Beardsley v. . Cook

38 N.E. 109, 143 N.Y. 143, 62 N.Y. St. Rep. 144, 98 Sickels 143, 1894 N.Y. LEXIS 928
CourtNew York Court of Appeals
DecidedOctober 9, 1894
StatusPublished
Cited by20 cases

This text of 38 N.E. 109 (Beardsley v. . Cook) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beardsley v. . Cook, 38 N.E. 109, 143 N.Y. 143, 62 N.Y. St. Rep. 144, 98 Sickels 143, 1894 N.Y. LEXIS 928 (N.Y. 1894).

Opinion

O’Brien, J.

About the first of August, 1890, the defendant entered into a Avritten agreement Avith the firm of Davis .& Fay, builders, whereby they agreed to furnish all the materials and labor in the erection of two houses for the defendant, to be completed on or before January 1, 1891, for the sum of $6,381, to be paid in installments as the work progressed and reached certain stages, the last payment, amounting to the sum of $2,181, to be paid when the houses were -completed.

About a month afterwards the plaintiff contracted, in writing, with Davis & Fay to furnish for these houses all the necessary interior and exterior trim, including doors, sash, blinds, wainscot, complete, except the Venetian blinds ; the window frames and stairs to be all cleaned and prepared for finish in the natural wood, for the sum of $1,175, to be paid as follows: $150 when sash delivered, $200 when the standing trim was on, $400 when the doors were hung, and $425 when the houses were completed. The builders entered *147 upon the performance of their contract with the defendant, and the plaintiff on the performance of his contract with them, and on the 11th of December, 1890, a considerable part of the work had been done, when the plaintiff procured from the .builders a written order upon the defendant, signed by them, and addressed to him, in which they requested the defendant to retain and pay to the plaintiff, from the last payment to be made to them under their contract, the sum of $1,175, according to the terms of their contract with the plaintiff. The defendant wrote across the face of this order his acceptance of the same. This action was brought upon the defendant’s contract with the plaintiff as evidenced by his acceptance of the order, and the plaintiff has recovered. The defendant’s obligation to the plaintiff, as expressed in the acceptance, was that he would retain in his hands from the last payment due upon his contract with the builders, sufficient to pay the plaintiff. The arrangement contemplated that the builders would perform their contract with the defendant., and thereby become entitled to the last payment, and that the plaintiff would perform his agreement with the builders, and thus entitle himself to call upon them to pay as they had agreed, and upon the defendant to discharge the obligation assumed by his acceptance. The difficulty in this cáse arises from the fact that the builders did not perform their contract with the defendant, nor did the plaintiff fully perform his contract with the builders, though perhaps the latter fact is not important except so far as it bears on the question' of the amount which remained in the defendant’s hands applicable to the last payment. The record discloses a state of facts not within the contemplation of the parties when the order which the plaintiff is seeking to enforce was accepted by the defendant. Some of these facts appear in the findings of the court; others are to be gathered from the undisputed testimony, though the learned trial judge refused to find them at the request of the defendant. By the terms of the contract between the defendant and the builders, the payments were to be made upon the certificate of the architect that performance *148 had been made to entitle the contractor to the particular payment. Bio such certificate was ever furnished, and there is no finding in the case that it was waived, or unnecessarily or improperly withheld. (Wright v. Reusens, 133 N. Y. 298; Weeks v. O’Brien, 141 id. 199.)

The builders never performed the contract and never completed the houses. It may be that there was a sufficient excuse for non-performance, but there is no finding on the subject and it is not'apparent from the proofs. There was a, clause in the building contract to the effect that in case they failed to complete the houses and furnish the necessary materials and labor for that purpose, then the defendant might do-it and deduct the expense of completion from any sums unpaid upon the contract. The defendant did complete the houses under this provision of the contract; whether with or without the consent of the builders is not now very material. But the learned trial judge refused to find that the builders failed to perform their contract, and the amount expended by the defendant in completing the houses, which was a most important element in ascertaining what portion, if any, of the last payment, from which the order in suit was to be paid, ever became due to the contractors ’has not been found, though requests to that effect were made by the defendant, and proof had been given on that subject. We agree with the learned counsel for the plaintiff that the mere fact that the defendant-completed the houses and the builders did not, does not necessarily affect the right of recovery upon the order. The defendant elected to complete the performance of the contract himself instead of insisting upon performance by the-builders, and, therefore, any part of the contract price or of the last payment that remains in his hands, after deducting the expenses of completing the houses, is applicable to the payment of the plaintiff’s claim, and under such circumstances the certificate of the architect would not be necessary to enable the builders or the plaintiff to recover the balance remaining in the defendant’s hands. But the difficulty is that the learned trial judge apparently refused to go into these *149 questions, or to find what the balance actually was, and it is not the province of an appellate court to attempt to spell out the facts from conflicting evidence. The learned -counsel for the plaintiff suggests that the last payment, from which the order in question was to be satisfied, had been depleted by the defendant by payments made to the builders in advance, after the acceptance of the order, and hence such payments should not be considered in determining the amount remaining in the defendant’s hands applicable to the payment of the claim. But there is no finding that such payments were made as matter of fact, and the counsel’s position in this respect is based upon inferences and arguments drawn from testimony quite uncertain and inconclusive. It is quite clear that this point was not brought to the attention of the trial court, nor developed at the trial in such a way as to render it available upon this appeal. It is not claimed that the plaintiff ever actually performed his contract with the builders by furnishing all the work and material embraced in it. The testimony is quite clear that he did not, and the fact is fairly to be implied from the findings. He did, however, furnish material for which he was never paid, amounting to a sum equal to the recovery in this case. It also appears that the builders or the defendant himself, after he had assumed the performance of the contract, were obliged to procure and pay for-material which the plaintiff had contracted to furnish. What, this amounted to is not found, and it is quite difficult to ascertain from the evidence.

The trial court has found in substance that performance on the part of the plaintiff was waived by the defendant, but there is no evidence in the case to warrant this conclusion. On the contrary, the testimony of the builders, which is not contradicted, is to the effect that they called upon him from time to time to furnish articles embraced in the contract, and that he failed to do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Century Cement Manufacturing Co. v. Fiore
264 A.D. 475 (Appellate Division of the Supreme Court of New York, 1942)
Rockmore v. Lehman
128 F.2d 564 (Second Circuit, 1942)
Arrow Iron Works, Inc. v. Greene
183 N.E. 515 (New York Court of Appeals, 1932)
Ahrens & Ott Mfg. Co. v. Moore
131 Tenn. 191 (Tennessee Supreme Court, 1914)
Hall v. . Jones
66 S.E. 350 (Supreme Court of North Carolina, 1909)
Spengler v. Stiles-Tull Lumber Co.
48 So. 966 (Mississippi Supreme Court, 1909)
White v. Livingston
69 A.D. 361 (Appellate Division of the Supreme Court of New York, 1902)
Prata v. Green
70 A.D. 224 (Appellate Division of the Supreme Court of New York, 1902)
Smith v. . Wetmore
60 N.E. 419 (New York Court of Appeals, 1901)
Bates v. Salt Springs National Bank
51 N.E. 1033 (New York Court of Appeals, 1898)
Ball & Wood Co. v. Jonathan Clark & Sons Co.
31 A.D. 356 (Appellate Division of the Supreme Court of New York, 1898)
Brainard v. . County of Kings
50 N.E. 263 (New York Court of Appeals, 1898)
Beardsley v. . Cook
49 N.E. 126 (New York Court of Appeals, 1898)
Beecher v. Schuback
1 A.D. 359 (Appellate Division of the Supreme Court of New York, 1896)
Hurd v. Johnson Park Inv. Co.
34 N.Y.S. 915 (Superior Court of New York, 1895)
Hurd v. Johnson Park Investment Co.
69 N.Y. St. Rep. 141 (Superior Court of Buffalo, 1895)
Beardsley v. Cook
35 N.Y.S. 12 (New York Supreme Court, 1895)
Murray v. Micolino
31 N.Y.S. 1109 (New York Supreme Court, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
38 N.E. 109, 143 N.Y. 143, 62 N.Y. St. Rep. 144, 98 Sickels 143, 1894 N.Y. LEXIS 928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beardsley-v-cook-ny-1894.