Century Cement Manufacturing Co. v. Fiore

264 A.D. 475, 36 N.Y.S.2d 332, 1942 N.Y. App. Div. LEXIS 4185
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 1, 1942
StatusPublished
Cited by8 cases

This text of 264 A.D. 475 (Century Cement Manufacturing Co. v. Fiore) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Century Cement Manufacturing Co. v. Fiore, 264 A.D. 475, 36 N.Y.S.2d 332, 1942 N.Y. App. Div. LEXIS 4185 (N.Y. Ct. App. 1942).

Opinions

Schenck, J.

This is an appeal from an order and judgment granting the motion of respondent, New York Casualty Company, for affirmative relief in its claim to a fund of $3,778.63 remaining in the hands of the State of New York unexpended and available for distribution upon a contract between the State of New York and the defendant Luciano. The appellant is assignee of Luciano’s rights and interest in the proceeds of the aforesaid contract. The respondent is surety on two bonds executed by Luciano in connection with the contract, one covering completion thereof, the other covering payment to materialmen and laborers employed in performance of the contract. The controversy herein arises from .the conflicting claims of these two parties to the aforesaid fund held by the State.

The contract in question was let in August, 1939, being officially approved September 11, 1939. It provided for the performance of certain construction work upon a State highway in Washington county. It also contained certain standard provisions in printed form and made part thereof for termination of the contract by the State under certain circumstances. The more pertinent parts of these provisions appearing on page 6 of the printed part of the contract are as follows:

“ 10. It is further mutually agreed that if at any time during the prosecution of the work the Commissioner of Highways shall determine that the work upon any contract for the construction or improvement of a State or county highway is not being performed according to the contract or for the best interests of the State, that said Commissioner of Highways may suspend or stop the work under contract while it is in progress, and that the Commissioner of Highways shall thereupon complete the work in such manner as will accord the contract, plans and specifications and be for the best interests of the State, or he may cancel the contract and readvertise and relet as provided in Section 40 of the Highway Law, being Chapter 63 of the Laws of 1936, and the amendments thereto, and any excess in the cost of completing the contract beyond the price for which it was originally awarded shall be charged to and paid by the Contractor failing to perform the work.

“ The Contractor further agrees, pursuant- to the provision of Section 40 of the Highway Law, that the State reserves the right [477]*477to suspend or cancel this contract as above provided, and to complete the work thereunder or readvertise and relet as the Commissioner of Highways may determine.

“ Whenever the Commissioner of Highways determines to suspend or stop work under the contract, a written notice sent by mail to the Contractor at his address and to the surety company, or bond man, at their address, shall be sufficient notice of his action in the premises.

“ 11. It is further mutually agreed that the State Department of Public Works, Division of Highways, may apply any moneys due or to become due under this contract to the completion of the work or to the payment of the second Contractor; and in case a contract let under such forfeiture is let at a figure in excess of the amount remaining unpaid on the contract so forfeited or cancelled free from all liens and other encumbrances, then the principal agrees to deposit, within ten days from the receipt of notice of such reletting, to the credit of the State Department of Public Works, Division of Highways, for the prosecution and completion of the work a sum of money which is equal to such excess. In case the State Department of Public Works, Division of Highways, decides to complete said work in any other manner than by contract, then the said principal agrees to deposit to the credit of the State Department of Public Works, Division of Highways, within ten days from the receipt of notice of the final completion of the work, the amount of any excess cost occasioned by such completion, over the amount remaining unpaid on the contract so forfeited or cancelled free from all hens and other encumbrances. It is further mutually agreed that if the Contractor fails to deposit such sum to the credit of the State Department of Public Works, Division of Highways, and the surety on the bond for the faithful performance of this contract pays or deposits the same, that the State Department of Public Works, Division of Highways, may subrogate to such surety ah rights, claims and titles to any moneys remaining in the hands of the State Department of Public Works, Division of Highways, which are adjudged as belonging to the Contractor Principal.”

In connection with the letting of the contract, furthermore, two bonds were required before Luciano’s bid could be accepted. Both were executed by Luciano as principal, and respondent, as surety. Both ran to the People of the State of New York as obligee. One bond was conditioned upon the completion of the contract in accordance with its terms and in such manner as to hold the State of New York harmless for damages, costs and judgments in excess of the amount of the contract. This is termed [478]*478the “ completion ” bond. The other bond, likewise running to the People as obligee, is conditioned upon the prompt payment of “ all moneys due to all persons supplying the contractor or a sub-contractor with labor and materials employed and used in carrying out the contract.” This is known as the “ labor and material ” bond. Both bonds were dated August 21, 1939.

Subsequently, after the letting of the contract and after the execution of the bonds, the contractor Luciano made his assignment to the appellant Fiore in consideration of moneys advanced presumably for use in connection with the contract. This assignment was filed November 25, 1939. On the said advances, there is a balance remaining in the sum of $3,950. Upon the basis of this assignment, appellant now claims the funds held by the State.

Following the assignment to Fiore, Luciano proceeded with the contract to partial completion. He was unable to complete it, however, and finally defaulted, as a result of which the State terminated the contract pursuant to the provisions thereof quoted above. At the time of the default Luciano had earned $4,925.71 on the contract on an estimate basis which had not been paid to him. The State elected to complete the contract itself at a cost of $1,147.08. This amount was deducted from the balance owing to Luciano, leaving a net balance on hand of $3,778.63, this amount being the subject of the controversy.

While the contract was completed by the State from the point of default at the foregoing comparatively small cost, that amount did not anywhere nearly approximate the total additional cost necessarily incurred in the final termination of the project. At the time, of default, there were numerous claims for materials and labor, wages and costs outstanding. Some apparently were reduced to mechanics’ liens. Others were not, but all seemed to be justified. At least they do not appear to have been controverted upon their respective merits in the present litigation. Because of these claims against the defaulting contractor, the respondent surety company herein paid out an aggregate of approximately $20,000 under the labor and material bond. Upon the basis of these payments, made pursuant to a bond conditioned upon Luciano’s payment of the items involved and upon which he had defaulted, respondent now claims right by subrogation to the funds in the possession of the State.

The order and judgment in favor of the respondent surety company should be affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Surety Corp. v. State National Bank of Frankfort
454 S.W.2d 354 (Court of Appeals of Kentucky (pre-1976), 1970)
State Bank v. Dan-Bar Contracting Co.
12 A.D.2d 416 (Appellate Division of the Supreme Court of New York, 1961)
State Bank v. Dan-Bar Contracting Co.
23 Misc. 2d 487 (New York Supreme Court, 1960)
In Re Massachusetts Bonding and Insurance Company
259 F.2d 33 (Second Circuit, 1958)
Massachusetts Bonding & Insurance v. New York
259 F.2d 33 (Second Circuit, 1958)
Perlin v. Greenberg
196 Misc. 865 (New York Supreme Court, 1949)
United States Fidelity & Guaranty Co. v. Triborough Bridge Authority
74 N.E.2d 226 (New York Court of Appeals, 1947)
Hedley v. New Amsterdam Casualty Co.
267 A.D. 800 (Appellate Division of the Supreme Court of New York, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
264 A.D. 475, 36 N.Y.S.2d 332, 1942 N.Y. App. Div. LEXIS 4185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/century-cement-manufacturing-co-v-fiore-nyappdiv-1942.