Bates v. Salt Springs National Bank

51 N.E. 1033, 157 N.Y. 322, 11 E.H. Smith 322, 1898 N.Y. LEXIS 583
CourtNew York Court of Appeals
DecidedNovember 22, 1898
StatusPublished
Cited by47 cases

This text of 51 N.E. 1033 (Bates v. Salt Springs National Bank) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bates v. Salt Springs National Bank, 51 N.E. 1033, 157 N.Y. 322, 11 E.H. Smith 322, 1898 N.Y. LEXIS 583 (N.Y. 1898).

Opinion

Gray, J.

These actions were brought for the foreclosure of mechanics’ liens and were consolidated by order of the court. The question presented is whether the appellant, the Salt Springs National Bank of Syracuse, as the assignee of the contractors, is entitled to a fund, which has been paid into court to abide the event of the action, as against the various parties who have filed lien's for work done and materials furnished in the execution of the contract. It appears that in December, 1890, the firm of Dickison and Allen entered into a contract with the trustees of the Masonic Hall and Asylum Fund for the erection of a Masonic home near Htica. The contract price of $139,500, was to be paid in twelve installments ; the last of which, being stated at the sum of $28,500, was payable when the buildings were completely finished and accepted. After the making of said contract, and in Febru *326 arv, 1891, before any work had been performed under the contract, the contractors assigned, in writing, to the defendant, the Salt Springs Bank, the last payment to be made on said contract as collateral security for their existing and future indebtedness to the bank. Notice of this assignment was given to the trustees on April 28th, 1892. Oh May 31st, and on June 4th following, mechanics’ liens were filed by the defendants Cahill and Utica Planing Mills. On the latter date the contractors made a further assignment to the Salt Springs-Bank, as collateral security, of all payments then, or which might thereafter become, due and payable on said contract, including extra work. Notice of this assignment was received by the trustees on June 6th. Thereupon, the contractors, being insolvent, abandoned the work and requested the trustees to finish the buildings under the contract. Between June 5th and July 17tli, 1892, other liens, aggregating over $18,000, were filed by the creditors of the contractors. At the time of the abandonment of the work, there was unpaid upon the contract, including extra work, the sum of $33,067.31. The trustees in completing the work on the buildings under the contract expended the sum of $8,478.32. Deducting fi'om that amount certain damages for delay and the expenses of completing the buildings, the sum which would have been payable to the contractors, if they had completed their contract, and which is now to be disposed of in this action, is $23,788.49. The Salt Springs Bank, on the 6th and on the 9th of June, 1892, recovered judgments against the contractors aggregating in amount the sum of upwards of $38,000, and, in proceedings supplementary to execution, the defendant Boss was appointed receiver of the joint and several property of the contractors. It was found that the indebtedness unpaid to the bank, inclusive of interest, exceeded the sum of $25,000.

The General Term of the Supreme Court has affinned a judgment of the trial court, under which the parties who had filed mechanics’ liens were adjudged to be entitled to be paid the amount of their respective liens in preference to the Salt *327 Springs Bank. The theory upon which this conclusion has been reached is that, under the proper construction of a certain clause in the contract, it was intended by the parties thereto that persons who labored for, or furnished, materials to the contractors should be protected. The clause which received this construction reads as follows : It is also agreed that no payment shall be made hereunder until the said parties of the second part, (meaning the contractors), shall have obtained a certificate from the clerk of Oneida county, showing that at the date of such payment, no liens or claims have been recorded or filed against said premises or building, which are then unsatisfied of record.” Upon the interpretation to be given to this provision must depend the decision of the question involved in this case, whether the amount unpaid upon the contract belonged to the bank fey virtue of its assignment, or whether it belongs to the lienholders to the extent of their liens. In considering that question the learned General Term discarded the suggestion of the respondents, that the amount unpaid upon the contract was not due by reason o£ the provision that no payment should be made until the contractors produced the county clerk’s certificate that no liens were unsatisfied; and, very properly, held that if the assignment to the bank carried the right to the amount unpaid on the contract, it was the duty of the court to set aside the liens, so that the bank could procure the proper certificate and thus obtain the fund to which it was in fact entitled. The opinion held that under the Mechanics’ Lien Law, (Chap. 342, Laws of 1885), the laborer, or material-man, has no preferential right to be paid out of the sum due the contractor, until he files his notice of lien. In the absence of anything to the contrary in the contract and before any notic.e is filed, the contractor may assign to his creditor, in payment of his debt, the whole, or any portion, of the moneys due, or to become due, under the contract and the assignee acquires a preference over a subsequent lienor. This view was based on abundant authority and is indisputable. (Brill v. Tuttle, 81 N. Y. 454; Lauer v. Dunn, 115 ib. 405; McCorkle v. Herrman, 117 ib. 297; Stevens v. Ogden, 130 ib. 182; Beards *328 ley v. Cook, 143 ib. 143.) The principle to be extracted from the eases is that a lienor obtains no greater right to the moneys payable by the owner, than the contractor has and if the latter has assigned to a creditor, pro tanto, the assignee gains a preference over subsequent liens. The court, however, adopting the view that the provision, or clause, of the contract in question prohibited payments, until the county clerk’s certificate was furnished, reached the conclusion that it had for its purpose the protection of the lienors, the laborers and the material-men, as well as the protection of the trustees. The reasoning to this conclusion was made upon the authority of certain cases in this court, which were thought to be controlling, viz.: The Merchants and Traders' National Bank v. The Mayor (97 N. Y. 355), and The Mechanics and Traders' National Bank v. Winant (123 N. Y. 265). ’ These cases related to contracts made by the city of New York in 1875 and 1876. They contained, by direction of an ordinance of the city, this clause: The said party of the second part (meaning the contractor), hereby further agrees that he will furnish said commissioner (meaning the commissioner of public works), with satisfactory evidence that all persons who have done work or furnished materials under this agreement, and who may have given written notice to the said commissioner, * * * have been fully paid or secured such balance. And in case such evidence be not furnished as aforesaid, such amount as may be necessary to meet the claims of the persons aforesaid (meaning the persons who had done work or furnished materials), shall be retained from any moneys due the said party of the second part under this agreement until the liabilities aforesaid shall be fully discharged, or such notice withdrawn.” Those cases held, in effect, that the purpose of that provision was to protect those employed under the contractor. That was its only purpose, and the reason for it was obvious.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Blower Corp. v. James Talcott, Inc.
18 Misc. 2d 1031 (New York Supreme Court, 1959)
City of New York v. Bedford Bar & Grill, Inc.
141 N.E.2d 575 (New York Court of Appeals, 1957)
Century Cement Manufacturing Co. v. Fiore
264 A.D. 475 (Appellate Division of the Supreme Court of New York, 1942)
Rockmore v. Lehman
128 F.2d 564 (Second Circuit, 1942)
Amiesite Construction Corp. v. Luciano Contracting & Building Co.
30 N.E.2d 483 (New York Court of Appeals, 1940)
Vulcan Rail & Construction Co. v. County of Westchester
250 A.D. 212 (Appellate Division of the Supreme Court of New York, 1937)
People v. Continental Casualty Co.
157 Misc. 15 (New York Supreme Court, 1935)
Lee v. William Bailey Corp.
196 N.E. 9 (New York Court of Appeals, 1935)
Lee v. William Bailey Corp.
240 A.D. 65 (Appellate Division of the Supreme Court of New York, 1934)
Arrow Iron Works, Inc. v. Greene
183 N.E. 515 (New York Court of Appeals, 1932)
State Ex Rel. Southern Surety Co. v. Schlesinger
151 N.E. 177 (Ohio Supreme Court, 1926)
Tuttle & Bailey Manufacturing Co. v. General Electric Co.
120 Misc. 87 (New York Supreme Court, 1922)
Merchants National Bank v. Long
113 Misc. 84 (New York Supreme Court, 1920)
Edison Electric Illuminating Co. v. Horace E. Frick Co.
116 N.E. 869 (New York Court of Appeals, 1917)
Federal Heating Co. v. City of Buffalo
99 Misc. 121 (New York Supreme Court, 1917)
Riverside Contracting Co. v. City of New York
113 N.E. 564 (New York Court of Appeals, 1916)
Standard Sand & Gravel Co. v. City of New York
172 A.D. 80 (Appellate Division of the Supreme Court of New York, 1916)
New York County National Bank v. Wood
169 A.D. 817 (Appellate Division of the Supreme Court of New York, 1915)
Kelsey Smith & Co. v. Douglas
165 A.D. 707 (Appellate Division of the Supreme Court of New York, 1915)
Post & McCord v. City of New York
86 Misc. 300 (New York Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
51 N.E. 1033, 157 N.Y. 322, 11 E.H. Smith 322, 1898 N.Y. LEXIS 583, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bates-v-salt-springs-national-bank-ny-1898.