People v. Continental Casualty Co.

157 Misc. 15
New York Supreme Court·Decided May 15, 1935·Published·Cited by 5 cases

Opinion

Staley, J.

This is an action brought by the People of the State of New York against the Continental Casualty Company to recover the sum of $25,643.90, the increased cost of carrying out a contract, the performance of which had been guaranteed by the defendant.

In August, 1929, Maxwell Brothers, Inc., entered into a contract with the State to build a sanitary sewer for the Wassaic State School at Wassaic, N. Y., for the sum of $179,285. The contract was to be completed on or before the 10th day of June, 1930.

The defendant, as surety, executed a bond to the plaintiff in the sum of $86,643, the condition of which was as follows, to wit: “ The condition of this obligation is such that if the said contractor, his, its, their successors, executors, administrators or assigns, or either of them shall faithfully and completely perform said contract, then this obligation to be void, otherwise to remain in full force and effect. The said surety hereby stipulates and agrees that no change, extension, alteration, or revision of the terms of said contract or of the plans and specifications accompanying the same shall in any way effect their, his, or its obligation on this bond.”

The contractor entered upon the performance of the contract, and continued to perform work, until February, 1930, when the contract [17] was abandoned. The State determined to finish the work itself. Thereafter, in May, 1930, the work was readvertised, and a contract to complete it was let to Joseph L. Cuozzo.

Cuozzo bid, to complete the work, the sum of $162,600. Various corrections were made in this bid; no change was made in the unit prices, but some of the extensions were wrong, and one or two items were eliminated as having been completed, including the building of the sewer under the New York Centrail railroad, a matter to be hereafter referred to. After these corrections were made, the amount of the contract was $154,347.50.

The contracts of Maxwell Brothers and of Cuozzo were on the basis of unit prices for estimated quantities.

On the basis of the quantities actually performed, the contract of Maxwell Brothers, Inc., at its unit prices would have amounted to the sum of $186,585.48 if performed by it, instead of the sum of $179,285 on the estimated quantities; and on the same basis the contract of Cuozzo at his unit prices amounted to the sum of $162,575.31 for quantities actually performed, instead of the sum of $154,347.50 on the estimated quantities.

The following provisions were contained in the contract and specifications made by Maxwell Brothers, Inc.:

“ 13. It is further mutually agreed that if in the judgment of the . Department of Mental Hygiene, the work is not being performed according to the contract or for the best interests of the State, the Department of Mental Hygiene shall have power to suspend or stop the work under this contract while it is in progress and complete the same in such manner as will accord with the contract specifications and be for the best interests of the State; or at the option of the Department of Mental Hygiene that the contract may be cancelled and the work readvertised and relet, and in such cases that any excess in the cost of completing the contract beyond the price for which the work was originally awarded shall be charged to and paid by the Contractor. If at any time in the conduct of the work it shall become apparent to the Superintendent of Public Works that any item in the contract will exceed in quantity his estimate by more than fifteen per centum, he shall so certify to the Department of Mental Hygiene, and the Department of Mental Hygiene shall thereupon determine whether the work in excess thereof shall be completed by the Contractor under the terms and at the prices specified in the contract, or whether it shall be done and furnished by the Department of Mental Hygiene, or whether a special contract shall be made for such excess. If the Department of Mental Hygiene shall determine that such work in excess of the Engineer’s [18] estimate shall be completed by the Contractor, he shall complete the same under the terms and at the prices specified herein.
“ 14. It is mutually agreed that the right is reserved to the' Department of Mental Hygiene to suspend or cancel this contract, as above provided, and to continue the work in whole or in part, to protect the work accomplished, to salvage the plant and material, to complete the contract or readvertise and relet the same, or combine any two or more of the foregoing items, as the Department of Mental Hygiene may determine, and that the right is reserved to the Department of Mental Hygiene to enter upon and complete any item of the contract which shall exceed in quantity the Engineer’s estimate by more than fifteen per centum, or to make a special contract for such excess.
15. The Contractor further promises and agrees that all tools, machinery, appliances and materials of every kind which shall be necessary and proper for use upon said work and used or delivered for use upon the same, shall at all times be owned by the Contractor free and clear from all hens or encumbrances of any kind or nature whatsoever, and that if the State by its officers or agents or any of them shall, in the exercise of the rights hereinbefore reserved, assume the execution of the contract or any part thereof or to perform the .said work or any part thereof, that the State may take possession of and use for that purpose all of said tools, machinery, appliances and materials or such thereof as may be necessary without let or hindrance by the Contractor or by the Contractor’s agents, servants or assistants, and that the State shall have the sole and exclusive right to the possession and use of such tools, machinery, appliances and materials as may be necessary for said purposes, and the value of the use thereof, which shall be determined by the Department of Mental Hygiene, shall be applied upon the cost of completing the contract and credited to the Contractor and the State shall not be liable for any depreciation, loss or damages to said tools, machinery, appliances and materials dining said use by the State unless caused by its negligence.”

The specifications for this work which are annexed to the contract and form a part thereto provide as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

People v. Continental Casualty Co., 157 Misc. 15 (N.Y. Super. Ct. 1935).

157 Misc. 15 (People v. Continental Casualty Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Joseph Forcellati
610 F.2d 25 (First Circuit, 1979)
Interstate System, Inc. v. Bev Pac, Inc.
77 Misc. 2d 129 (New York Supreme Court, 1974)
People v. Caldwell-Garvan & Bertini, Inc.
161 Misc. 864 (New York Supreme Court, 1937)