evidence does not prove, nor is there any finding, that the owner completed them according to the plans and specifications; and if, as claimed by the lienors, the testimony tends to show they were completed by the owner, we are unable, except in respect to one particular, viz., some trim work for which he paid, to determine in what manner or [363]*363to what extent such work conformed to or deviated from the plans and specifications.

Upon sufficient evidence the referee has found that the contractors did not complete, or substantially complete, the buildings, and, therefore, the conclusion follows necessarily that there was a failure to sustain the only issue which was tendered by the pleadings, either as between the plaintiff or the other lienors and the owner.

In Elting v. Dayton (17 N. Y. Supp. 849), which was an action brought by a builder to recover for work done under a building contract, the complaint alleged full performance on his part, and the proof in this respect having failed, evidence of modification of the contract or waiver was offered by the plaintiff by way of excuse against the objection of the owner. Such testimony was held inadmissible under the pleadings, the presiding justice of this court who wrote the opinion in that case saying : An allegation in the complaint that the terms of a contract have been fully complied with, does not authorize proof that it has not been complied with because of certain facts in respect to which no mention is made in the jfieadings. * * * The only issue tendered by a pleading containing this allegation is as to completion of the contract, not to excuses for nonperformance. It might have been true that, upon a proper application made, the plaintiff would have been allowed to amend his complaint, and, if no objection had been taken to the admission of this testimony, that this court would have amended the complaint in order to support the judgment. But in view of the fact that objection was taken to this testimony at the time of the trial, upon the precise ground which is urged here, and exception taken to the overruling of the objection, the court cannot consider the pleadings amended to conform to the proof.”

The advantage of the rule which requires that a trial should be conducted and a conclusion reached secv/ndmn allegata et probata is well exemplified in this ease wherein, after we depart from the point indicated by the pleadings, we are taken from a clear and open way into a labyrinth of by-paths, which the appellants’’ counsel themselves have pursued and which they now urge upon the court to' follow, without any well-defined notion of where they will lead, but with the hope that a way can be found to reach a satisfactory destination. The referee has traveled over most of [364]*364these, and witli his account of the excursion we might well rest content were it not that it is insisted that in one or two places most fatal to the appellants he lost his way.

It is insisted that the contractors did not abandon the work, bnt were prevented by the owner from proceeding beyond October 11, 1889, and, therefore, were entitled to recover, in any view of the case, upon a quantum meruit, whether the buildings were finally completed or not. If the right to recover were placed on this ground, and the evidence were sufficiently clear to support a finding that the contractors did not abandon the work, but were prevented by the owner from completing, there might be some force in this contention. But not only is there no finding, but the evidence itself does not satisfactorily show, that through any fault of the owner the contractors were prevented from performing their contract. There was some evidence from which it appeared that instead of cash the ■owner substituted notes which the contractors were obliged to have discounted, and that this to some extent embarrassed the contractors. But the latter did not claim or prove that the owner was not justified in giving the notice of his election to complete the work himself — all that appears being that upon getting such notice the contractors thereafter ceased to do any work upon the buildings.

It is further insisted that the election by the owner to complete the work, whether rightful or wrongful, does not change the lienors’ rights, the argument being that if the building was substantially ■completed under the contract before the action was commenced, it matters not whether by the contractors or by the contractor jpro hae ■vice, in either event the lienors would be entitled to the benefit of the rule of substantial performance, whether such was the work of Schuback, the owner, or of Barron & Barron, the contractors. We not do assent to this proposition, because the lienors’ rights were predicated upon the substantial completion by the contractors; and if the owner rightfully elected to take the contractors’ place, the subsequent completion by him of the buildings would present a case for the application of the rule laid down in Van Clief v. Van Vechten (130 N. Y. 577), which is thus stated: If nothing is due to the contractor pursuant -to the contract when the lien is filed, and he abandons the undertaking without just cause, but the owner completes the building according to .the contract, and under a provision thereof permitting it, the lien [365]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edward E. Buhler Co. v. New York Dock Co.
170 A.D. 486 (Appellate Division of the Supreme Court of New York, 1915)
Rosenthal Paper Co. v. National Folding Box & Paper Co.
91 Misc. 405 (City of New York Municipal Court, 1915)
Borup v. Von Kokeritz
162 A.D. 394 (Appellate Division of the Supreme Court of New York, 1914)
Maneely v. City of New York
119 A.D. 376 (Appellate Division of the Supreme Court of New York, 1907)
Williams v. Fire Ass'n
119 A.D. 573 (Appellate Division of the Supreme Court of New York, 1907)
Martin v. Flahive
112 A.D. 347 (Appellate Division of the Supreme Court of New York, 1906)
Brandt v. City of New York
110 A.D. 396 (Appellate Division of the Supreme Court of New York, 1905)
Ryer v. Prudential Insurance
85 A.D. 7 (Appellate Division of the Supreme Court of New York, 1903)
Burr v. Union Surety & Guaranty Co.
86 A.D. 545 (Appellate Division of the Supreme Court of New York, 1903)
Brainard v. . County of Kings
50 N.E. 263 (New York Court of Appeals, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
1 A.D. 359, 37 N.Y.S. 325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beecher-v-schuback-nyappdiv-1896.